Exam Information
Free practice questions with explanations
GAQM CASPO-001 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 14
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Understanding the Product Owner Role
A Product Owner at a logistics software company is asked by the CEO to also assign daily tasks to developers and set the sprint's technical design, because the development team has been slow. The Scrum Master notes that the team has been self-organising well over the last three sprints. Under the Scrum Guide, what is the BEST response from the Product Owner?
The Product Owner should maximise the value of the product and manage the Product Backlog, but must not direct the Developers on how to do their work. The team should be asked to review impediments in the Sprint Retrospective and the Scrum Master should facilitate that discussion with the CEO.
Choose one.Correct Answer: BExplanationThe Scrum Guide makes the Developers responsible for how the Sprint Backlog is turned into an Increment, and the Product Owner must not direct them. The Product Owner should raise the slowness concern through the Sprint Retrospective, where impediments are inspected and adapted. Accepting task assignment merges the Product Owner and Developer accountabilities. Setting technical design repeats the same error. Replacing the team is outside the Product Owner's authority and skips inspection of the actual cause.
-
2 Question 2 Single choice Envisioning the Product
A healthcare provider is building a patient-scheduling product. Executives want a product vision that will guide decisions for the next two years, but regulators may change reporting rules within six months and the budget is approved only one year at a time. The Product Owner must communicate the vision so that Sprint-level decisions stay aligned without locking the team into features that may become obsolete. Which approach BEST meets these constraints?
Choose one.Correct Answer: BExplanationA concise vision describing the outcome for patients, paired with a Product Goal that the Scrum Team commits to, gives direction while staying adaptable to the regulatory change the scenario describes. A detailed two-year feature list would lock in obsolete scope. Waiting for final rules leaves the team without direction for the whole period. Equating the vision with the backlog conflates the destination with the current route and loses the strategic purpose.
-
3 Question 3 Single choice Working with the Product Backlog
A Product Owner for a retail mobile app has a Product Backlog of 140 items, many created over two years and never refined. Sprint Planning is in four days, and the Developers report that they cannot estimate most items. The Product Owner must improve the backlog within the time available without delaying the sprint. Which action should the Product Owner take FIRST?
Choose one.Correct Answer: DExplanationOrdering the backlog so the most valuable and riskiest items sit at the top, then refining those with the Developers, makes the upcoming Sprint Planning workable within the four-day window. Deleting old items discards information without checking value. Estimating 140 items at once is unrealistic and wastes effort on low-priority work. Moving the backlog out of the Product Backlog breaks the single ordered source of work the Scrum Guide requires.
-
4 Question 4 Single choice Planning the Release
A fintech company must deliver a payments release by a regulatory deadline in 10 weeks. The release contains 60 backlog items, and Scrum Team velocity over the last five sprints has averaged 34 story points per two-week sprint with a range of 26 to 41. The stakeholders ask the Product Owner for a firm date. The Product Owner must give a forecast that is honest about uncertainty. Which approach is MOST appropriate?
Choose one.Correct Answer: BExplanationUsing the observed velocity range produces a forecast with honest best and worst cases, and ordering scope by value lets the Product Owner decide what must ship by the deadline. A single average promise ignores the 26 to 41 spread. Inflating estimates corrupts the empirical measure and hides the real problem. Dropping regulatory items removes content the scenario identifies as required for the deadline.
-
5 Question 5 Single choice Collaborating in the Sprint Meetings
During Sprint Planning, a Product Owner brings a Sprint Goal that reads 'Complete the sixteen backlog items selected for this sprint.' The Developers ask whether a Sprint Goal should describe a business outcome. The team is working on a bank's loan-origination product, where a sprint must also meet an internal audit requirement that the Developers' quality process be applied. Which Sprint Goal is MOST appropriate?
Choose one.Correct Answer: BExplanationA Sprint Goal should express a coherent objective the Increment achieves, and the Scrum Guide frames it as the purpose of the sprint rather than a count of items. Describing applicants being able to submit complete applications, with compliant data capture, captures both the business outcome and the audit constraint. Counting items reduces the goal to output. Estimate-size criteria say nothing about value. Full codebase coverage is an unrelated and unachievable technical target for one sprint.
-
6 Question 6 Single choice Transitioning into the Product Owner Role
A project manager has just been appointed Product Owner for an internal HR platform that is currently delivered through a fixed-scope waterfall contract. The project manager is used to owning the schedule and budget and is considering keeping the Gantt chart and the change-control board in place while the team begins Scrum. The sponsor wants the team to adopt Scrum within one quarter. Which action BEST supports the transition?
Choose one.Correct Answer: BExplanationReplacing the fixed requirements list with a single ordered Product Backlog, and agreeing a Product Goal and a regular review, moves the organisation toward the empirical model Scrum requires. Keeping the Gantt chart as the primary plan preserves the predictive model that Scrum replaces. Delegating the schedule splits accountability for value. Freezing scope with fixed dates reproduces the waterfall commitment the transition is meant to remove.
-
7 Question 7 Single choice Understanding the Product Owner Role
A Product Owner for a travel booking company notices that stakeholders are sending requests directly to individual Developers, who are reprioritising their work without telling the Product Owner. The Sprint Goal is at risk. The Product Owner wants to restore a single source of ordering for the work. Which action is MOST effective?
Choose one.Correct Answer: DExplanationThe Product Owner is accountable for ordering the Product Backlog, so routing all requests into that single ordered list and making the Product Owner the channel for priority changes restores clarity. Passing requests to the Scrum Master gives a facilitator a decision the Scrum Guide does not assign to them. A second backlog splits the source of truth. Letting Developers reorder the backlog removes the Product Owner's accountability for value ordering.
-
8 Question 8 Single choice Collaborating in the Sprint Meetings
During a Sprint Review for a government e-services portal, the Product Owner presents an Increment that is functionally complete but has two known performance defects that the Developers have logged. Stakeholders ask to accept the Increment as done so the next sprint can start. The Product Owner must decide how to handle the Sprint Review. Which action is the MOST appropriate?
Choose one.Correct Answer: BExplanationThe Sprint Review is for inspecting the Increment and adapting the Product Backlog, so transparency about known defects and stakeholder feedback is what the event is for. Marking work done while hiding defects misrepresents the Increment's state. Cancelling the review defeats inspection. Substituting mockups for the real Increment removes the empirical evidence the review depends on.
-
9 Question 9 Order list Working with the Product Backlog
A Product Owner must prepare a backlog item for a new customer-notification feature so that it can be selected at the next Sprint Planning. Choose the correct order of steps. Drag the steps into the correct order.
Drag the steps into the correct order, or use the arrows.
- Write the item with acceptance criteria and place it in the ordered Product Backlog.
- Confirm with the Developers that the refined item is understood and sized sufficiently.
- Re-order the Product Backlog so the item reflects its value relative to other items.
- Clarify the customer problem and the expected outcome with stakeholders.
Correct Answer:- Clarify the customer problem and the expected outcome with stakeholders.
- Write the item with acceptance criteria and place it in the ordered Product Backlog.
- Confirm with the Developers that the refined item is understood and sized sufficiently.
- Re-order the Product Backlog so the item reflects its value relative to other items.
ExplanationThe Product Owner first clarifies the problem and outcome with stakeholders, then writes the item with acceptance criteria. The Developers then confirm understanding and sizing through refinement, and the item is ordered in the backlog according to its value. Placing the item before clarifying it produces an item the team cannot size. Confirming sizing before the item is written reverses the dependency. Starting with Developer refinement before any stakeholder clarification leaves the team estimating an undefined problem.
-
10 Question 10 Order list Planning the Release
A Product Owner must plan a release that will be delivered over four sprints for a subscription-billing product. Choose the correct order of steps. Drag the steps into the correct order.
Drag the steps into the correct order, or use the arrows.
- Review the forecast and the release scope with stakeholders, and adjust scope as needed.
- Agree the Release Goal and the scope that must be included.
- Order the release scope by value and dependency.
- Forecast the release date using the observed range of velocity.
Correct Answer:- Agree the Release Goal and the scope that must be included.
- Order the release scope by value and dependency.
- Forecast the release date using the observed range of velocity.
- Review the forecast and the release scope with stakeholders, and adjust scope as needed.
ExplanationThe release planning sequence starts by agreeing the Release Goal and included scope, then orders that scope by value and dependency. Only after the scope is ordered can the Product Owner forecast the date from velocity. Stakeholders then review the forecast and adjust scope. Forecasting before scope is ordered gives a date for undefined work. Reviewing before the forecast exists means stakeholders have nothing to evaluate.
-
11 Question 11 Single choice Envisioning the Product
A Product Owner for a hospital scheduling product wants to communicate the product vision clearly to different audiences. Match each communication item to the element of the vision it best supports.
1. Statement of the patient outcome the product must improve
2. Measurable indicator that shows whether progress toward the outcome is real
3. Short-term commitment the Scrum Team will pursue during the next few sprints
Targets:
Target X: Product Goal
Target Y: Vision statement
Target Z: Key result measure
Choose the correct mapping.Correct Answer: CExplanationThe statement of the outcome patients should experience is the vision itself, the measurable indicator of progress is the key result measure, and the commitment the team pursues over the next few sprints is the Product Goal. Assigning the outcome to the Product Goal confuses a near-term commitment with the long-range vision. Mapping the measure to the vision mixes the indicator with the purpose. The remaining mapping swaps the Product Goal and the measure, which misplaces the short-term commitment.
-
12 Question 12 Single choice Working with the Product Backlog
A Product Owner is attributing the following backlog activities to their correct purpose. Match each activity to the backlog quality it primarily improves.
1. Splitting a large epic into smaller items that fit in one sprint
2. Adding acceptance criteria to each item
3. Ordering the items by value and risk
Targets:
Target X: Ordering
Target Y: Readiness for selection
Target Z: Clarity of expected result
Choose the correct mapping.Correct Answer: AExplanationSplitting an epic so items fit a sprint makes them ready for selection. Adding acceptance criteria clarifies the expected result. Ordering by value and risk establishes which items come first. The other mappings either assign the splitting activity to clarity of expected result, which is the job of acceptance criteria, or put ordering on acceptance criteria, which is not what ordering does.
-
13 Question 13 Dropdown Planning the Release
Choose the correct values. Choose the correct value for each blank.
Choose the correct value for each blank.
A Product Owner is reviewing a release forecast for a product with a 10-week deadline. The team completes sprints of two weeks, and the team's velocity over the last five sprints ranged from 26 to 41 story points. The Product Owner calculates the release capacity over the five remaining sprints using the worst observed velocity of points per sprint and the best of points per sprint.Correct Answer:A Product Owner is reviewing a release forecast for a product with a 10-week deadline. The team completes sprints of two weeks, and the team's velocity over the last five sprints ranged from 26 to 41 story points. The Product Owner calculates the release capacity over the five remaining sprints using the worst observed velocity of 26 points per sprint and the best of 41 points per sprint.
ExplanationThe worst observed velocity is 26 story points per sprint and the best is 41, which are the bounds the scenario gives. Multiplying by five sprints yields 130 and 205, which are totals rather than per-sprint values, so the choice pairing those totals with per-sprint labels is wrong. Using the average of 34 as the worst case misreads the range. Pairing 34 with 41 drops the true worst case.
-
14 Question 14 Dropdown Collaborating in the Sprint Meetings
Choose the correct values. Choose the correct value for each blank.
Choose the correct value for each blank.
A Scrum Team holds a Daily Scrum each morning. The Product Owner notices that the Daily Scrum has become a status report to the Product Owner, and the Developers direct their updates to the Product Owner rather than planning the next day's work. The Scrum Master wants the Daily Scrum to focus on progress toward the Sprint Goal. The Developers should answer questions, and the event should be time-boxed to minutes for a team of up to ten people.Correct Answer:A Scrum Team holds a Daily Scrum each morning. The Product Owner notices that the Daily Scrum has become a status report to the Product Owner, and the Developers direct their updates to the Product Owner rather than planning the next day's work. The Scrum Master wants the Daily Scrum to focus on progress toward the Sprint Goal. The Developers should answer three questions, and the event should be time-boxed to 15 minutes for a team of up to ten people.
ExplanationThe Scrum Guide's Daily Scrum is a fifteen-minute event for the Developers, which is time-boxed so the team can inspect progress toward the Sprint Goal and adapt the plan. The three-question structure is the common framing used to keep the event focused on progress and impediments. Sixty minutes is far longer than the fifteen-minute time-box. Status reporting to the Product Owner is the very behaviour the scenario says the Scrum Master wants to eliminate. A forty-five-minute box also exceeds the time-box.
These are 14 of the 80 questions in the full CASPO-001 pack.
Get All 80 QuestionsGet all 80 questions & answers
Full access options for GAQM CASPO-001
Self-study
PDF Version
- 80 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 80 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 80 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CASPO-001 Exam (Certified Agile Scrum Product Owner Exam) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.