Exam Information
Free practice questions with explanations
Huawei H20-923_V1.0 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 17
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice UPS5000H Lab Guide
A data center engineer is commissioning a UPS5000H system that feeds two independent IT rows. After energising the rectifier and inverter, the commissioning checklist shows the bypass path as healthy but the static bypass has not been tested under load. The customer requires that the UPS can transfer the critical load to bypass without interruption during a planned inverter maintenance window. Which action should the engineer take FIRST to verify this requirement?
Correct Answer: DExplanationThe requirement is about uninterrupted transfer to bypass during inverter maintenance, so the engineer must prove the bypass transfer itself works under the real load before anything else. A controlled transfer to bypass with confirmation that output stays within the bypass tolerance is the verification that directly addresses the requirement. Disabling the battery does not test the bypass path and would instead create a battery-backup risk. Raising charge current affects battery recharge, not transfer behaviour. Changing the output frequency setting to match a generator is unrelated to the static bypass test and risks introducing a synchronisation fault.
-
2 Question 2 Single choice FusionCol8000-A Lab Guide
A colocation provider is commissioning a row of in-room air-cooled fan wall units on a raised-floor hot-aisle layout. During commissioning, the rack inlet temperatures at the top of the cabinets exceed the target while the lower cabinets are within range. The provider has a strict budget and cannot add more units. Airflow management in the room is already optimised with blanking panels fitted. Which corrective action is the MOST appropriate first step?
Correct Answer: DExplanationThe top-of-rack hotspot in an air-cooled fan wall deployment points to recirculation or insufficient airflow delivery at height, and the cheapest correct step is to verify fan speed, supply temperature setpoints and recirculation paths before spending money. Raising chilled water temperature does not apply to an air-cooled fan wall and would worsen the problem. Removing containment would increase mixing and make the hotspot worse. Lowering fan speed reduces airflow and would also deepen the thermal problem.
-
3 Question 3 Single choice FusionCol8000-C (110-440) In-Room Chilled Water Smart Cooling Product
A managed services company is adding a FusionCol8000-C chilled water unit to an existing room whose power envelope is constrained. The planning team must choose the unit's operating configuration. The room has a chilled water supply that is available but limited in temperature headroom, and the facility team wants to avoid overloading the building's chiller plant during peak hours. Which design decision BEST aligns the unit with these constraints?
Correct Answer: DExplanationThe chilled water unit must be sized within its stated power range and the supply temperature must respect the plant's actual headroom, which is what the constraints demand. Pushing flow and return temperature upward ignores the stated plant limit. Running fans at maximum constantly adds power draw that the constrained envelope cannot absorb. Putting the cooling unit on the generator bus is a power-resilience decision that does not address the chiller-plant and power-envelope constraint in the stem.
-
4 Question 4 Single choice Data Center Cooling Solutions
A retail bank is redesigning the cooling for a 300 kW data hall that currently uses perimeter CRAC units blowing into an open floor. Rack densities are rising unevenly, with a few racks above 15 kW and the rest near 4 kW. The bank wants to reduce fan energy and avoid hotspots without a full rebuild in the next quarter. Which strategy is the MOST appropriate starting point?
Correct Answer: DExplanationContainment and blanking panels address the mixing that causes the uneven hotspots without a rebuild, and aligning capacity with the dense zones addresses the uneven rack loads. Consolidating to one distant unit ignores local density and would not fix the hotspots. Lowering supply temperature across the hall spends fan and chiller energy everywhere to cure a localised problem, contrary to the energy goal. Adding tiles everywhere distributes airflow uniformly, which wastes air on low-density racks and does not solve the mixing.
-
5 Question 5 Single choice Huawei Data Center Facility Solutions
A government agency wants a single facility vendor to deliver power, cooling, monitoring and prefabricated space for a new remote site with a 24-month deployment target. The agency's procurement rules require that integration responsibility for the whole facility sits with one accountable party, and that the solution can be delivered as a pre-tested, factory-integrated unit to reduce on-site work. Which Huawei offering best matches this requirement at the portfolio level?
Correct Answer: DExplanationThe FusionModule2000 is Huawei's prefabricated modular data center, which matches both the single-accountability requirement and the factory-integrated, pre-tested delivery model. A standalone UPS5000H covers only power, so the agency would still have to integrate multiple vendors, violating the procurement rule. A SmartLi 3.0 battery is only short-term backup and does not provide a complete facility. An ECC800-Pro is a monitoring controller that cannot supply the physical facility on its own.
-
6 Question 6 Single choice Huawei DCIM Lab Guide
A data center operator has deployed a DCIM system to monitor power and cooling. After commissioning, the operations team reports that the DCIM dashboard shows alarms from the UPS but the cooling units show as offline, although the cooling units are physically running and reachable on the management network. The operator must restore full monitoring within the change window and must not change the physical cabling. Which troubleshooting step should the engineer perform FIRST?
Correct Answer: DExplanationBecause the devices are physically reachable, the most likely cause is a mismatch in the communication address or protocol parameters configured in DCIM, and verifying those is the efficient first step that avoids cabling changes. Replacing cables contradicts the no-cabling-change constraint and ignores that the devices are already reachable. Restarting the UPS does not affect the cooling units' registration. Disabling alarm filtering would hide the status rather than restore communication.
-
7 Question 7 Single choice Huawei DCIM Installation and Deployment Lab Guide
A project engineer is deploying a DCIM system in a new data center. The site has a segregated management network, and the DCIM server must reach the power and cooling devices but must not be exposed to the production network. During installation, the engineer is asked to make the DCIM server accessible to the monitoring team in the head office over the corporate WAN. Which deployment approach best meets all these requirements?
Correct Answer: DExplanationKeeping the server on the segregated management network protects it from the production network, while a controlled gateway provides the head-office access without exposing the device network broadly. Attaching the server to production and opening all ports violates the segregation requirement. Routing the WAN directly into the device subnet exposes control equipment to the corporate network. Moving the server to head office over a public link is insecure and the stem ties the server to the site.
-
8 Question 8 Single choice iManager NetEco 6000 Product Introduction
A regional operator runs several small data centers and wants one platform to centrally monitor facility equipment, consolidate alarms and generate operational reports for management, while keeping each site's local controllers in place. The operator's security team requires that no site device be managed directly from the central platform without an authenticated, role-based account. Which capability of iManager NetEco 6000 best addresses the centralised-monitoring requirement while respecting the security rule?
Correct Answer: DExplanationNetEco 6000 provides centralised monitoring and alarm consolidation, and role-based access control enforces the authenticated, per-user access the security team demands. A shared administrator account breaks the individual-accountability requirement. Disabling authentication directly violates the security rule. Manual spreadsheet export does not deliver the centralised real-time monitoring the operator needs.
-
9 Question 9 Single choice Introduction to Huawei DCIM Controller ECC800-Pro
A facility engineer is planning the connection of an ECC800-Pro controller to a set of third-party environmental sensors and a Huawei UPS. The site uses a mixture of communication interfaces, and the engineer must keep all sensor data available on the controller's local interface even when the upstream network is down. Which design choice BEST satisfies this requirement?
Correct Answer: DExplanationAttaching devices through their supported local interfaces lets the ECC800-Pro collect and display data without depending on the upstream network, which is the explicit requirement. Routing everything through a single network switch makes the controller network-dependent, so outages would blind it. Relying on a cloud service fails the same offline requirement. Disabling the local interface removes the very path the requirement needs.
-
10 Question 10 Single choice Introduction to Huawei Precision Air Conditioners
A telecom site uses precision air conditioners in a small server room that experiences high latent load during humid summers. Operators have noticed the room humidity drifts upward between maintenance visits, causing condensation risk on cold surfaces, while temperature stays within target. The site cannot add an external humidifier and must keep the existing units. Which configuration change is the MOST appropriate?
Correct Answer: DExplanationPrecision units control humidity through their configured humidity setpoints and humidity control functions, so matching those parameters to the latent load corrects the drift without extra hardware. Lowering temperature setpoint changes temperature control and the unit has no independent humidity lever in that way, and it would cool the room unnecessarily. Disabling dehumidification removes the very function that holds humidity down. Raising fan speed moves air but does not set the humidity target.
-
11 Question 11 Single choice Introduction to the Modular Data Center FusionModule2000
A manufacturer is evaluating the FusionModule2000 for a small factory site that expects to scale from one module to several over five years. The site has limited floor space and an existing grid connection that cannot be upgraded for at least 18 months. The engineering team asks which architectural feature most directly supports both phased expansion and the limited initial power envelope. Which answer best identifies that feature?
Correct Answer: DExplanationThe FusionModule2000's modular architecture allows capacity to be added incrementally, which matches the phased growth and the constrained initial power. Installing a power block sized for the final build-out would exceed the grid limit on day one. A design requiring the full room first contradicts the phased goal, and a fixed chiller plant commissioned up front adds the same early overload.
-
12 Question 12 Single choice SmartLi 3.0 (Short-Term Backup Power) Maintenance Operations
A data center operator receives an alarm from a SmartLi 3.0 battery system indicating that one battery unit's voltage is trending lower than its peers during routine monitoring. The site must keep the critical load protected throughout, and the operator wants to avoid unnecessary replacement of healthy units. Which action should the maintenance engineer take FIRST?
Correct Answer: DExplanationThe engineer should first confirm the deviation through the monitoring data and compare the unit with its peers, which avoids replacing healthy hardware and keeps protection in place. Immediate replacement skips diagnosis and risks wasting good units. Raising the charging voltage across the whole string can overcharge healthy units and is unsafe. Disconnecting the entire string removes backup protection for the critical load.
-
13 Question 13 Single choice Training on FusionDC1000A
An operator plans to deploy a FusionDC1000A prefabricated modular data center in a location with a narrow access road and a strict weight limit on the transport route. During site survey, the team must decide how to plan the delivery and installation so the unit arrives intact and can be placed on a prepared foundation. Which planning decision is the MOST appropriate?
Correct Answer: DExplanationThe key constraints are the route's weight and dimension limits, so checking the module's transport figures against the route and preparing the foundation and access before delivery addresses the real risk. Transporting the assembled unit regardless of route limits could halt the delivery or damage it. Dismantling into loose cabinets for on-site reassembly without a foundation ignores the prepared-base requirement. Skipping the survey removes the very check the constraints require.
-
14 Question 14 Multiple choice Basic Knowledge of Power Distribution
A colocation provider is designing the low-voltage distribution for a data hall that must keep critical IT loads energised during a single-path failure. The provider wants to reduce the chance that a fault on one branch takes down multiple racks. (Choose two.)
Correct Answer: B, DExplanationFeeding dual-corded equipment from two independent paths is the core of path redundancy, so a single branch fault leaves the load supplied. Balancing phases prevents overloading one phase and reduces nuisance trips and capacity loss across the distribution. Sharing one board or merging A and B paths creates a common point of failure. A single upstream breaker for the whole hall makes one trip drop every rack, which contradicts the goal.
-
15 Question 15 Multiple choice FusionCol8000-A Lab Guide
A facilities team is commissioning a set of FusionCol8000-A cooling units and wants to confirm the installation is ready before powering up the system for normal operation. The commissioning plan must check conditions that prevent unsafe or unreliable operation. Which TWO checks should be completed before the units are powered for normal operation? (Choose two.)
Correct Answer: D, EExplanationVerifying electrical supply, cabling and protection against the rated specification is a prerequisite for safe power-up, and confirming an unobstructed condensate path prevents water damage during operation. Running fans at maximum during first power-up is a test step, not a readiness check, and it can mask issues. Removing containment before power-up would worsen airflow management. Leaving the communication address at default invites conflicts with other devices on the monitoring network.
-
16 Question 16 Multiple choice Huawei UPS5000H Lab Guide
A data center engineer is preparing a UPS5000H for commissioning under a constraint that the site's battery backup must cover the critical load for the design autonomy time, and the battery string must be correctly set up before the system is put into service. Which TWO actions are necessary to complete the battery configuration correctly before commissioning is accepted? (Choose two.)
Correct Answer: D, EExplanationThe battery count and string configuration must match the autonomy requirement and the UPS specification, otherwise backup time falls short of the design. Checking polarity and torque on the connection is a required safety step before the string is put into service. Delaying the battery connection leaves the load unprotected during commissioning. Overcharging with an out-of-spec float voltage damages the batteries. Mixing capacities produces imbalance and unreliable backup.
-
17 Question 17 Multiple choice Introduction to Huawei Precision Air Conditioners
A site operator is commissioning a set of precision air conditioners for a server room that will be connected to the site's central monitoring. The operator must ensure the units are reliable and that alarms reach the monitoring team when a fault occurs. Which TWO actions best support these requirements? (Choose two.)
Correct Answer: B, DExplanationConfiguring critical alarm reporting ensures faults reach the monitoring team, and testing the communication link confirms the alarm path actually works before it is needed. Widening setpoints hides real conditions rather than managing them. Muting alarms removes the warning the operator depends on. Permanently powering off the standby unit removes the redundancy that keeps the room cooled when the duty unit fails.
These are 17 of the 60 questions in the full H20-923_V1.0 pack.
Get All 60 QuestionsGet all 60 questions & answers
Full access options for Huawei H20-923_V1.0
Self-study
PDF Version
- 60 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 60 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 60 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the H20-923_V1.0 Exam (HCSP-Field-Data Center Facility V1.0) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.