Exam Information
Free practice questions with explanations
NCARB Project-Planning-Design Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 10
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Building Systems, Materials, & Assemblies
A three-story clinic is being designed in a coastal city with high humidity and salt-laden air. The owner requires a roof assembly with a service life of at least 30 years and a low maintenance regime, and the budget cannot support a fully adhered membrane with embedded sensors. The structure is a steel deck with lightweight concrete topping. The design team must select a roofing system that resists moisture intrusion, provides adequate drainage for a flat roof, and meets the insulation values required by the energy code. Mechanical rooftop equipment will be placed on curbs over the roof. Which roof assembly strategy best meets these requirements?
Correct Answer: DExplanationA mechanically attached single-ply membrane over polyisocyanurate, with tapered insulation feeding interior drains, gives a long-lived, low-maintenance assembly that drains reliably and meets insulation demand, and it avoids the sensor-embedded adhered system the budget excludes. Fully adhered modified bitumen with exterior scuppers is durable but its gravel topping and parapet outlets add upkeep in salt air. Built-up asphalt over expanded polystyrene lacks the compressive strength and slope management a flat roof needs and drains poorly from a single centre point. Spray foam relies on the steel deck's inherent slope, which is not a drainage strategy for a flat roof.
-
2 Question 2 Single choice Codes & Regulations
A two-storey mixed-use building is planned on a corner lot in a district where the zoning code limits height to 12 metres and requires a 3-metre setback along any street frontage. The building is classified as Group B occupancy on the ground floor and Group R-2 residential above, and the local jurisdiction adopts the model building code with amendments. The design team wants a 12-metre high ground floor with a rooftop amenity structure that exceeds the height limit by 1.8 metres. The project team asks which path best resolves the conflict while keeping the design viable. Which action is the BEST first step?
Correct Answer: DExplanationBecause the rooftop structure exceeds a zoning height limit, the zoning ordinance governs and the proper route is a variance request that establishes hardship. Reclassifying occupancy would be an unsupported change to meet a zoning problem and would not alter zoning height. Relabelling the pergola as exempt ignores that the enclosed amenity structure is measured under the zoning definition. Increasing the setback does not change the height limit at all, so it cannot resolve the conflict.
-
3 Question 3 Single choice Environmental Conditions & Context
A developer plans a single-family residential development on a sloped 2-hectare parcel in a temperate climate. The site contains a mature oak grove on the north-east quadrant, a seasonal stream along the south boundary, and a neighbouring property with a tall commercial building to the west that will shade the lot in winter afternoons. The program requires solar access for photovoltaic panels on at least half of the lots, and the local stormwater rules require infiltration of the first 25 millimetres of rainfall on site. The design team is establishing lot and building locations. Which siting decision best integrates the site analysis?
Correct Answer: DExplanationSiting along an east-west axis on the south-facing slope maximises solar gain for panels and reduces winter shading from the western building, while keeping footprints out of oak root zones protects the trees. The stream buffer also doubles as a location for the infiltration swales that the first-flush rule requires. The flat-north option bypasses infiltration, violating the stormwater requirement. Placing buildings under the canopy and clustering against the shading western building both undermine the solar access requirement.
-
4 Question 4 Single choice Project Costs & Budgeting
A library renovation has a fixed capital budget and must evaluate two design alternatives for its exterior envelope. Alternative One uses a triple-glazed curtain wall with a higher installed cost but a lower projected annual heating and cooling load. Alternative Two uses a double-glazed storefront with a lower first cost but higher energy use and a shorter maintenance cycle. The owner has stated that the building must remain within the budget at completion and that the owner is willing to accept a longer simple payback period only if the operating savings are documented. The owner also needs the facility to be operational within 14 months. Which evaluation approach is most appropriate to compare these alternatives?
Correct Answer: DExplanationA life-cycle cost comparison captures the trade-off between higher first cost and operating savings, and the owner specifically asked for documented operating savings, so it fits the request. The fixed budget and 14-month schedule are then checked against the preferred option. Ignoring operating costs conflicts with the documented-savings requirement. Choosing the costlier curtain wall because it seems durable is unsupported without a cost basis. Comparing energy alone wrongly assumes identical maintenance, which the stem indicates is not true.
-
5 Question 5 Single choice Project Integration of Program & Systems
An architect is configuring a 40,000-square-foot laboratory building for a research client. The program requires a 24-hour exhaust system for fume hoods, vibration-sensitive instrument rooms located away from mechanical equipment, and a clear vertical separation between the lab zone and the office zone. The site restricts building height to four storeys, and the client insists on a single central mechanical floor. The structural engineer notes that the lab floors need long clear spans to accommodate flexible bench layouts. Which building configuration best integrates the program and systems?
Correct Answer: DExplanationPutting the single central mechanical floor between the lab and office zones gives the required vertical separation and serves both zones efficiently, while exhaust risers reach the roof for dispersion. Locating instrument rooms on the lowest storey keeps them far from vibration sources, and it respects the long-span structural requirement by keeping the lab floors clear. Placing instruments next to chillers creates vibration and noise conflicts. Discharging exhaust near air intakes is a recognised hazard, and an annex contradicts the single-mechanical-floor requirement.
-
6 Question 6 Multiple choice Building Systems, Materials, & Assemblies
A school gymnasium with a 12-metre clear span needs a roof structure that will carry rooftop solar panels, provide a long-span column-free interior, and keep the sound from rain impact within acceptable levels for classroom adjacency. The budget excludes exposed steel trusses with fireproofing. Which TWO assembly or system decisions best meet these requirements? (Choose two.)
Correct Answer: A, CExplanationGlulam beams with cross-laminated timber panels deliver a 12-metre column-free span with a structure that can carry panel loads and avoids the exposed steel fireproofing the budget excludes. The suspended acoustic ceiling addresses rain impact and reverberation for the adjacent classrooms, which the bare roof decks cannot manage. Steel joists with metal deck and insulation are structurally workable but the deck gives poor sound control. Exposed open web joists fail the acoustic requirement, and concrete topping over corrugated deck lacks a sound-absorptive layer.
-
7 Question 7 Single choice Environmental Conditions & Context
A design team is preparing a passive-design strategy for a single-storey community centre in a hot, arid climate. The site analysis indicates strong prevailing winds from the south-west, intense afternoon solar exposure on the west façade, and a nearby arterial road generating significant noise on the north side. The brief calls for natural ventilation in the main hall and daylight without glare. Which combination of design responses is most appropriate?
Correct Answer: DExplanationDeep overhangs or vegetation on the west glazing control afternoon heat gain while preserving daylight, and openings aligned to south-west winds with high-level placement support stack and cross ventilation. Placing service rooms on the noisy north edge uses them as an acoustic buffer. Maximising west glazing worsens overheating, so it contradicts the climate analysis. Sealing the wind-facing side and depending on mechanical cooling ignores the passive requirement, and opening the north façade to the road brings in noise.
-
8 Question 8 Single choice Codes & Regulations
A seven-storey apartment building is being designed under the model building code. The team plans to use a combustible mass timber structure with exposed ceilings in the corridors, and the occupancy is R-2. The jurisdiction has adopted sprinkler and fire-resistance amendments. The architect must integrate the requirements so that the design is compliant before schematic design is complete. Which approach best integrates the code requirements?
Correct Answer: DExplanationMass timber construction types have specific allowable heights and area limits, and fire-resistance ratings for the structure must be established alongside sprinkler coverage and interior finish restrictions in exit corridors. Treating sprinklers as removing structural fire-resistance requirements is incorrect, since sprinklers modify but do not eliminate them. Reclassifying an R-2 building to Group B to avoid requirements is improper, as occupancy must reflect actual use. Deferring interior finish rules to permit review risks major redesign because finish classes affect corridor design early.
-
9 Question 9 Single choice Project Integration of Program & Systems
A hospital outpatient wing has a program requiring 18 exam rooms, a radiology suite with shielded walls, and a pharmacy that must be accessible from the main lobby without crossing the clinical circulation. The site allows two storeys and a limited footprint. The owner requires the radiology suite to be on the ground floor for patient access and the pharmacy to be near the entry. The mechanical engineer reports that the imaging equipment needs a dedicated chilled water loop and a shielded electrical feed. Which planning arrangement best integrates the program and systems?
Correct Answer: DExplanationKeeping radiology on the ground floor satisfies access and allows its dedicated chilled water and shielded electrical service to be grouped in an adjacent zone, which shortens runs and separates the heavy equipment from patient corridors. Placing the pharmacy beside the entry meets the lobby access requirement without crossing clinical circulation. Putting radiology upstairs breaks the owner's access requirement, and locating the pharmacy in the basement fails accessibility. Routing chilled water beneath patient corridors creates noise and maintenance conflicts.
-
10 Question 10 Single choice Building Systems, Materials, & Assemblies
A data processing centre requires a raised access floor, a dedicated fire suppression system compatible with energised electronics, and power distribution that can be extended without shutdown. The owner's security requirement prohibits any overhead water piping above server aisles. The mechanical team proposes a chilled-water perimeter cooling system with an underfloor air distribution plenum. Which fire suppression approach best satisfies both the equipment protection and the security constraint?
Correct Answer: BExplanationA clean-agent gas system provides fire suppression without water, which suits energised electronics and satisfies the prohibition on overhead water piping above the server aisles. Wet pipe sprinklers place water directly over the aisles, breaking the security constraint. Pre-action and deluge systems still install overhead water piping in the protected zone, so they fail the same requirement even though they reduce accidental discharge.
These are 10 of the 100 questions in the full Project-Planning-Design pack.
Get All 100 QuestionsGet all 100 questions & answers
Full access options for NCARB Project-Planning-Design
Self-study
PDF Version
- 100 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 100 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 100 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the Project-Planning-Design Exam (ARE 5.0 Project Planning & Design (PPD)) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.