2026 Actual NCARB Project-Management Dumps, Updated Exam Questions for Guaranteed Pass

ARE 5.0 Project Management (PjM) Exam - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorNCARB
Exam codeProject-Management
Exam nameARE 5.0 Project Management (PjM) Exam
Questions in pack79
Last updatedNovember 21, 2026
Related certificationsNCARB Certifications

Free practice questions with explanations

NCARB Project-Management Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
13
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Contracts

    An architect is reviewing the owner/architect agreement for a 4-story medical office building. The owner has requested that the architect's basic services fee be reduced because the owner's project manager will handle all coordination between the consultants and the contractor. The architect's firm wants to keep its standard-of-care obligations intact and avoid unpaid liability exposure. The owner also wants the architect to take responsibility for a geotechnical report the owner's own staff procured directly from a lab. Which action should the architect take FIRST before signing the revised agreement?

  2. 2 Question 2 Single choice Contracts

    An architect's firm has a consultant agreement with a structural engineer for a mixed-use project. The owner's agreement with the architect specifies that the architect must provide a fully coordinated set of construction documents by a fixed milestone. The structural engineer's proposal states a delivery date two weeks after that milestone and limits its services to the design of the structural system only, excluding review of shop drawings. The architect wants to integrate the consultant's work without exposing the firm to a pass-through risk it cannot control. What is the best course of action?

  3. 3 Question 3 Single choice Contracts

    An architect is preparing to verify the owner/contractor agreement for a school renovation delivered under a stipulated sum contract. The owner's draft agreement references the architect's construction documents but attaches an earlier set of drawings dated before the final permit set was issued. The owner asks the architect to confirm that the agreement conforms to the project documents. The contract administration obligations are to be performed by the architect under the owner/architect agreement. Which action best verifies adherence and protects the project record?

  4. 4 Question 4 Single choice Integration of Building Materials & Systems

    A design firm is preparing a quality control review of the construction documents for a 12-story laboratory building before the 90 percent submission. The project team has recently changed, and a new drafter applied an outdated fire-resistance rating detail from a previous project. The jurisdiction adopted a newer model code edition that changed the required rating for the corridor walls. The firm's quality management procedure requires review checklists tied to applicable codes. What is the most effective quality control step to reduce this risk going forward?

  5. 5 Question 5 Multiple choice Integration of Building Materials & Systems

    A firm is developing procedures to reduce liability during the design phase of a hospital expansion. The project includes a new emergency generator, sprinkler extensions, and stair pressurisation systems that must comply with the adopted building and life safety codes. Which TWO procedures best reduce risk and support the standard of care? (Choose two.)

  6. 6 Question 6 Single choice Integration of Building Materials & Systems

    During construction documentation for a cold-storage facility, the design team evaluates a proposed roofing assembly. The owner's specification requires a manufacturer's warranty, and the design team has been asked to maintain the integrity of the approved design objectives for thermal performance and vapour control. A value-engineering proposal from the contractor substitutes a different insulation board that has a lower R-value per inch but is thinner, and the contractor asserts it is equivalent. What is the best management action for the design process?

  7. 7 Question 7 Single choice Project Execution

    A mid-sized firm is administering a $14 million office fit-out under a construction manager at risk delivery method. Midway through construction documents, the owner requests additional conference rooms and a new executive suite. The owner's budget was set at a fixed figure in the owner/architect agreement, and the contract documents show the project is already 6 percent over the target construction cost. The owner asks the architect to proceed with the new spaces immediately and to sort out the budget later. What should the architect do FIRST?

  8. 8 Question 8 Single choice Project Execution

    An architect is administering a multi-building campus project delivered under design-bid-build. The owner's project team has issued four separate written requests over six months that each add a small, reasonable-seeming item to the scope, such as an additional exterior light, a revised door hardware group, and an extra parking stall. None of these were recorded as formal changes, and the consultant fees and schedule have not been adjusted. The owner now asks why the project is behind schedule. Which action best addresses this situation?

  9. 9 Question 9 Single choice Project Execution

    An architectural firm is preparing documentation for a public library project to be procured through a design-build delivery method. The owner's bid documents must allow the design-build contractor to develop the detailed design, while the owner retains a performance-based program. The authority having jurisdiction requires submission of a building permit before any construction, and the owner wants the design-builder to obtain permits. The firm's draft performance criteria currently specify exact wall assembly details. Which revision best supports the specified delivery method and the permit requirement?

  10. 10 Question 10 Single choice Project Work Planning

    A project manager is developing a work plan for a 40,000 square foot community clinic with a fixed completion date tied to a grant deadline. The team includes two internal designers, one structural consultant, one MEP consultant, and a civil consultant whose availability is limited to three days per week. The structural engineer's deliverables depend on architectural floor plans, and the MEP consultant needs structural openings before finalizing ductwork. The schedule must show a critical path that meets the grant deadline. Which schedule element best supports this requirement?

  11. 11 Question 11 Single choice Project Work Planning

    A firm has been awarded a 6-month renovation of a historic courthouse. The project includes a phased occupancy plan, requiring the building to remain partially occupied, and the authority having jurisdiction requires a separate review for fire-separation work in each phase. The owner's facilities director has asked for weekly updates, while the structural engineer and the general contractor communicate through their own weekly meeting. The project manager needs a communication plan that prevents missed decisions affecting phased occupancy. Which approach is most appropriate?

  12. 12 Question 12 Single choice Resource Management

    An architecture firm is assembling a team for a 220,000 square foot mixed-use project with a tight schedule and a requirement that the firm's internal staff have experience with the adopted energy code. The principal wants to assign a junior designer who has strong Revit skills but no code experience, and a senior technical staff member who is currently allocated 80 percent to another project through the same quarter. Which criterion should drive the team composition decision?

  13. 13 Question 13 Single choice Resource Management

    A firm is allocating resources across three concurrent projects, each with a different phase schedule. The construction documents phase on Project A is consuming 60 percent of available drafting hours, and Project B's design development milestone falls in the same two weeks. The firm wants to manage its staff's time so that no individual exceeds sustainable utilisation, and the principal insists on maintaining quality reviews for all milestones. Which resource management method best addresses this situation?

These are 13 of the 79 questions in the full Project-Management pack.

Get All 79 Questions

Get all 79 questions & answers

734 Satisfied customers
95.2% Pass rate feedback
84.8% Said questions matched
92% Found material helpful

Full access options for NCARB Project-Management

Self-study

PDF Version

$40.00 $20.00
  • 79 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 79 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the Project-Management Exam (ARE 5.0 Project Management (PjM) Exam) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed