Exam Information
Free practice questions with explanations
CIPS L6M5 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 14
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Understand contracting for programmes
A government agency is procuring a 36-month rail depot upgrade. The scope is well defined, but the agency's engineers expect design changes once ground surveys are complete, and the agency wants the contractor to take responsibility for detailed design, procurement of long-lead equipment and construction under a single point of accountability. The agency has limited in-house engineering capacity and wants to avoid managing multiple interface contracts. Which contract form is MOST appropriate?
Correct Answer: BExplanationAn EPC contract places detailed design, procurement and construction with one contractor under a single point of responsibility, which matches the agency's need to avoid interface management. Management contracting and construction management leave trade packages and interfaces with the client, contrary to the stated constraint. A design-and-build contract with completed agency design would transfer the design risk back to the agency, which the stem explicitly rules out given expected design changes.
-
2 Question 2 Single choice Understand contracting for programmes
A utility plans a 25-year waste-to-energy facility. The utility wants the private partner to finance the plant, build it, and operate it for the concession period before transferring ownership back. Lenders require that revenue risk be borne by the operator, and the utility wants the asset's whole-life performance to be the operator's responsibility. Which forms of contract best describe this arrangement?
Correct Answer: AExplanationA build-operate-transfer structure fits because the private partner finances, builds and operates for the concession period and then transfers the asset, with revenue and performance risk sitting with the operator as lenders require. Retaining ownership and revenue risk with the utility contradicts the stated risk allocation. Splitting construction and operations into separate contracts breaks the whole-life responsibility the utility wants, and a management contract with availability payments leaves lifecycle risk with the utility.
-
3 Question 3 Single choice Understand programme leadership approaches
A programme manager is reviewing a supplier's cost proposal for a multi-year equipment programme. The buyer wants to reduce unit cost without reducing the performance specification, and has agreed to share savings with the supplier. The supplier has offered its cost breakdown, but the buyer's team cannot yet verify labour rates or overhead allocations. Which cost transparency mechanism should the buyer adopt FIRST to achieve its aim while maintaining trust?
Correct Answer: AExplanationOpen book costing gives the buyer visibility of labour rates, overheads and margins, and with audit rights and a shared cost model the buyer can verify the cost base needed for savings-sharing. Fixed lump sum pricing would hide the cost drivers the buyer needs to test. A target cost incentive with a confidential cost model fails the verification requirement, and re-tendering before any analysis discards the existing relationship without first establishing the cost facts.
-
4 Question 4 Single choice Understand programme leadership approaches
A programme's earned value report shows a cost performance index of 0.82 and a schedule performance index of 0.95 at the end of month 14 of a 30-month programme. The steering board has asked for a remedial action plan within the reporting cycle. Budget at completion is unchanged and the sponsor will not approve scope reduction. Which action is the MOST appropriate NEXT step?
Correct Answer: AExplanationWith a CPI of 0.82 the programme is overspending, and before any remedy is chosen the cause must be located, so variance analysis by work package is the right next step and feeds directly into remedial actions. Re-baselining would conceal the overrun, which the steering board is trying to address and the budget is not being changed. Requesting funding skips the diagnosis, and freezing changes and cancelling variations risks disputes and does not address root causes.
-
5 Question 5 Single choice Understand programme leadership approaches
A contractor delivering a 20-month logistics programme has run 9 weeks behind its contractual milestone because the client issued late design information. The client's contract includes a compensation event clause requiring notification within 8 weeks of becoming aware of the delay. The contractor's project manager became aware of the delay 5 weeks ago but has not yet notified the client, and the client's delay is now contributing to a second, unrelated shortfall in supplier deliveries. Which action should the contractor take FIRST?
Correct Answer: AExplanationThe contractor became aware of the delay 5 weeks ago, so the 8-week notification window is still open and the first priority is to notify the client of the compensation event in time to preserve entitlement. Waiting for the client to raise the issue risks losing the right to compensation. The supplier shortfall needs its own assessment and cannot be claimed before the original event has been properly notified, and arbitration is premature without formal notification and a chance to resolve the matter contractually.
-
6 Question 6 Single choice Understand contracting for programmes
A consortium is bidding for a public-private partnership to deliver hospital accommodation. The public authority requires the private partner to demonstrate that its financing structure, equity and debt arrangements, and service delivery responsibilities are clearly separated, and that the private partner bears availability risk. Which element of the PPP structure is MOST directly responsible for meeting the authority's requirement that the private partner bears availability risk?
Correct Answer: AExplanationA unitary charge with availability deductions is the mechanism through which payment to the private partner depends on the facility being available to the required standard, so availability risk transfers to the partner. A special purpose vehicle structures the financing and ring-fences liabilities but does not itself allocate availability risk. Lender step-in rights protect finance providers after default, and a capital grant transfers funding rather than performance risk.
-
7 Question 7 Single choice Understand contracting for programmes
A programme manager is comparing contract forms for a multi-phase infrastructure programme. The client expects scope to evolve across phases, wishes to retain the option to change the contractor's scope, and wants a form with clear compensation event and early warning procedures. The client's legal team is wary of any form that introduces ambiguity over design responsibility. Which is the BEST choice of standard form for this programme?
Correct Answer: AExplanationThe NEC engineering and construction contract is built around early warning and compensation event procedures and allows option clauses to be selected to match the programme, which suits evolving scope. The JCT form and a bespoke short form would not provide the same compensation event mechanism, and the FIDIC red book, with design left to the employer, would leave the design ambiguity the legal team wants to avoid. The chosen form must give clear procedures and design responsibility simultaneously.
-
8 Question 8 Single choice Understand programme leadership approaches
A supplier has defaulted on a 12-month delivery programme, causing the buyer to incur additional expediting costs and lost production revenue. The contract limits liability for consequential loss to direct losses only and includes a liquidated damages clause at a fixed daily rate. The buyer's analysis shows the actual loss exceeds the liquidated damages cap. Which remedy is the buyer MOST likely to be able to recover in full under the contract terms?
Correct Answer: AExplanationExpediting costs incurred to recover from the default are direct losses flowing from the supplier's failure, so they fall within the liability regime the contract allows. Lost production revenue is excluded as consequential loss, and the liquidated damages cap prevents recovery above the agreed sum for delay. Specific performance is an equitable remedy that a court may refuse for supply contracts and is not a monetary recovery of loss.
-
9 Question 9 Multiple choice Understand contracting for programmes
A government department is planning a long-term programme for maintaining a national road network and wants a contract form that allocates design responsibility and gives the contractor an incentive to reduce whole-life costs. Which TWO features of a design, build, operate and maintain arrangement would BEST meet these requirements? (Choose two.)
Correct Answer: D, EExplanationMaking the contractor responsible for design, construction and lifecycle maintenance, with payment tied to long-term performance, aligns incentives so that lower whole-life cost benefits the contractor. Cost-plus reimbursement removes the incentive to reduce cost, and retaining design with the department reintroduces the allocation problem. Annual re-tendering of maintenance undermines the integrated long-term responsibility and makes whole-life performance a separate, short-term contest.
-
10 Question 10 Multiple choice Understand programme leadership approaches
A programme director is implementing value engineering on a complex plant build that has exceeded its cost target by 14 percent. The director wants to reduce cost without degrading required performance and without breaching the contract. Which TWO actions would be MOST appropriate? (Choose two.)
Correct Answer: B, DExplanationValue engineering starts with functional analysis that tests each cost element against the performance requirement, and proposals for alternatives are then submitted through the contract's change procedure so the client can approve them. Removing a safety feature or lowering specification without client knowledge breaches the contract and the client's trust. Deferring maintenance design without assessment shifts cost and risk to later phases rather than reducing whole-life cost.
-
11 Question 11 Order list Understand programme leadership approaches
A programme manager needs to close a multi-year programme with a supplier. The programme is ending with outstanding variations, unresolved claims and warranty periods still running. The manager must finalise the closure in a defensible sequence. Drag the steps into the correct order.
Drag the steps into the correct order, or use the arrows.
- Issue the final payment certificate and release retentions after the defects or warranty period
- Record lessons learned and archive contract and performance records
- Confirm acceptance of the deliverables against the contract specification
- Agree the final account and settle outstanding variations and claims
Correct Answer:- Confirm acceptance of the deliverables against the contract specification
- Agree the final account and settle outstanding variations and claims
- Issue the final payment certificate and release retentions after the defects or warranty period
- Record lessons learned and archive contract and performance records
ExplanationAcceptance of deliverables must be confirmed first so that the final account and variations can be settled against what was actually delivered. Once the final account is agreed the final payment certificate can be issued and retentions released after the warranty period, and lessons learned and archiving close the programme. Settling the final account before confirming acceptance would fix a price for work not yet verified, and releasing retentions before the warranty period ends removes the client's security.
-
12 Question 12 Order list Understand programme leadership approaches
A programme team is preparing a budget estimate for a new infrastructure phase of a rail programme. The team wants a defensible budget that can later support variance analysis and control. Drag the steps into the correct order.
Drag the steps into the correct order, or use the arrows.
- Set control thresholds and reporting mechanisms for tracking actual cost against baseline
- Establish a work breakdown structure and cost estimate for each work package
- Identify and quantify risks and add contingency reserves to the estimate
- Agree the cost baseline and approve the budget with the sponsor
Correct Answer:- Establish a work breakdown structure and cost estimate for each work package
- Identify and quantify risks and add contingency reserves to the estimate
- Agree the cost baseline and approve the budget with the sponsor
- Set control thresholds and reporting mechanisms for tracking actual cost against baseline
ExplanationThe work breakdown structure and work package estimates come first, followed by identifying risks and adding contingency so the estimate includes them. The cost baseline is then agreed and approved, and only after that are control thresholds and reporting set to track actual cost against that baseline. Approving the budget before estimating or adding contingency would fix a baseline without the cost content it needs to be monitored against.
-
13 Question 13 Dropdown Understand contracting for programmes
Which pair of values correctly completes the statement? Choose the correct value for each blank.
Choose the correct value for each blank.
A programme manager is reviewing a lump sum contract for a plant upgrade. The contract's pricing schedule is split into two elements, and the manager needs the correct description of each. Under a fixed lump sum arrangement the contractor's price for the defined scope is set at tender and is by changes to quantities, while a schedule of rates is typically used where quantities are uncertain and the employer pays for work at the agreed unit rates.Correct Answer:A programme manager is reviewing a lump sum contract for a plant upgrade. The contract's pricing schedule is split into two elements, and the manager needs the correct description of each. Under a fixed lump sum arrangement the contractor's price for the defined scope is set at tender and is not adjusted by changes to quantities, while a schedule of rates is typically used where quantities are uncertain and the employer pays for work actually measured and carried out at the agreed unit rates.
ExplanationA fixed lump sum price is set for the defined scope and is not adjusted for changes in quantities, whereas a schedule of rates pays for the quantities actually measured and carried out at the agreed unit rates. The other pairings reverse or misstate the basis of payment, and the fixed lump sum variant that is paid on completion would not describe a schedule of rates.
-
14 Question 14 Dropdown Understand programme leadership approaches
A programme's earned value dataset shows the following for a work package: budgeted cost of work scheduled (PV) of 400,000, budgeted cost of work performed (EV) of 340,000, and actual cost of work performed (AC) of 380,000. The cost variance is calculated as EV minus AC, and the cost performance index is calculated as EV divided by AC. The programme manager reports the result to the steering board. Choose the correct value for each blank.
Choose the correct value for each blank.
The cost variance is and the cost performance index is .Correct Answer:The cost variance is -40,000 and the cost performance index is 0.89.
ExplanationCost variance is EV minus AC, which is 340,000 minus 380,000 giving -40,000, and the cost performance index is EV divided by AC, which is 340,000 divided by 380,000, approximately 0.89. Option B and D reverse the sign convention or the division, and option C uses PV rather than EV in the variance calculation, which is the schedule-based figure, not the cost variance.
These are 14 of the 83 questions in the full L6M5 pack.
Get All 83 QuestionsGet all 83 questions & answers
Full access options for CIPS L6M5
Self-study
PDF Version
- 83 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 83 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 83 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the L6M5 Exam (Strategic Programme Leadership) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.