Exam Information
Free practice questions with explanations
Pure Storage FlashArray-Implementation-Specialist Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 12
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Pre-Installation/Upgrade
A financial services firm is replacing a three-node VMware cluster's storage with a new FlashArray//X70 in its primary data centre. The site has a single 208V 30A PDU circuit per rack and a fixed 10GbE iSCSI fabric. The network team reports that the existing switches are at 90 percent port utilisation and cannot add 25GbE uplinks until a change window in six weeks. The project lead wants to start cabling and power-on next week to meet the migration deadline. Which action should the implementation specialist take FIRST during pre-installation planning?
Correct Answer: CExplanationPower and cooling are verified before racking because the rack circuit and airflow budget constrain whether the chassis can be powered at all, and this is the earliest gating item in site preparation. Cabling to the existing switches ignores the port and bandwidth limits the network team reported, so it would not meet the design. Upgrading Purity immediately is an upgrade activity that belongs after installation and validation, not a precondition. Asking to move the deadline bypasses planning work that can be done now, since the power and cabling review does not depend on the switch replacement.
-
2 Question 2 Single choice Installation
A healthcare provider is installing a new FlashArray//XL170 with two controllers and two expansion shelves. The installation engineer has racked the chassis and connected power. During the first physical check, the engineer notices that the two shelves were cabled into the array's back-end SAS ports in a pattern that leaves one shelf with a single path, and the Purity GUI already shows a redundancy warning. The go-live is scheduled for the evening. Which action should the engineer take NEXT?
Correct Answer: BExplanationBack-end cabling must provide redundant paths to every shelf, and a single-path shelf is a fault that should be corrected before the array is accepted into service. Correcting the cabling to the documented layout and confirming dual paths on each shelf addresses the root cause. Deferring it until after go-live leaves the array exposed during its most sensitive period. Silencing the health warning hides a real redundancy gap, and moving shelves between controller pairs is not a supported way to balance a misdesigned back-end.
-
3 Question 3 Multiple choice Post-Installation/Upgrade
A logistics company has completed the installation of a FlashArray//X90 and connected it to two VMware ESXi clusters over redundant Fibre Channel fabrics. The implementation specialist must confirm functionality before handover. The customer's policy requires that the array be proven to tolerate a loss of one fabric without an outage to any LUN. Which TWO validation activities should the specialist perform to meet this requirement? (Choose two.)
Correct Answer: B, DExplanationConfirming multipath visibility from every host to every volume across both fabrics establishes that the redundancy exists in the configuration. A controlled fabric failure test with continued I/O proves the requirement is actually met rather than assumed. A general health check does not show per-host path loss tolerance, and checking driver versions, while useful, does not demonstrate fabric-loss tolerance. Mounting a volume through only the primary fabric tests the wrong condition and proves nothing about survival of a fabric failure.
-
4 Question 4 Single choice Upgrades
A government agency runs a FlashArray//X50 replicating asynchronously to a second site using ActiveCluster-free protection groups. The agency's change board requires that the Purity upgrade be performed with zero planned downtime for production volumes, and it has a policy that no upgrade may proceed unless the array can be rolled back to its prior release. The implementation specialist has the upgrade package staged. Which action is the MOST appropriate before starting the upgrade?
Correct Answer: DExplanationThe pre-upgrade health check and compatibility review against the current host and replication setup confirm the upgrade can be performed non-disruptively and identify blockers, while confirming the rollback path satisfies the change board's policy. Taking snapshots and accepting replication disruption conflicts with the zero-downtime and replication-continuity needs. Deleting protection groups would break the replication design and violate the protection requirement. Upgrading the secondary first ignores the supported ordering and compatibility considerations between replicating arrays.
-
5 Question 5 Single choice Installation
A retail chain is installing a FlashArray//X20 at a remote store that lacks an on-site storage engineer. The site has a flat management network with no DHCP scope reserved for storage. The remote installer must bring the array into the central management system without a laptop being connected directly to each controller. The corporate security standard prohibits enabling unnecessary services on the management interface. Which approach BEST satisfies the requirements for initial setup?
Correct Answer: DExplanationInitial configuration on a FlashArray is performed by assigning management addressing directly to the controllers, typically from a temporary connection, and the temporary access is removed once the array is registered, which satisfies the security standard. Enabling an HTTP service on the management interface conflicts with the policy on unnecessary services. Using the replication interface mixes traffic roles and is not a recommended management path. Relying on DHCP discovery is not guaranteed on a network with no reserved scope and does not meet the requirement for a reliable first connection.
-
6 Question 6 Single choice Upgrades
An insurance company has a FlashArray//X70 running an older Purity release and must upgrade it before a compliance audit in three weeks. The array hosts Oracle databases whose vendor certifies only a subset of Purity releases with its current patch level. The array also connects to a SAN switch fabric whose firmware is scheduled for replacement in the next quarter. The change team asks which constraint should drive the target release selection. Which factor should the implementation specialist prioritise?
Correct Answer: DExplanationThe target Purity release has to be chosen from those supported by the interoperability guidance for the actual host OS, HBA drivers and database stack, and the planned fabric firmware change affects the upgrade sequencing. The newest release is not automatically compatible with certified application versions, so picking it blindly is risky. Choosing by reboot count ignores support, and matching the secondary site's release ignores host certification as well.
-
7 Question 7 Multiple choice Pre-Installation/Upgrade
A university is consolidating several legacy storage arrays onto a new FlashArray//X70 with two controllers. The data centre is on a tight budget and the IT team wants to reuse existing Fibre Channel HBAs and switches where possible. The lead must complete pre-installation planning and identify the constraints that must be validated before hardware is ordered or installed. Which TWO actions are required during planning to avoid an unsupported design? (Choose two.)
Correct Answer: B, CExplanationReusing HBAs is only viable when their model, firmware and driver are on the supported interoperability list for the chosen Purity release, so this has to be validated during planning. Zoning and port speed must line up with the array's front-end ports and host HBAs, otherwise the design either fails to connect or runs at unintended speeds. Assuming switch compatibility, ordering before checking support, and copying legacy masking designs are all planning shortcuts that create unsupported or unworkable configurations.
-
8 Question 8 Single choice Post-Installation/Upgrade
A manufacturer completed a FlashArray installation and its host team reports intermittent read latency spikes on a SQL Server cluster during business hours. The implementation specialist must determine whether the post-installation configuration is correct before escalating. The team confirms that the hosts use the vendor-recommended multipath settings and that all volumes are visible on all paths. Which check is the MOST appropriate next step to validate the post-installation configuration?
Correct Answer: CExplanationReviewing Purity's performance data for the affected volumes during the reported window shows whether latency originates on the array or on the host side, and it confirms the configuration against the observed workload. Resizing volumes is not a diagnosis of latency. Disabling multipathing would remove redundancy and risks an outage, and rebooting controllers during business hours is a disruptive action that should never be used as a diagnostic step.
-
9 Question 9 Single choice Installation
A pharmaceutical firm is installing a FlashArray//X50 that must meet a data-at-rest encryption requirement. Its security policy demands that encryption keys be managed by an external key manager and that the array not store keys locally in a form accessible without the external service. The installation team is about to complete the initial system setup. Which action BEST meets the policy during installation?
Correct Answer: AExplanationThe policy requires that keys be held externally, so the external key manager integration must be in place and tested before any production data is stored, otherwise data could be written under keys the policy does not allow. Using the built-in self-encryption with local key storage contradicts the stated requirement. Deferring the integration until after release leaves data unprotected under a non-compliant design, and relying on data centre physical security is not a substitute for the encryption requirement.
-
10 Question 10 Multiple choice Upgrades
A telecommunications provider is planning a Purity upgrade on a FlashArray//XL170 that replicates synchronously to a metro-area partner site. The NOC has a runbook that states an upgrade must not begin until all risks to replication and host connectivity are reviewed. The implementation specialist must choose the actions that reduce the risk of a broken replication state or an outage during the upgrade. Which TWO actions should be included in the plan? (Choose two.)
Correct Answer: B, DExplanationA healthy replication baseline with no backlog ensures a clean starting point and makes it easier to recover if the upgrade disturbs replication. Confirming multipathing on every host means controller reboots are absorbed without application outages. Upgrading both synchronous arrays at once removes the controlled ordering that protects the pair, pausing all I/O causes an outage, and disabling replication breaks the protection the business relies on.
-
11 Question 11 Single choice Post-Installation/Upgrade
A media company completed a FlashArray installation and a subsequent Purity upgrade. Two weeks later, the storage team sees that the volumes that were presented before the upgrade are still visible, but a newly provisioned volume for a Linux host does not appear on the host. The host can see the array on its HBA ports and the zoning is correct. The company's governance policy requires that every new host be validated in the change record before production use. Which validation step should the specialist perform FIRST?
Correct Answer: CExplanationBecause the host can see the array and zoning is correct, the most likely gap is the host object definition or the volume connection on the array, so validating that mapping is the correct first step and is also recorded for governance. Reinstalling the operating system is disruptive and not diagnostic. Deleting volumes would destroy data and is unnecessary. Reverting the array release is a major change that is not justified without first checking the host-to-volume mapping.
-
12 Question 12 Single choice Upgrades
A regional bank must upgrade the Purity release on a FlashArray//X70 that supports a trading application. The bank's change policy requires that the upgrade path be justified against the array's current release and that the change include a documented rollback decision point. The specialist is comparing two options: an upgrade that jumps directly to the target release, and a staged path through an intermediate release that the vendor documents as a supported upgrade step. Which approach is MOST appropriate?
Correct Answer: DExplanationThe vendor's documented upgrade path defines which releases can be moved between safely, so it is the authoritative basis for the change and must be followed exactly, including any required intermediate step. Defining the rollback decision point satisfies the bank's change policy. Assuming a direct jump is always safe ignores the documented path, downgrading to an older release introduces unnecessary risk, and treating the upgrade as irreversible without a plan fails the governance requirement.
These are 12 of the 234 questions in the full FlashArray-Implementation-Specialist pack.
Get All 234 QuestionsGet all 234 questions & answers
Full access options for Pure Storage FlashArray-Implementation-Specialist
Self-study
PDF Version
- 234 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 234 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 234 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the FlashArray-Implementation-Specialist Exam (Pure Storage Certified FlashArray Implementation Specialist) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.