Exam Information
Free practice questions with explanations
NCARB Project-Management Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 13
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Contracts
An architect is reviewing the owner/architect agreement for a 4-story medical office building. The owner has requested that the architect's basic services fee be reduced because the owner's project manager will handle all coordination between the consultants and the contractor. The architect's firm wants to keep its standard-of-care obligations intact and avoid unpaid liability exposure. The owner also wants the architect to take responsibility for a geotechnical report the owner's own staff procured directly from a lab. Which action should the architect take FIRST before signing the revised agreement?
Correct Answer: BExplanationBefore signing, the architect has to verify that the owner/architect agreement describes services that match what the architect will really do, including coordination and responsibility for owner-procured information. Confirming the basic services scope and what is excluded protects the standard of care and prevents uncompensated work. Accepting a lower fee with a liability cap ignores that the duties remain and the cap may be unenforceable or unfavourable. Deferring the geotechnical responsibility to a change order leaves an unresolved risk at signing. Deleting coordination from consultant agreements would break the architect's integration obligations and is not a sound contract practice.
-
2 Question 2 Single choice Contracts
An architect's firm has a consultant agreement with a structural engineer for a mixed-use project. The owner's agreement with the architect specifies that the architect must provide a fully coordinated set of construction documents by a fixed milestone. The structural engineer's proposal states a delivery date two weeks after that milestone and limits its services to the design of the structural system only, excluding review of shop drawings. The architect wants to integrate the consultant's work without exposing the firm to a pass-through risk it cannot control. What is the best course of action?
Correct Answer: BExplanationThe architect must align the consultant agreement with the owner/architect agreement so that the consultant's schedule, scope, and exclusions do not leave the architect liable for gaps it cannot cover. Matching the delivery date to the owner milestone and clarifying the exclusions achieves this. Relying on force majeure is not a valid excuse for ordinary consultant delay. Changing the owner agreement to suit the consultant reverses the proper hierarchy of obligations. Requiring uncompensated shop drawing review is an unpriced expansion of scope that the consultant will not accept and that creates unbudgeted obligations.
-
3 Question 3 Single choice Contracts
An architect is preparing to verify the owner/contractor agreement for a school renovation delivered under a stipulated sum contract. The owner's draft agreement references the architect's construction documents but attaches an earlier set of drawings dated before the final permit set was issued. The owner asks the architect to confirm that the agreement conforms to the project documents. The contract administration obligations are to be performed by the architect under the owner/architect agreement. Which action best verifies adherence and protects the project record?
Correct Answer: DExplanationThe owner/contractor agreement must incorporate the correct, issued construction documents, and the architect is responsible for verifying that the contract documents match the permit set. Comparing the attached set with the issued drawings and requesting correction before execution closes the gap. Reviewing only general conditions ignores that incorporated drawings govern the work. Relying on the contractor to find discrepancies shifts an architect responsibility onto others. Substituting sketches for issued drawings would create an unauthorised and unpermitted contract basis.
-
4 Question 4 Single choice Integration of Building Materials & Systems
A design firm is preparing a quality control review of the construction documents for a 12-story laboratory building before the 90 percent submission. The project team has recently changed, and a new drafter applied an outdated fire-resistance rating detail from a previous project. The jurisdiction adopted a newer model code edition that changed the required rating for the corridor walls. The firm's quality management procedure requires review checklists tied to applicable codes. What is the most effective quality control step to reduce this risk going forward?
Correct Answer: DExplanationA code-compliance checklist tied to the adopted edition and local amendments gives a documented, repeatable control that catches outdated details such as a superseded fire-rating requirement. Signed reviewer sign-off at each milestone also builds accountability into the quality management procedure. Relying on the contractor shifts responsibility the architect owns. The building official's review is a regulatory check, not a substitute for the firm's own quality control. Using the previous project's code edition would perpetuate the error.
-
5 Question 5 Multiple choice Integration of Building Materials & Systems
A firm is developing procedures to reduce liability during the design phase of a hospital expansion. The project includes a new emergency generator, sprinkler extensions, and stair pressurisation systems that must comply with the adopted building and life safety codes. Which TWO procedures best reduce risk and support the standard of care? (Choose two.)
Correct Answer: A, DExplanationDocumented cross-discipline coordination reviews catch conflicts between code-driven systems such as stair pressurisation and sprinkler extensions before they propagate into documents. Maintaining a log of code interpretations and jurisdictional comments reviewed at each milestone creates traceability and reduces recurring deficiencies. Accepting consultant calculations without review abandons the architect's coordination responsibility. Deferring life safety review to construction administration leaves errors undetected until late and costly. Letting the contractor select sprinkler layout without design review bypasses the design integrity the architect must maintain.
-
6 Question 6 Single choice Integration of Building Materials & Systems
During construction documentation for a cold-storage facility, the design team evaluates a proposed roofing assembly. The owner's specification requires a manufacturer's warranty, and the design team has been asked to maintain the integrity of the approved design objectives for thermal performance and vapour control. A value-engineering proposal from the contractor substitutes a different insulation board that has a lower R-value per inch but is thinner, and the contractor asserts it is equivalent. What is the best management action for the design process?
Correct Answer: DExplanationMaintaining design integrity means evaluating a proposed substitution against the approved thermal and vapour control criteria and the warranty requirement, then documenting the result. This is the controlled path for value-engineering proposals. Accepting based on cost and a claim of equivalence skips the verification the design team owes the owner. Automatically rejecting all substitutions is not a rule of practice and may forfeit a valid saving. Verbal approval without documentation creates an unrecorded change to the design basis.
-
7 Question 7 Single choice Project Execution
A mid-sized firm is administering a $14 million office fit-out under a construction manager at risk delivery method. Midway through construction documents, the owner requests additional conference rooms and a new executive suite. The owner's budget was set at a fixed figure in the owner/architect agreement, and the contract documents show the project is already 6 percent over the target construction cost. The owner asks the architect to proceed with the new spaces immediately and to sort out the budget later. What should the architect do FIRST?
Correct Answer: DExplanationA scope change that already places the project over budget requires a written assessment of cost and schedule impacts and documented owner authorization before design or construction proceeds. This keeps the budget compliance and the scope baseline defensible. Quietly reducing finishes without disclosure undermines the owner's informed decision. Having the CM price work without owner review bypasses the owner's approval authority. Designing first and reconciling later creates scope creep with unapproved cost exposure.
-
8 Question 8 Single choice Project Execution
An architect is administering a multi-building campus project delivered under design-bid-build. The owner's project team has issued four separate written requests over six months that each add a small, reasonable-seeming item to the scope, such as an additional exterior light, a revised door hardware group, and an extra parking stall. None of these were recorded as formal changes, and the consultant fees and schedule have not been adjusted. The owner now asks why the project is behind schedule. Which action best addresses this situation?
Correct Answer: DExplanationThe accumulated, unrecorded additions are classic scope creep, and the fix is a formal log that tracks each addition against the baseline scope, its cost and schedule impact, and whether it falls under basic or additional services. Presenting that log lets the owner make an informed decision on fees and schedule. Absorbing the additions erodes profitability and hides the true impact. Blaming the contractor misattributes a problem created by the scope drift. Stopping all work is disproportionate and does not address the documentation gap.
-
9 Question 9 Single choice Project Execution
An architectural firm is preparing documentation for a public library project to be procured through a design-build delivery method. The owner's bid documents must allow the design-build contractor to develop the detailed design, while the owner retains a performance-based program. The authority having jurisdiction requires submission of a building permit before any construction, and the owner wants the design-builder to obtain permits. The firm's draft performance criteria currently specify exact wall assembly details. Which revision best supports the specified delivery method and the permit requirement?
Correct Answer: DExplanationIn design-build, the owner's documents set performance criteria rather than prescriptive construction details, so the design-builder can develop the detailed design. Writing the requirements as thermal, fire, and structural outcomes keeps the documents aligned with that delivery method while still supporting permit review. Keeping exact details defeats the delivery method and creates a conflict with the design-builder's responsibility. Removing the permit requirement is not permitted by the authority having jurisdiction. Assigning the permit to the owner contradicts the stated delivery responsibilities.
-
10 Question 10 Single choice Project Work Planning
A project manager is developing a work plan for a 40,000 square foot community clinic with a fixed completion date tied to a grant deadline. The team includes two internal designers, one structural consultant, one MEP consultant, and a civil consultant whose availability is limited to three days per week. The structural engineer's deliverables depend on architectural floor plans, and the MEP consultant needs structural openings before finalizing ductwork. The schedule must show a critical path that meets the grant deadline. Which schedule element best supports this requirement?
Correct Answer: DExplanationA logic-linked schedule captures the real hand-offs between architecture, structure, and MEP, and computing the critical path against the grant date shows whether the plan is achievable and where float is lost. Separate task lists without dependency links hide the sequencing risks that drive the deadline. A single milestone gives no control over interim progress. Front-loading all consultant work ignores the stated availability limits and the actual dependency on architectural plans.
-
11 Question 11 Single choice Project Work Planning
A firm has been awarded a 6-month renovation of a historic courthouse. The project includes a phased occupancy plan, requiring the building to remain partially occupied, and the authority having jurisdiction requires a separate review for fire-separation work in each phase. The owner's facilities director has asked for weekly updates, while the structural engineer and the general contractor communicate through their own weekly meeting. The project manager needs a communication plan that prevents missed decisions affecting phased occupancy. Which approach is most appropriate?
Correct Answer: DExplanationA consolidated communication matrix with defined audiences, content, frequency, and owners, plus shared decision logs, ensures phased occupancy decisions and fire-separation reviews reach every party in time. Allowing consultants to bypass the project manager fragments decisions and risks conflicting direction. Delaying updates until completion leaves the owner unaware of decisions affecting phased occupancy. Routing everything through the contractor filters the owner's information and ignores the consultants' direct responsibilities.
-
12 Question 12 Single choice Resource Management
An architecture firm is assembling a team for a 220,000 square foot mixed-use project with a tight schedule and a requirement that the firm's internal staff have experience with the adopted energy code. The principal wants to assign a junior designer who has strong Revit skills but no code experience, and a senior technical staff member who is currently allocated 80 percent to another project through the same quarter. Which criterion should drive the team composition decision?
Correct Answer: DExplanationTeam composition should be driven by the competencies the deliverables demand, such as energy code expertise for this project, and by a realistic confirmation of each person's time commitment. Assigning based on a single skill or seniority ignores the stated code requirement and the existing workload. Assigning the senior staff member fully when already 80 percent committed creates an unrealistic plan. Outsourcing all technical roles is an unjustified cost and control decision not supported by the constraints.
-
13 Question 13 Single choice Resource Management
A firm is allocating resources across three concurrent projects, each with a different phase schedule. The construction documents phase on Project A is consuming 60 percent of available drafting hours, and Project B's design development milestone falls in the same two weeks. The firm wants to manage its staff's time so that no individual exceeds sustainable utilisation, and the principal insists on maintaining quality reviews for all milestones. Which resource management method best addresses this situation?
Correct Answer: DExplanationA resource loading plan that tracks weekly hours per person by project and phase makes overallocation visible and allows leveling and sequencing of quality reviews around the milestone dates. Independent assignment by each project manager creates the conflicts in the first place. Dropping quality reviews breaches the firm's standard of care and the principal's requirement. Deferring Project B ignores its committed milestone and the stated constraint to keep reviews in place.
These are 13 of the 79 questions in the full Project-Management pack.
Get All 79 QuestionsGet all 79 questions & answers
Full access options for NCARB Project-Management
Self-study
PDF Version
- 79 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 79 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 79 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the Project-Management Exam (ARE 5.0 Project Management (PjM) Exam) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.