Exam Information
Free practice questions with explanations
ISTQB CTAL-TM Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 10
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice The Test Process
A test manager at a payments company runs a hybrid program: the core banking integration follows a stage-gated plan with formal test exit criteria, while the mobile app team works in two-week Scrum sprints. Compliance requires that every release candidate has traceable evidence of completed regression testing. The mobile team's sprint reviews are already producing working increments, but the program steering committee wants one consolidated test status view by month-end. Budget for new tooling is frozen. What should the test manager do FIRST to establish a consistent test monitoring approach across both streams?
Correct Answer: AExplanationBecause the compliance requirement and the steering committee's need for one status view both apply across streams, the first step is to agree a common monitoring approach: shared metrics, reporting cadence and evidence mapping that suit each lifecycle. Forcing one lifecycle onto the other breaks the sprint rhythm, buying tooling conflicts with the frozen budget, and waiving compliance evidence is not something the manager can grant. Agreeing measures first lets tooling or process changes be decided afterwards.
-
2 Question 2 Single choice Test Metrics
A test manager for a retail e-commerce platform is preparing a weekly report for the steering group. Over the last three sprints, the team has executed 80 percent of planned test cases, but 35 percent of executed cases were re-opened after retest because the defect fix was incomplete. The steering group asks whether the team is on track for the planned release in six weeks. The manager has no authority to change scope. Which metric set BEST supports a decision on release readiness?
Correct Answer: CExplanationExecution percentage alone says nothing about quality, and the 35 percent re-open rate is a warning sign that the 80 percent figure hides. Pairing the re-open rate with open high-severity defects and coverage of risk areas gives stakeholders evidence on whether the release is ready. Defect counts can rise because of better testing, and execution time is an effort measure rather than a readiness indicator.
-
3 Question 3 Single choice Test Estimation
A test manager is estimating testing effort for a new insurance claims module. The module is built by a team that has never used the new rules engine, the requirements are still changing every sprint, and the test environment is shared with two other projects and is available only three days a week. The project sponsor wants a single firm number within two days. Which estimation approach is MOST appropriate for the test manager to recommend?
Correct Answer: AExplanationThe uncertainty in requirements, the unfamiliar rules engine and the limited environment availability all need to be visible in the estimate. A work-breakdown estimate that separates environment constraints and presents a range, refined as the requirements stabilise, reflects those factors honestly. A single figure from a dissimilar project ignores the new technology, counting cases ignores environment limits, and waiting for frozen requirements contradicts the sprint-by-sprint change pattern.
-
4 Question 4 Single choice Defect Management
A test manager is implementing a defect management process for a team delivering features in two-week sprints. Testers currently log defects directly in the tracker with inconsistent severity values, and several defects have been closed by developers without retest. The product owner wants to be able to prioritise defects in sprint planning, and the compliance auditor requires an audit trail of every defect status change. The team uses a tracker that supports custom workflows and role-based transitions. Which defect workflow design BEST meets these requirements?
Correct Answer: AExplanationThe tracker's custom workflows and role-based transitions allow the manager to stop developers closing defects without retest, to make severity a controlled field for prioritisation, and to keep a timestamped record of each change for the auditor. Allowing any role to close defects repeats the original problem, a weekly spreadsheet loses audit history, and removing severity prevents consistent prioritisation.
-
5 Question 5 Single choice Test Metrics
A test manager reviews the test report for a logistics system going through a performance test cycle. The report shows that all 40 load scenarios passed their response-time targets on average, but the 95th percentile response time for the order-tracking scenario exceeded its service-level target in four of the six test runs. The report is due to the steering group today. The manager must report results so that stakeholders can decide whether to proceed to go-live. What should the report contain?
Correct Answer: AExplanationAverages can hide tail latency, so the 95th percentile breach in four of six runs is the finding that matters for a go-live decision. A report that states the scenario results, the breach and its implications lets stakeholders weigh the risk. Reporting averages or omitting the exception misleads the decision makers, and recommending proceeding without that information goes beyond the evidence.
-
6 Question 6 Single choice The Test Team
A test manager is preparing a skills assessment for a newly formed test team of eight people, including two experienced automation engineers, four manual testers with domain knowledge but no automation experience, and two recent graduates. The project will rely heavily on API test automation within the next quarter. The manager has a limited training budget and must avoid assessments that disadvantage team members in front of peers. Which assessment technique is MOST appropriate?
Correct Answer: AExplanationA confidential practical exercise tied to the API automation need gives objective evidence of skill gaps without public comparison, and it allows the manager to target the limited training budget. Public rankings damage team cohesion, self-assessment alone is unreliable, and replacing staff based on CVs ignores both the budget and the value of domain knowledge.
-
7 Question 7 Multiple choice Risk-Based Testing
A test manager for a healthcare scheduling application identifies that the release includes a change to appointment-conflict logic, a minor cosmetic change to the login page, and a new integration with an external prescription service. The test budget covers only about 60 percent of the planned regression suite. Which TWO test management actions BEST apply risk-based testing to this situation? (Choose two.)
Correct Answer: B, EExplanationRisk-based testing directs effort to areas where the likelihood and impact of failure are highest, which is the conflict logic and the new integration. Explicitly agreeing with the product owner which lower-risk areas are deferred or sampled, and recording the residual risk, makes the reduced coverage a decision rather than an accident. Dropping the login tests entirely ignores authentication risk, running the full suite in document order ignores the budget limit, and adding login tests spends effort on the lowest-risk change.
-
8 Question 8 Single choice Test Metrics
A test manager is responsible for controlling progress on a test phase for a government tax system that must complete by a fixed legal deadline. After two weeks, the burndown chart shows 55 percent of planned test cases executed against 40 percent of the planned time elapsed, but the open critical defect count is rising and 20 percent of executed tests are blocked by an unstable environment. The sponsor asks whether to add two more testers to recover schedule. What is the MOST appropriate control action?
Correct Answer: BExplanationThe apparent lead in execution is misleading because 20 percent of tests are blocked and critical defects are rising, so the progress picture is not as healthy as it looks. Diagnosing the environment problem and the defect trend before acting lets the manager judge whether extra testers would actually help. Adding people to a blocked environment rarely speeds progress, ignoring the defect trend misreports status, and cutting scope without stakeholder agreement is a governance failure.
-
9 Question 9 Single choice The Test Process
A test manager has finished the system test phase for a travel booking platform. Several test objectives were not fully met: three high-priority defects remain open with agreed deferral, and the regression suite covers 85 percent of planned cases. The release is scheduled for the following week, and the business sponsor wants to start the next project phase immediately. Which activity should the test manager perform NEXT to complete the test phase properly?
Correct Answer: AExplanationTest completion requires consolidating results, recording lessons learned and reporting the unmet objectives and accepted risks so the sponsor signs off with full knowledge. Starting the next phase or archiving the environment before that report skips completion activities, and closing defects artificially falsifies the record of deferred risk.
-
10 Question 10 Multiple choice The Test Team
A test manager is planning the cost of quality for a team that has recently suffered several production incidents after releases. The manager must present costs to the steering group in terms of the four cost-of-quality categories. Which TWO of the following examples correctly belong to the prevention and appraisal categories respectively? (Choose two.)
Correct Answer: A, DExplanationPrevention costs are incurred to stop defects arising, such as writing test design guidelines, and appraisal costs are incurred to measure quality, such as executing regression tests and reviewing testability. Fixing production defects and paying compensation are failure costs, and running a risk workshop after the incident is a reactive failure-related activity, not an appraisal cost in the sense of measuring quality before release.
These are 10 of the 228 questions in the full CTAL-TM pack.
Get All 228 QuestionsGet all 228 questions & answers
Full access options for ISTQB CTAL-TM
Self-study
PDF Version
- 228 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 228 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 228 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CTAL-TM Exam (Certified Tester Advanced Level Test Management v3.0) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.