Exam Information
Free practice questions with explanations
CIPS L6M9 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 16
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Understand the strategic nature and influence of supply network design
A regional white-goods manufacturer currently runs one large assembly plant that serves all four national distribution centres. Demand has grown unevenly, and the board is considering a second assembly site. Management wants the network to keep unit costs low on high-volume standard models while still responding quickly to regional variants that account for 15 per cent of sales. Lead times for regional variants must fall from six weeks to under two weeks. Capital is limited, and the company cannot exceed its current inventory holding levels. Which network configuration best meets these requirements?
Correct Answer: AExplanationThe regional finishing site keeps the scale benefits of the central plant for standard models while placing late-stage variant configuration close to demand, which is how a split or postponement network reduces lead time without raising total inventory. Consolidating into one plant leaves the six-week lead time unchanged for variants. Offshore outsourcing with extra safety stock breaks the inventory ceiling and does nothing for responsiveness. A full second plant in the most distant region exceeds the capital limit and still fails to serve the highest-demand areas quickly.
-
2 Question 2 Single choice Assess the strategic value of resource planning and control
A distributor of industrial fasteners runs its planning with a weekly material requirements cycle. Sales has begun accepting orders for delivery within 48 hours, and the warehouse reports that scheduled picking capacity is regularly exceeded on Mondays and Thursdays while idle on Wednesdays. Inventory accuracy is 91 per cent, and planners override system suggestions daily. The director wants to improve control of resources without adding headcount. Which action should be taken FIRST?
Correct Answer: BExplanationThe root issue is that loading ignores finite capacity, so the plan overloads certain days while others stand idle. Establishing accurate capacity-constrained loading and sequencing is the foundation of the resource planning and control process, and it must precede any judgement about inventory or staffing. Higher safety stock hides the capacity problem and conflicts with the need to control stock. A fortnightly cycle worsens responsiveness for 48-hour orders. Temporary staff adds cost without fixing the mismatch between load and available capacity, and the stem rules out adding headcount.
-
3 Question 3 Single choice Understand operations strategy and its contribution to overall business success
A mid-sized packaging company has grown from one product family to six and now competes on both price and delivery reliability. Its operations manager has written a strategy that lists cost reduction as the only performance objective, although the sales director reports that the three largest customers have recently switched suppliers because of late deliveries. The board wants the operations strategy to be genuinely aligned with the corporate plan, which emphasises premium service for key accounts. Which action best demonstrates that the operations strategy is aligned with business strategy?
Correct Answer: AExplanationOperations strategy is aligned when its performance objectives such as dependability, speed, quality, flexibility and cost reflect the market and corporate priorities, and when capacity and resource decisions are reconciled to them. Here the customer evidence shows dependability matters most, so restating objectives and checking capacity against them is the right step. A cost-only objective is exactly the misalignment that lost the accounts. Matching rival unit costs ignores the service dimension customers are rejecting. Handing delivery targets to sales separates a performance objective from the function that delivers it.
-
4 Question 4 Single choice Understand the strategic nature and influence of supply network design
A consumer electronics firm is deciding whether to make or buy a key subassembly. Internal production would require specialised tooling costing 4.2 million with a six-year life. The current supplier quotes a unit price 18 per cent below the firm's full internal cost but has suffered two quality escapes in the last year. The subassembly is not a source of competitive differentiation, and the firm has no internal design capability in this area. Which decision is most consistent with sound supply network design principles?
Correct Answer: AExplanationMake-or-buy decisions turn on whether the activity is a source of competitive advantage and whether the firm has the capability to run it well. Because the subassembly is non-differentiating and the firm lacks design capability, committing 4.2 million to tooling is hard to justify, while managing the supplier's quality through development and a second source addresses the escapes. Insourcing assumes internal production would avoid quality problems, which the stem gives no basis for. Acquisition is disproportionate for a non-core input. Offshoring without fixing the quality record ignores the evidence and adds lead time risk.
-
5 Question 5 Single choice Assess the strategic value of resource planning and control
A hospital pharmacy uses a planning system that releases purchase orders for consumables based on a monthly forecast. Clinical departments increasingly request urgent deliveries, and stock-outs of two items occurred last quarter. The pharmacy manager wants to establish a control loop that detects deviation early and corrects the plan. Which mechanism most directly provides this control?
Correct Answer: AExplanationMonitoring and control in resource planning means comparing actual performance against the schedule, using tolerances to decide when intervention is needed, and feeding the result back into loading and sequencing. Consumption tracked against tolerances will surface the urgent demand earlier than a monthly cycle does. A longer horizon and annual review worsen responsiveness. Universal buffer stock raises cost and ties up space without giving the planner information to act on.
-
6 Question 6 Single choice Understand operations strategy and its contribution to overall business success
A furniture manufacturer uses a four-stage model to assess how its operations function supports strategy. Its current stage is internal neutrality: operations simply executes the plans that marketing and finance produce. The chief executive wants operations to contribute to competitive advantage through its design and capacity choices. Which step represents the most appropriate next move towards the higher stages?
Correct Answer: BExplanationThe four-stage model moves operations from internal neutrality, where it merely implements, towards external neutrality and beyond, where its capabilities shape competitive choices. Involving operations in strategy formulation so that capacity and process capabilities are considered alongside market requirements is the mechanism that progresses it. Moving supplier selection to marketing removes a capability from operations rather than strengthening it. Freezing investment and cutting headcount both reduce the function's ability to contribute.
-
7 Question 7 Single choice Understand the strategic nature and influence of supply network design
A software-enabled hardware company sells direct online to customers and through two retail partners. Its management has noticed that the retail partners are receiving the same products through a separate distribution route, and online margins are being eroded by channel conflict. The company is reviewing whether disintermediation can improve its position. Which consideration is most important when deciding whether to bypass the retailers?
Correct Answer: AExplanationDisintermediation is attractive only where the firm can perform the intermediary's value-adding activities, such as local stock holding, returns handling and customer contact, at lower total cost than the intermediary charges. The relevant comparison is cost to serve against the margin given up, not the simple removal of a layer. Assuming internet channels remove logistics ignores the physical movement of goods. Fewer intermediaries does not reduce supplier management. Retailer volume matters, but the decision turns on the firm's capability to absorb the functions.
-
8 Question 8 Single choice Assess the strategic value of resource planning and control
A regional food distributor runs three depots. The planning team uses a common scheduling rule: orders are loaded in order of receipt, and each depot's vehicles are scheduled to full capacity. Customers with chilled-product contracts are complaining of late deliveries, while ambient-product orders are delivered early. Management wants to align prioritisation with customer service commitments without increasing fleet size. Which change best addresses the problem?
Correct Answer: BExplanationThe planning system loads by receipt date, which ignores the priority that contracts and perishability should impose. Introducing prioritisation and sequencing rules based on service commitment and product characteristics corrects the allocation within existing capacity, which is what the brief asks for. Buying vehicles breaks the no-fleet-increase constraint. First-in-last-out makes the sequencing arbitrary and does not reflect commitments. Outsourcing chilled work changes the cost base and does not address the prioritisation logic itself.
-
9 Question 9 Multiple choice Understand the strategic nature and influence of supply network design
A pharmaceutical company is reconfiguring its supply network after a merger. Its management wants the network to be resilient to single-site disruption while keeping the number of suppliers manageable for regulatory audit. Which TWO actions best support this objective? (Choose two.)
Correct Answer: B, DExplanationResilience against single-site disruption is built by qualifying an alternative site for critical volume and by holding buffer stock at a location not exposed to the same risk, both of which keep the network functioning if the primary source fails. Consolidating packaging or excipients to one supplier increases the very exposure the company wants to avoid. Concentrating all production in one low-cost region creates a single point of failure.
-
10 Question 10 Single choice Understand operations strategy and its contribution to overall business success
A precision engineering firm has set operations objectives for quality, speed, dependability, flexibility and cost. Its managers disagree about how to rank them. The sales team says the firm's customers are buying on delivery reliability and fast response to engineering changes, while the finance team argues that unit cost must remain the leading measure. The operations manager must decide how to set priorities that are defensible. Which approach is most appropriate?
Correct Answer: CExplanationPerformance objectives should be prioritised by what the market actually requires, distinguishing order-winners from qualifiers, and the firm must recognise that some objectives trade off against each other. Ranking by internal budget influence or historical order reflects organisational politics rather than customer need. Giving equal weight prevents any real strategic choice from being made.
-
11 Question 11 Single choice Understand the strategic nature and influence of supply network design
A components manufacturer is choosing between offshoring production to a low-cost country and keeping production in its home country where its primary customers are located. Offshoring would lower the landed unit cost by 11 per cent, but the lead time to the main customer would rise from 5 days to 28 days. The customer contract penalises late delivery, and the product is ordered with short notice. Which conclusion is best supported by these facts?
Correct Answer: AExplanationThe 28-day lead time directly conflicts with short-notice ordering and the late-delivery penalty, so offshoring the whole volume would breach the service requirement. Splitting the network, with forecast-driven volume offshore and responsive volume near the customer, captures part of the saving without violating the constraint. Larger shipments do not remove a 28-day transit for short-notice orders. Offshoring is not always more expensive, so the rejection rule is wrong. Passing penalties to customers ignores the service obligation the stem describes.
-
12 Question 12 Order list Assess the strategic value of resource planning and control
A distribution centre manager is introducing a finite-capacity loading and monitoring cycle for outbound orders. Arrange them into the correct sequence. Drag the steps into the correct order.
Drag the steps into the correct order, or use the arrows.
- Compare actual picking output with the scheduled load at defined checkpoints.
- Sequence the loaded orders by service priority and release them to the floor.
- Capture confirmed orders and current stock positions in the planning system.
- Replan the schedule where variance exceeds the agreed tolerance.
- Load orders against available labour and dock capacity for each shift.
Correct Answer:- Capture confirmed orders and current stock positions in the planning system.
- Load orders against available labour and dock capacity for each shift.
- Sequence the loaded orders by service priority and release them to the floor.
- Compare actual picking output with the scheduled load at defined checkpoints.
- Replan the schedule where variance exceeds the agreed tolerance.
ExplanationThe loop begins with accurate information on confirmed orders and stock, then loads orders against finite capacity, then sequences them by priority and releases them. Monitoring compares actual output with the plan, and replanning is triggered only when variance breaches tolerance. Sequencing before loading would order work that has not yet been checked against capacity. Monitoring before release would compare against a schedule that does not yet exist. Replanning before measurement would correct nothing.
-
13 Question 13 Drag and drop Understand operations strategy and its contribution to overall business success
A consumer goods company is mapping its performance objectives to the decisions that support them. Match each performance objective to the operations decision that most directly delivers it. Drag each item onto its matching target.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
SpeedDependabilityFlexibilityReducing queue and throughput times through process and layout redesignMaintaining a single long production run to minimise changeover lossesHolding planned buffer capacity so that schedules can be met despite disruptionCorrect Answer:- Dependability → Holding planned buffer capacity so that schedules can be met despite disruption
- Flexibility → Maintaining a single long production run to minimise changeover losses
- Speed → Reducing queue and throughput times through process and layout redesign
ExplanationDependability is delivered by buffer capacity that protects schedule adherence, flexibility by the ability to change products and volumes, and speed by reducing throughput time through process design. Long production runs maximise efficiency at the expense of flexibility, so they are a flexibility trade-off rather than a dependability tool. Assigning P to dependability reverses the link. Redesigning layout for throughput is a speed decision, not a flexibility decision, which rules out R for flexibility.
-
14 Question 14 Dropdown Understand the strategic nature and influence of supply network design
Choose the correct value for each blank.
Choose the correct value for each blank.
A manufacturer's network analysis shows that its plant has a fixed capacity of 40,000 units per month, while forecast demand averages 52,000 units with a peak of 61,000 units. The planning director proposes to meet peak demand by contracting extra capacity from an external partner. Management must decide how much capacity to buy from the partner and how to treat the residual gap. The network design principle that governs the choice of optimum capacity is that capacity should be sized to demand, and any shortfall in internal capacity should be covered by capacity rather than by permanently enlarging the internal footprint.
Correct Answer:A manufacturer's network analysis shows that its plant has a fixed capacity of 40,000 units per month, while forecast demand averages 52,000 units with a peak of 61,000 units. The planning director proposes to meet peak demand by contracting extra capacity from an external partner. Management must decide how much capacity to buy from the partner and how to treat the residual gap. The network design principle that governs the choice of optimum capacity is that capacity should be sized to average demand, and any shortfall in internal capacity should be covered by flexible external capacity rather than by permanently enlarging the internal footprint.
average
flexible externalExplanationSizing internal capacity to the average load and covering variation through flexible external capacity avoids the cost of idle plant during low periods while still serving peaks, which is the logic behind the optimum-capacity decision. Sizing to peak demand leaves the plant underused most of the year and fixed internal expansion is the costly option the stem warns against. Sizing to the minimum leaves a permanent gap that the partner would need to fill, and a permanent external arrangement is not the flexible response being sought. Sizing to the maximum with fixed internal capacity compounds the idle-capacity cost.
-
15 Question 15 Single choice Assess the strategic value of resource planning and control
A drinks bottler runs a single production line that must switch between twelve product variants. Changeover takes 45 minutes, and the planning team currently sequences runs by due date alone, creating frequent changeovers and missed flavour-specific orders. The operations director asks for a change that reduces changeover losses while still meeting due dates. Which sequencing approach best meets the requirement?
Correct Answer: AExplanationSequencing that groups similar variants reduces the number of changeovers while keeping the schedule aligned with due dates, which balances the trade-off the stem describes. Due-date-only sequencing is the current cause of excess changeovers, and overtime adds cost without reducing the losses. Running largest volumes first defers orders that the customer is waiting for. A single batch of twelve variants cannot meet due dates for each product and is not achievable on one line with unlimited changeover avoidance.
-
16 Question 16 Single choice Understand operations strategy and its contribution to overall business success
A mid-sized textile company wants its operations strategy to contribute to competitive advantage. Its strategy is currently a list of targets for output volume and labour productivity, with no explicit statement of what customers value or how capacity and resources will be committed over the next three years. The managing director asks for a revision that is testable. Which revision best meets this need?
Correct Answer: AExplanationA testable operations strategy states a clear vision and objectives, links them to market requirements, and reconciles strategic decisions to capacity and resources over specific timescales and outputs. More productivity targets address only one dimension and remain untethered to customer value. Copying a competitor ignores the company's own market and resources. Removing quantitative targets makes the strategy impossible to test.
These are 16 of the 84 questions in the full L6M9 pack.
Get All 84 QuestionsGet all 84 questions & answers
Full access options for CIPS L6M9
Self-study
PDF Version
- 84 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 84 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 84 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the L6M9 Exam (Supply Network Design) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.