Exam Information
Free practice questions with explanations
NCARB PDD Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 12
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Construction Cost Estimates
A mid-sized firm is reviewing a schematic-design cost estimate for a three-story school addition. The estimate was prepared using a unit-cost approach based on gross floor area and lists a single lump-sum line for 'building envelope' without quantities. The design includes a large amount of curtain wall, a green roof assembly, and a radiant floor slab. The owner has a fixed budget and wants to confirm that the estimate reflects the current design before the design development phase begins. Which action should the project architect take FIRST to confirm alignment between the estimate and the design?
Correct Answer: CExplanationA lump-sum envelope line cannot be checked against the drawings, so the estimate cannot be confirmed as aligned with the design. Asking the estimator to quantify the curtain wall, green roof and roofing assemblies lets the architect compare each cost driver with what is actually drawn. Raising contingency hides the gap rather than explaining it, switching to a per-room basis does not address the envelope, and deferring the review lets an unverified budget carry into design development.
-
2 Question 2 Single choice Construction Documentation
A design team is preparing a set of construction documents for a mixed-use building that includes a basement parking level, a ground-floor retail podium, and residential floors above. The client has requested that the site and building documentation clearly communicate which floors are accessible to the public and which are restricted, and the zoning review requires floor-area calculations by use. Schedules for doors and finishes already exist on separate sheets. During coordination, the team notices that the floor plans do not indicate the building's relationship to adjacent property lines. Which documentation addition best meets the stated needs without duplicating information already covered elsewhere?
Correct Answer: CExplanationDocumenting use separation and floor-area breakdowns is best handled on the plans themselves, supported by a site plan that shows setbacks and property line relationships, which the floor plans cannot provide. Enlarged plans of one area do not address the whole-building requirement, a door schedule with fire ratings serves a different purpose than use zoning, and a finish legend conveys material rather than access or occupancy. Duplicating schedule information on plans would also add redundancy the scenario explicitly avoids.
-
3 Question 3 Single choice Integration of Building Materials & Systems
A ten-story laboratory building is being sized during design development. The mechanical engineer has proposed a variable-air-volume system with a central air-handling unit on the roof. The architect notes that the ceiling plenum above the labs is only 900 mm deep, and the structural system uses deep steel beams at 9 m spacing with long-span trusses in the mechanical floor. The client requires that each lab have independently controlled exhaust and that the fan-coil units not penetrate the fire-rated corridor walls. Which coordination step should the team take FIRST to determine whether the proposed mechanical distribution can meet these goals?
Correct Answer: CExplanationWhether ductwork fits within a 900 mm plenum crossing deep beams and truss depths is a geometric question that only a sectional coordination study can answer, and it also reveals where fire-rated walls would be penetrated. Raising fan pressure does not create space and may worsen noise and energy use. Locating exhaust fans at grade conflicts with the lab requirement of independent control and rooftop discharge, and relocating fan-coil units into the corridor violates the explicit prohibition on penetrating fire-rated corridor walls.
-
4 Question 4 Single choice Project Manual & Specifications
An architect is preparing the project manual for a regional library renovation. The owner's facilities group has asked that the specifications govern the replacement of an existing HVAC control system, which is being partially retained. The drawings show new control points and a new front-end graphic interface, but the specification section for controls currently refers to a generic 'building automation system' and does not list the retained equipment or the required integration points. The contractor has already submitted a bid based on the current drawings. Which action should the architect take to keep the project manual and drawings coordinated before bidding proceeds?
Correct Answer: CExplanationSpecifications and drawings must describe the same scope, and the controls section must name the retained equipment and integration points shown on the drawings for the bidders to price the work consistently. A general coordination clause shifts risk to the contractor after award and leaves the conflict unresolved. Moving controls to an allowance changes the bid basis without fixing the documents, and issuing drawings as final before the specification is aligned would invite conflicting interpretations.
-
5 Question 5 Single choice Construction Documentation
During construction of a four-story office building, the owner requests a change to the stair layout to add an elevator lobby on levels two through four. The contractor has already completed the structural framing at those levels. The architect must issue a revision and communicate the change to the owner and the design team. The owner's approval is needed before the design team revises the structural drawings. Which action should the architect take FIRST?
Correct Answer: BExplanationBecause the owner must approve the change before the design team revises structural documents, the architect first needs to define the proposed change and its consequences, which a sketch or revised plan with a code and framing impact review provides. Issuing a bulletin or a construction change directive before approval bypasses the required sequence, and reissuing the full set is premature because the scope of the change is not yet settled.
-
6 Question 6 Multiple choice Integration of Building Materials & Systems
A developer is converting a warehouse into a performing arts space with a 300-seat auditorium. The acoustician requires a noise criterion (NC) of 25 in the auditorium and a sound isolation rating between the auditorium and adjacent office space that is higher than the wall assembly originally drawn. The lighting designer wants a theatrical rig supported from a steel grid above the stage, and the fire marshal requires sprinkler coverage at the stage. The existing roof structure has limited capacity for additional loads. Which TWO coordination decisions best integrate these specialty systems with the building structure and each other? (Choose two.)
Correct Answer: B, EExplanationSeparating the acoustic ceiling from the lighting grid and sprinkler supports keeps vibration and loads from compromising the acoustic performance, which is a common coordination requirement for performing spaces. Coordinating sprinkler heads with the grid and having the structural engineer check combined loads addresses both the fire protection and the limited roof capacity. Hanging the grid from existing roof steel ignores the stated capacity limit, omitting acoustic seals undermines the isolation goal, and loading the ceiling onto sprinkler mains creates an unsafe and non-acoustic support arrangement.
-
7 Question 7 Single choice Construction Cost Estimates
A design firm receives a cost estimate for a 60,000 square foot medical office building in which the structural steel, concrete and mechanical lines are priced by subcontractor quotes, but the estimate has no quantity support for the interior finishes. The architect knows that the design calls for terrazzo flooring in patient corridors and a specialty wall covering at the exam rooms. The project is under a strict cost target, and the next design review is in two days. Which step best confirms whether the interior finishes line items align with the design intent?
Correct Answer: BExplanationVerifying each finish line against the room finish plan and finish schedule checks that the priced materials, quantities and locations match what the design calls for, which is the direct test of alignment. An average cost per square foot ignores the specific terrazzo and wall covering. A finish allowance defers the very alignment question the review needs answered, and substituting resilient flooring changes the design without confirming the current estimate.
-
8 Question 8 Single choice Project Manual & Specifications
A firm is writing the specifications for a university recreation center. The project manual includes a general requirements division, a bidding requirements section and a set of technical sections. The architect is reviewing a draft in which the roofing specification calls for a specific manufacturer's membrane but also allows 'equivalent products' without any performance criteria. The roofing detail on the drawings shows a particular insulation thickness and fastening pattern that depends on the membrane's wind uplift rating. The owner's standards require that substitutions be approved through a formal request process. Which revision best meets the requirements of the project manual and specifications?
Correct Answer: BExplanationSpecifications that allow equivalents must state the performance criteria a substitute has to meet, and here the wind uplift rating governs the insulation thickness and fastening pattern shown on the drawings. Pairing that criterion with the owner's formal substitution process keeps the documents coordinated. Allowing any membrane removes the performance link, letting the installer adjust the attachment pattern on the drawing creates a conflict between documents, and removing the detail from the drawings breaks the required coordination between drawings and specifications.
-
9 Question 9 Single choice Construction Documentation
A design team is preparing the site documentation for a hospital expansion on a constrained urban lot. The drawings must show existing utilities, the proposed building footprint, the construction staging area, and the location of a temporary pedestrian route that keeps the adjacent emergency entrance open. The survey was completed two years ago, and the city has since installed new storm lines in the adjacent street. The contractor will need to start site work in four weeks. Which action is the MOST appropriate first step to ensure the site documentation is reliable for bidding and construction?
Correct Answer: BExplanationBecause the survey is two years old and the city has since changed the utilities, the existing conditions must be updated before the site documentation can be relied on for bidding and staging decisions. A new survey and utility locate fix the base information, after which the staging area and temporary route can be drawn accurately. A general note shifts the risk to the contractor, a separate phasing diagram leaves the site plan out of date, and the original utility map predates the new storm lines.
-
10 Question 10 Multiple choice Integration of Building Materials & Systems
A design team is developing the coordination for a six-story residential building with a rooftop mechanical penthouse. The engineers have sized the rooftop units and the building's vertical shafts, and the structural engineer has set beam depths for the transfer level below the penthouse. The fire protection engineer has noted that the sprinkler standpipe must be routed in a rated shaft that also carries electrical risers. The owner requires that vibration from the rooftop units not reach residential units below. Which TWO actions are the most appropriate to coordinate these systems? (Choose two.)
Correct Answer: A, CExplanationIsolating the rooftop units on curbs supported by identified structural members, with the penthouse deck and transfer beams checked for the isolated loads, addresses vibration at the source and keeps the structure coordinated. Combining the standpipe with the electrical riser in a fire-rated shaft requires that the shaft dimensions and rating are confirmed against the actual pipe and conduit sizes. Hanging units from transfer beams transfers vibration into the structure below, routing ducts through residential corridors conflicts with the vibration goal and layout, and relying on a ceiling alone does not stop vibration at the source.
-
11 Question 11 Single choice Project Manual & Specifications
A firm is preparing the project manual for a fire station renovation. The owner's project manager has asked for a bidding requirements package that identifies which documents bidders must submit with their proposals and how the bid will be evaluated. The manager also wants the general conditions to reflect the owner's required insurance and bonding amounts, which differ from the firm's standard template. The owner has an existing contract form with a separate agreement between owner and contractor. Which component of the project manual should the architect prioritize to ensure these requirements are clearly communicated to bidders before bidding opens?
Correct Answer: BExplanationBidding requirements and the general conditions are the parts of the project manual that set out how bids are submitted and evaluated and which insurance and bonding obligations apply, so they are the priority for communicating the owner's requirements before bidding. Technical specifications describe materials and workmanship rather than bid procedure. General notes on drawings are not the place for insurance terms, and the agreement form is executed after award rather than read by bidders as the governing bid instructions.
-
12 Question 12 Single choice Construction Documentation
A design team is coordinating the construction documents for a multi-building campus. The client has asked for a single, consistent set of drawings that can be issued to the bidding contractors. The team has found that the door numbering on the architectural floor plans does not match the hardware schedule, which numbers doors differently across two buildings, and the finish schedule uses room numbers that were changed in the latest revision. The project is about to be issued for bidding in three days. Which step should the team take FIRST to produce a clear and coordinated documentation set?
Correct Answer: BExplanationConsistent numbering across plans and schedules is the foundation for a coordinated document set, so the team needs one numbering system applied to every affected sheet before issuing. A cover cross-reference table leaves the schedules inconsistent and invites errors during bidding. Issuing schedules later as an addendum delays the coordination problem rather than solving it, and renumbering only the hardware schedule leaves the finish schedule mismatched with the revised room numbers.
These are 12 of the 100 questions in the full PDD pack.
Get All 100 QuestionsGet all 100 questions & answers
Full access options for NCARB PDD
Self-study
PDF Version
- 100 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 100 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 100 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the PDD Exam (ARE 5.0 Project Development and Documentation Exam) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.