2026 Actual CIPS L6M5 Dumps, Updated Exam Questions for Guaranteed Pass

Strategic Programme Leadership - Free Practice Questions with Explanations, Exam Dumps, and Complete Practice Pack from DumpsProvider.

Exam Information

VendorCIPS
Exam codeL6M5
Exam nameStrategic Programme Leadership
Questions in pack83
Last updatedNovember 21, 2026
Related certificationsLevel 6 Professional Diploma in Procurement and Supply

Free practice questions with explanations

CIPS L6M5 Practice Questions

Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.

Questions
14
Answered
0
Correct
0
Score
-
  1. 1 Question 1 Single choice Understand contracting for programmes

    A government agency is procuring a 36-month rail depot upgrade. The scope is well defined, but the agency's engineers expect design changes once ground surveys are complete, and the agency wants the contractor to take responsibility for detailed design, procurement of long-lead equipment and construction under a single point of accountability. The agency has limited in-house engineering capacity and wants to avoid managing multiple interface contracts. Which contract form is MOST appropriate?

  2. 2 Question 2 Single choice Understand contracting for programmes

    A utility plans a 25-year waste-to-energy facility. The utility wants the private partner to finance the plant, build it, and operate it for the concession period before transferring ownership back. Lenders require that revenue risk be borne by the operator, and the utility wants the asset's whole-life performance to be the operator's responsibility. Which forms of contract best describe this arrangement?

  3. 3 Question 3 Single choice Understand programme leadership approaches

    A programme manager is reviewing a supplier's cost proposal for a multi-year equipment programme. The buyer wants to reduce unit cost without reducing the performance specification, and has agreed to share savings with the supplier. The supplier has offered its cost breakdown, but the buyer's team cannot yet verify labour rates or overhead allocations. Which cost transparency mechanism should the buyer adopt FIRST to achieve its aim while maintaining trust?

  4. 4 Question 4 Single choice Understand programme leadership approaches

    A programme's earned value report shows a cost performance index of 0.82 and a schedule performance index of 0.95 at the end of month 14 of a 30-month programme. The steering board has asked for a remedial action plan within the reporting cycle. Budget at completion is unchanged and the sponsor will not approve scope reduction. Which action is the MOST appropriate NEXT step?

  5. 5 Question 5 Single choice Understand programme leadership approaches

    A contractor delivering a 20-month logistics programme has run 9 weeks behind its contractual milestone because the client issued late design information. The client's contract includes a compensation event clause requiring notification within 8 weeks of becoming aware of the delay. The contractor's project manager became aware of the delay 5 weeks ago but has not yet notified the client, and the client's delay is now contributing to a second, unrelated shortfall in supplier deliveries. Which action should the contractor take FIRST?

  6. 6 Question 6 Single choice Understand contracting for programmes

    A consortium is bidding for a public-private partnership to deliver hospital accommodation. The public authority requires the private partner to demonstrate that its financing structure, equity and debt arrangements, and service delivery responsibilities are clearly separated, and that the private partner bears availability risk. Which element of the PPP structure is MOST directly responsible for meeting the authority's requirement that the private partner bears availability risk?

  7. 7 Question 7 Single choice Understand contracting for programmes

    A programme manager is comparing contract forms for a multi-phase infrastructure programme. The client expects scope to evolve across phases, wishes to retain the option to change the contractor's scope, and wants a form with clear compensation event and early warning procedures. The client's legal team is wary of any form that introduces ambiguity over design responsibility. Which is the BEST choice of standard form for this programme?

  8. 8 Question 8 Single choice Understand programme leadership approaches

    A supplier has defaulted on a 12-month delivery programme, causing the buyer to incur additional expediting costs and lost production revenue. The contract limits liability for consequential loss to direct losses only and includes a liquidated damages clause at a fixed daily rate. The buyer's analysis shows the actual loss exceeds the liquidated damages cap. Which remedy is the buyer MOST likely to be able to recover in full under the contract terms?

  9. 9 Question 9 Multiple choice Understand contracting for programmes

    A government department is planning a long-term programme for maintaining a national road network and wants a contract form that allocates design responsibility and gives the contractor an incentive to reduce whole-life costs. Which TWO features of a design, build, operate and maintain arrangement would BEST meet these requirements? (Choose two.)

  10. 10 Question 10 Multiple choice Understand programme leadership approaches

    A programme director is implementing value engineering on a complex plant build that has exceeded its cost target by 14 percent. The director wants to reduce cost without degrading required performance and without breaching the contract. Which TWO actions would be MOST appropriate? (Choose two.)

  11. 11 Question 11 Order list Understand programme leadership approaches

    A programme manager needs to close a multi-year programme with a supplier. The programme is ending with outstanding variations, unresolved claims and warranty periods still running. The manager must finalise the closure in a defensible sequence. Drag the steps into the correct order.

    Drag the steps into the correct order, or use the arrows.

    1. Issue the final payment certificate and release retentions after the defects or warranty period
    2. Record lessons learned and archive contract and performance records
    3. Confirm acceptance of the deliverables against the contract specification
    4. Agree the final account and settle outstanding variations and claims
  12. 12 Question 12 Order list Understand programme leadership approaches

    A programme team is preparing a budget estimate for a new infrastructure phase of a rail programme. The team wants a defensible budget that can later support variance analysis and control. Drag the steps into the correct order.

    Drag the steps into the correct order, or use the arrows.

    1. Set control thresholds and reporting mechanisms for tracking actual cost against baseline
    2. Establish a work breakdown structure and cost estimate for each work package
    3. Identify and quantify risks and add contingency reserves to the estimate
    4. Agree the cost baseline and approve the budget with the sponsor
  13. 13 Question 13 Dropdown Understand contracting for programmes

    Which pair of values correctly completes the statement? Choose the correct value for each blank.

    Choose the correct value for each blank.

    A programme manager is reviewing a lump sum contract for a plant upgrade. The contract's pricing schedule is split into two elements, and the manager needs the correct description of each. Under a fixed lump sum arrangement the contractor's price for the defined scope is set at tender and is by changes to quantities, while a schedule of rates is typically used where quantities are uncertain and the employer pays for work at the agreed unit rates.
  14. 14 Question 14 Dropdown Understand programme leadership approaches

    A programme's earned value dataset shows the following for a work package: budgeted cost of work scheduled (PV) of 400,000, budgeted cost of work performed (EV) of 340,000, and actual cost of work performed (AC) of 380,000. The cost variance is calculated as EV minus AC, and the cost performance index is calculated as EV divided by AC. The programme manager reports the result to the steering board. Choose the correct value for each blank.

    Choose the correct value for each blank.

    The cost variance is and the cost performance index is .

These are 14 of the 83 questions in the full L6M5 pack.

Get All 83 Questions

Get all 83 questions & answers

742 Satisfied customers
94.1% Pass rate feedback
84.1% Said questions matched
95% Found material helpful

Full access options for CIPS L6M5

Self-study

PDF Version

$40.00 $20.00
  • 83 actual exam questions
  • Compatible with all devices
  • Printable PDF format
  • No download limits
  • 90 days free updates
  • 24/7 customer support

Exam simulation

Online Practice Test

$50.00 $25.00
  • 83 actual exam questions
  • Actual exam environment
  • 90 days free updates
  • Browser-based software
  • 24/7 customer support

100% Money Back Guarantee

Your success comes first

At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the L6M5 Exam (Strategic Programme Leadership) on your very first attempt.

In a rare case, if you fail your exam, we will refund your amount without asking a single question.

100%

Security & Privacy

10000+

Satisfied Customers

24/7

Committed Service

100%

Money Back Guranteed