Exam Information
Free practice questions with explanations
Huawei H35-481_V2.0 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 14
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice 5G RAN Fundamentals and Architecture
A regional operator is deploying a standalone 5G NR gNB in a dense urban area. The gNB must split its protocol stack so that latency-sensitive user-plane processing runs close to the radio, while control and non-real-time functions are centralised to reduce site hardware cost. The design team must keep the F1 interface between the central and distributed units standards-based so that a third-party CU can be used later. Which architecture decision meets these requirements?
Correct Answer: DExplanationThe standard option 2 style split places RRC, SDAP and PDCP in the centralised unit, while RLC, MAC and high/low PHY sit in the distributed unit, with the F1 interface carrying traffic between them. This keeps latency-critical scheduling near the radio and lets control functions be pooled, and because F1 is standardised a third-party CU remains possible. Placing RRC in the DU breaks the centralisation goal, while terminating F1 at RLC is not the defined split point. Keeping the full stack in one baseband unit removes the pooling benefit the operator wants.
-
2 Question 2 Single choice 5G RAN Operations and Maintenance
An operator's NOC receives alarms that the cell throughput on a 3.5 GHz NR cell has dropped by 40 percent over the past two hours. Counters show the average PRB utilisation remains moderate, but the uplink BLER on the same cell has risen sharply while RSRP and SINR are stable. No hardware alarms are raised and the change freeze prevents parameter edits until the next maintenance window. The engineer must first narrow the fault domain using only performance and fault data already collected. What is the most appropriate first action?
Correct Answer: DExplanationStable RSRP and SINR with rising uplink BLER and a healthy PRB load point toward an uplink-specific impairment, classically external interference raising the uplink noise floor, which the interference measurement per PRB exposes without any configuration change. The change freeze rules out parameter edits, and a board reset would be disruptive and unjustified without hardware alarms. Raising downlink power does not address an uplink problem, and handing over all users is a heavy action that tells the engineer little.
-
3 Question 3 Single choice 5G RAN Security
A national operator is hardening its 5G standalone core and RAN for a government customer. The security policy requires that user-plane traffic between the gNB and the UPF be protected against eavesdropping and tampering on the transport network, that the protection be applied at the transport layer rather than inside each application, and that the solution must not require changes to the gNB radio software. The transport between the gNB and the core is a shared IP backhaul owned by a third party. Which measure best satisfies all three requirements?
Correct Answer: AExplanationIPsec protects IP traffic at the network layer, so it covers the N2 and N3 interfaces over the third-party backhaul without modifying application software on the gNB. Air interface integrity protection only covers the radio link and offers no protection once traffic leaves the site. SUPI concealment protects identity over the radio path, and NAS ciphering protects UE to AMF signalling, neither of which secures the N3 user-plane transport between gNB and UPF.
-
4 Question 4 Single choice Advanced 5G Radio Technologies
A mobile operator runs a non-standalone (NSA) 5G deployment where the LTE anchor provides the control plane and an NR secondary cell group carries additional user-plane throughput. Users at the cell edge on the 3.5 GHz NR carrier show frequent SCG failures, and the operator wants to add a second NR carrier to use carrier aggregation in the secondary cell group without disrupting the LTE anchor. Field measurements show the NR carrier is interference limited at the cell edge. Which action should the engineer take first?
Correct Answer: AExplanationThe NR carrier is interference limited at the cell edge, so cell-edge SINR must be improved before aggregation can add value; enabling inter-cell interference coordination and confirming SINR gives the right ordering. Aggregating a second carrier on top of an interference-limited edge would simply spread the same problem. Carrier aggregation in NSA applies to the secondary cell group, not to the primary LTE anchor as proposed. Migrating to SA is a large architectural change beyond the stated scope, and lengthening the SCG failure timer only hides radio failures.
-
5 Question 5 Single choice Emerging Technologies and Future Trends
A manufacturing enterprise is evaluating whether its private 5G network should use a fixed beamforming design for its indoor cells or move toward dynamic beamforming powered by massive MIMO. The factory floor has many mobile automated guided vehicles, the uplink must support frequent small reports, and the site has limited space for antenna arrays and a tight power budget. Which trend-based conclusion is most defensible for the next upgrade phase?
Correct Answer: AExplanationDynamic beamforming driven by uplink sounding lets the gNB steer narrow beams toward moving AGVs, improving SINR and capacity without raising transmit power, which fits the constrained power budget. Analogue-only beamforming still depends on feedback and cannot adapt per user as flexibly. Rejecting dynamic beamforming overlooks its benefit for mobile devices, and macro sites do not solve an indoor coverage and capacity requirement.
-
6 Question 6 Single choice Practical 5G RAN Implementation
A field engineer commissions a new 5G NR base station that will serve a logistics hub. The site is to be integrated into the operator's network and must synchronise accurately for TDD operation between neighbouring cells. The engineer has already installed the baseband unit and radio units, and the transport link to the core is up. Before the cell can be activated and carry traffic, the engineer must ensure the base station receives a valid time and frequency reference. What should be configured to meet this requirement?
Correct Answer: DExplanationTDD cells must be synchronised in both time and frequency, so the base station needs a configured clock source such as GPS or PTP and a locked synchronisation status before cell activation is meaningful. Transport reachability and cell identity do not guarantee the timing needed for TDD alignment. Licensing enables capacity but does not provide a reference clock.
-
7 Question 7 Multiple choice 5G RAN Fundamentals and Architecture
A carrier is designing a 5G standalone network to offer an enterprise a dedicated network slice for industrial control with strict latency and reliability targets. The design must isolate this slice's radio resources from the consumer slice in the RAN while the same gNBs serve both. Which TWO design choices best meet these requirements? (Choose two.)
Correct Answer: B, CExplanationSlicing in 5G is identified by S-NSSAI, and the gNB can apply per-slice radio resource policies to isolate the industrial slice from the consumer slice on shared hardware. Network slice selection at the AMF lets the UE be registered to the correct slice so that the RAN and core apply the matching policy. A separate gNB per site contradicts the shared-infrastructure requirement, a dedicated PLMN identity is not how slices are separated, and disabling all shared scheduling is impractical and not required.
-
8 Question 8 Order list 5G RAN Operations and Maintenance
A radio engineer receives a ticket reporting that a 5G cell is intermittently dropping users during handover to a neighbour cell. The engineer must follow a structured fault-handling process that starts with confirming the symptom and ends with verifying the fix, without making uncontrolled changes. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Check the neighbour relation and handover parameters against the planned configuration.
- Apply the approved parameter correction through the change process.
- Confirm the symptom with alarm and performance data and define the affected cells.
- Re-measure handover success and drop rates to verify the fault is cleared.
- Collect handover success rate and drop counters for the affected cell pair over the fault period.
Correct Answer:- Collect handover success rate and drop counters for the affected cell pair over the fault period.
- Confirm the symptom with alarm and performance data and define the affected cells.
- Check the neighbour relation and handover parameters against the planned configuration.
- Apply the approved parameter correction through the change process.
- Re-measure handover success and drop rates to verify the fault is cleared.
ExplanationA disciplined process confirms the symptom and scope first, gathers performance evidence, then examines the neighbour relation and handover configuration before making an approved change. Verification comes last, since only re-measured counters can prove the correction worked. Changing parameters before collecting evidence or confirming scope would risk unnecessary side effects, and skipping the change process would violate control requirements.
-
9 Question 9 Drag and drop 5G RAN Security
A mobile operator is reviewing its 5G RAN security controls ahead of an audit. The audit team has listed three security requirements that must each be matched to the control that addresses it. Match each requirement to the control that meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Verify that the gNB and core mutually authenticate before traffic is exchangedProtect the N3 user-plane traffic between gNB and UPF on the shared IP transportProtect subscriber identity from being exposed over the radio interface during initial attachMutual authentication during the primary authentication procedureIntegrity protection of the NR air interface signallingIPsec tunnel between the gNB and the core transport gatewaySUCI concealment using the home network public keyNetwork slice admission control at the AMFCorrect Answer:- Protect subscriber identity from being exposed over the radio interface during initial attach → SUCI concealment using the home network public key
- Protect the N3 user-plane traffic between gNB and UPF on the shared IP transport → IPsec tunnel between the gNB and the core transport gateway
- Verify that the gNB and core mutually authenticate before traffic is exchanged → Mutual authentication during the primary authentication procedure
ExplanationSUCI concealment hides the permanent identity during initial attach, while IPsec protects N3 traffic on untrusted or shared transport. Mutual authentication is achieved through the primary authentication procedure with the subscriber and network. Air interface integrity protects radio signalling rather than the transport identity, and slice admission control addresses resource allocation, so neither matches the listed requirements.
-
10 Question 10 Dropdown Practical 5G RAN Implementation
A deployment engineer is preparing a base station for a new NR cell on an indoor distributed antenna system. The engineer must set the cell bandwidth and the subcarrier spacing consistent with the planned 100 MHz channel on the 3.5 GHz band, where the common numerology is 30 kHz. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
The cell is configured with a channel bandwidth of MHz and a subcarrier spacing of kHz, with the sync raster placed on the planned frequency.Correct Answer:The cell is configured with a channel bandwidth of 100 MHz and a subcarrier spacing of 30 kHz, with the sync raster placed on the planned frequency.
ExplanationA 100 MHz channel is the bandwidth stated in the plan, and 30 kHz is the common numerology for 3.5 GHz NR, matching the requirement. The 20 and 50 MHz options do not match the planned channel, and 200 MHz is not a valid NR channel bandwidth option here. The 15 kHz spacing is typical of lower bands, and 60 and 120 kHz do not match the planned numerology.
-
11 Question 11 Single choice 5G RAN Operations and Maintenance
A transport network carrying backhaul for several 5G gNBs shows packet loss that only affects the user-plane traffic during busy hours. The operator wants to find the cause without taking any production site out of service. The NOC has access to the gNB performance counters, the transport device queue statistics and the time-series data from the last two weeks. Which approach is the most effective next step to pinpoint where the loss occurs?
Correct Answer: DExplanationCorrelating busy-hour loss with queue drop statistics on each transport segment localises the bottleneck without disruptive action, which is the requirement here. Rebooting routers would interrupt traffic, and removing QoS marking would worsen prioritisation for latency-sensitive flows. Adding carriers addresses radio capacity rather than a transport loss problem.
-
12 Question 12 Multiple choice Advanced 5G Radio Technologies
A regional operator is planning a 5G NR deployment that must share its 3.5 GHz spectrum with an existing LTE layer that will be phased out over three years. The engineer must choose spectrum utilisation approaches that let NR and LTE coexist during the transition without service degradation on either layer. Which THREE approaches are appropriate? (Choose three.)
Correct Answer: A, B, CExplanationDynamic spectrum sharing lets the same carrier be allocated between NR and LTE on demand, which suits a phased transition. A fixed split with planned review offers a controlled alternative, and guard band planning keeps cross-layer interference within limits. Giving NR the whole carrier immediately would strand LTE users on that band, and identical PCI and ARFCN values would cause conflicts rather than coexistence.
-
13 Question 13 Single choice Advanced 5G Radio Technologies
A network planner must decide the uplink and downlink slot ratio for a TDD NR cell on a campus where most traffic is downlink video streaming to handheld devices, with a smaller share of uplink traffic from cameras. The planner is required to keep cross-link interference between neighbouring TDD cells under control and to avoid changing slot configuration during operation. Which configuration decision best meets these requirements?
Correct Answer: DExplanationA downlink-heavy pattern matches the traffic profile, and aligning the slot pattern across neighbouring cells avoids cross-link interference between uplink and downlink transmissions. Equal balance wastes capacity on a downlink-dominated campus, and an uplink-heavy pattern serves the minority traffic at the expense of video. Mixing patterns between neighbours creates cross-link interference rather than preventing it.
-
14 Question 14 Single choice Emerging Technologies and Future Trends
A telecom operator is assessing how emerging RAN openness trends could affect its long-term 5G strategy. The operator wants to reduce dependence on a single vendor for its RAN functions while keeping performance-critical scheduling in the base station. It also needs to remain compliant with the existing operations process and avoid replacing its production core in the next two years. Which strategy is most consistent with these goals?
Correct Answer: BExplanationStandardised split interfaces let the operator diversify CU sourcing while keeping latency-critical scheduling in the DU at the site, which matches the performance and phased-change constraints. Moving scheduling to a best-effort cloud path would break latency guarantees. An immediate full virtualisation conflicts with the two-year constraint, and staying fully proprietary keeps the vendor dependence the operator wants to reduce.
These are 14 of the 60 questions in the full H35-481_V2.0 pack.
Get All 60 QuestionsGet all 60 questions & answers
Full access options for Huawei H35-481_V2.0
Self-study
PDF Version
- 60 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 60 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 60 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the H35-481_V2.0 Exam (HCIP-5G-RAN V2.0) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.