2026 Actual Scaled Agile SSM Dumps, Updated Exam Questions for Guaranteed Pass

SSM (6.0) - SAFe Scrum Master - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorScaled Agile
Exam codeSSM
Exam nameSSM (6.0) - SAFe Scrum Master
Questions in pack92
Last updatedNovember 21, 2026
Related certificationsSAFe Scrum Master

Free practice questions with explanations

Scaled Agile SSM Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
11
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Defining the Scrum Master / Team Coach role

    A Scrum Master on a Agile Release Train (ART) notices that a team's Product Owner regularly accepts stories into the iteration after the Iteration Planning event has started, and the team then complains that they cannot finish committed work. The team members are polite and avoid conflict, so the issue is rarely raised in the retrospective. The Scrum Master has already facilitated two retrospectives without surfacing it. The ART's Release Train Engineer (RTE) wants the team to reach a stable, predictable flow before the next PI. Which action BEST reflects the Scrum Master / Team Coach responsibility for building team capability in this situation?

  2. 2 Question 2 Single choice Introducing Scrum in SAFe

    A large financial services enterprise is moving 12 Agile teams into a single Agile Release Train. Leadership wants to reduce the release cycle for a regulated mobile banking product from quarterly to on-demand, while keeping audit evidence and a controlled release to production. The current pipeline has a manual change-approval gate that takes five days, and the automated test suite runs only nightly. Several teams have asked whether they should adopt Continuous Integration and Continuous Deployment before or after changing their release approval process. Which action should the Scrum Master recommend FIRST to support Release on Demand?

  3. 3 Question 3 Single choice Supporting ART Events

    During PI Planning for a 10-team Agile Release Train, the Business Owners identify that two features depend on a shared API that the Platform team will not finish until the second iteration of the PI. Several teams have already drafted their iteration plans for the first iteration, and the Product Management representative wants to lock the program board before lunch. The ART must produce a confident set of plans and objectives, and the Scrum Master has been asked to facilitate the team breakouts. Which action should the Scrum Master take NEXT, given that the dependency risk is now visible?

  4. 4 Question 4 Single choice Supporting Team Events

    A team of eight developers uses two-week iterations and holds the Iteration Retrospective at the end of each iteration. The team's last three retrospectives produced action items that were never completed, and members now say the sessions feel like a status update. The Scrum Master wants the next retrospective to produce a small number of actionable improvements, and the team has limited time to spare. Which facilitation approach is MOST appropriate for the Scrum Master to apply?

  5. 5 Question 5 Multiple choice Defining the Scrum Master / Team Coach role

    A Scrum Master is coaching a new team that is struggling with self-organisation. The team members look to the Scrum Master to decide task assignments, estimate stories, and resolve conflicts between developers. The Team Coach role in SAFe is intended to help the team grow capability over time. Which TWO actions by the Scrum Master best support the goal of building a self-managing team? (Choose two.)

  6. 6 Question 6 Single choice Introducing Scrum in SAFe

    A SAFe enterprise has organised its Agile teams into an Agile Release Train. One team has delivered consistently for four PIs, but its Scrum Master notices that the team still has a single developer who is the only person able to deploy the service, and two members rarely contribute to code reviews. Leadership asks the Scrum Master to describe how this team could be considered high-performing. Which characteristic of a high-performing team is MOST directly missing?

  7. 7 Question 7 Single choice Supporting ART Events

    An Agile Release Train has completed its final iteration of a Program Increment, and the Inspect and Adapt event is scheduled. The metrics show that two teams have delivered most planned features on time, but the integrated solution has failed system tests twice, and the root cause appears to be inconsistent interface contracts between teams. The ART's Scrum Masters have been asked to prepare for the problem-solving workshop. Which action BEST prepares the Scrum Master to support the Inspect and Adapt event effectively?

  8. 8 Question 8 Single choice Supporting Team Events

    A team is preparing for its Iteration Planning event. The Product Owner has ordered the backlog, but about a third of the top stories have acceptance criteria that are unclear, and two stories depend on decisions by a team in another part of the ART. The team needs to commit to a realistic iteration goal and has only a short timebox for planning. The Scrum Master is considering whether to ask the team to commit to all top-ordered stories anyway. Which action should the Scrum Master take to support a sound commitment?

  9. 9 Question 9 Multiple choice Supporting Team Events

    A Scrum Master is facilitating Team Sync and Backlog Refinement for a team that has several dependencies on other teams in the Agile Release Train. Team members complain that these meetings take too long, and the Product Owner says refinement is being pulled into the iteration. The Scrum Master wants both events to add value without becoming status meetings. Which TWO actions best support that goal? (Choose two.)

  10. 10 Question 10 Single choice Supporting ART Events

    An Agile Release Train is planning its IP Iteration before the Inspect and Adapt event for a Program Increment. The ART has a shared CI/CD pipeline that is unstable, and several teams have deferred their PI objectives to the IP iteration. Management wants the IP iteration to be used as a buffer for recovering from these deferrals, but the Scrum Master is concerned that the team will be asked to add new features. Which statement correctly describes how the IP Iteration should be used?

  11. 11 Question 11 Single choice Defining the Scrum Master / Team Coach role

    A Scrum Master is coaching a team whose Product Owner is frequently absent and has delegated backlog decisions to developers, who now have conflicting ideas about priorities. The team asks the Scrum Master to make the final ordering decision so that work can continue. The Scrum Master believes the team needs to learn to work through prioritisation conflicts with the Product Owner, not avoid them. Which response BEST reflects effective team coaching?

These are 11 of the 92 questions in the full SSM pack.

Get All 92 Questions

Get all 92 questions & answers

719 Satisfied customers
94.8% Pass rate feedback
82.8% Said questions matched
97% Found material helpful

Full access options for Scaled Agile SSM

Self-study

PDF Version

$40.00 $20.00
  • 92 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 92 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the SSM Exam (SSM (6.0) - SAFe Scrum Master) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed