Exam Information
Free practice questions with explanations
CIPS L5M7 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 16
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Understand improvement methodologies that can be used in supply chains
A regional food manufacturer sources packaging film from a single converter. Over the last quarter, the converter's incoming lots have been released after 100% inspection, yet line stoppages caused by film splits have risen. The procurement director wants to move from detecting defects to preventing them, and the converter is willing to share its process data but has a small quality team. Which action should the procurement team take FIRST?
Correct Answer: DExplanationMoving from inspection to prevention means building quality into the process, and the first step is understanding whether the converter's process is capable and in control. A joint capability study using its existing control chart data gives evidence of where splits originate without adding cost. Raising inspection sampling only increases detection, which the scenario has already shown is insufficient. Safety stock hides the problem rather than fixing it, and switching suppliers before diagnosing the cause risks repeating the same failure with a new source.
-
2 Question 2 Single choice Understand measures required to achieve competitive advantage in supply chains
A medical device company is choosing between two pricing structures for a three-year contract to supply precision machined housings. The supplier has a volatile raw material input whose cost moves by up to 20 percent per year. The buyer wants to share the benefit of supplier productivity gains while protecting the supplier from extreme material price swings, and it has agreed open book access to the supplier's cost base. The contract must also avoid rewarding the supplier for cost inflation it cannot control. Which pricing arrangement is MOST appropriate?
Correct Answer: DExplanationA fixed base price with an index-linked adjustment for the volatile input isolates the material risk that the supplier cannot control, while a gain share on productivity rewards the supplier for improvements that the buyer also benefits from. A fixed price for three years would expose the supplier to large material swings and invite supply failure. Cost plus a percentage fee rewards the supplier for higher costs, which the scenario explicitly rules out. A pure variable price passes all cost movement to the buyer and offers no incentive for productivity.
-
3 Question 3 Single choice Understand the dynamics of supply chains
A consumer electronics firm currently manages its contract manufacturer as a direct tier one supplier. Its procurement team discovers that a critical capacitor shortage has originated with a tier three sub-supplier that the firm has never audited, and the tier one supplier has been allocating scarce output to other customers. The firm wants to reduce supply vulnerability without breaking the existing tier one relationship or adding a full second sourcing program within six months. Which action is the BEST next step?
Correct Answer: BExplanationNetwork visibility is the foundation for managing supply vulnerability in a multi-tier chain, and requiring the tier one supplier to disclose and map its sub-tier base respects the existing relationship while revealing single points of failure. Bypassing the tier one supplier with a direct purchase order damages the contractual relationship and may breach exclusivity terms. Terminating the contract is disproportionate and disruptive within six months. Raising volumes does not address the hidden tier three dependency and may simply reward an allocation problem.
-
4 Question 4 Single choice Understand improvement methodologies that can be used in supply chains
A procurement team is monitoring the delivery lead time of a bought-in fastener supplied to an assembly plant. Over 60 consecutive daily samples the mean lead time is 5.0 days with a standard deviation of 0.4 days, and the process is stable. The plant requires that at least 99.7 percent of deliveries arrive within 6.2 days to avoid line disruption. Assuming the data are normally distributed, what is the MOST appropriate conclusion?
Correct Answer: BExplanationWith a mean of 5.0 and standard deviation of 0.4, the 6.2 day limit sits exactly three standard deviations above the mean, which corresponds to roughly 99.7 percent of a normal distribution lying below it. The stability of the process means the normal model is a reasonable basis for the judgement. Treating the mean being below the limit as a failure misreads a one-sided specification. Two standard deviations would be 5.8 days, not 6.2, so that reading is arithmetically wrong. Sample size is not the limiting issue here, since 60 stable observations already support a capability estimate.
-
5 Question 5 Single choice Understand measures required to achieve competitive advantage in supply chains
A retailer buys seasonal apparel from four suppliers. It is considering consolidating volume into one supplier to obtain a lower unit price. Its category analysis shows that the four suppliers differ materially in responsiveness: two can deliver mid-season replenishment within ten days, while the other two need six weeks. The retailer's differentiation strategy depends on fast fashion replenishment, and the consolidated supplier would only offer the lower price on a single-source basis. Which course of action gives the retailer the GREATEST sustainable advantage?
Correct Answer: BExplanationAggregating volume with the two responsive suppliers preserves the speed capability that underpins the differentiation strategy, while volume commitments give the buyer leverage to negotiate price reductions. Consolidating with the cheapest supplier secures unit cost but removes the replenishment speed that drives the advantage. Splitting equally across all four dilutes volume so that no supplier has an incentive to invest and loses aggregation benefits. Moving to the slow suppliers sacrifices the core capability for a marginal unit price gain.
-
6 Question 6 Single choice Understand the dynamics of supply chains
A bank is redesigning its procurement operating model after a supplier onboarding delay of nine months. The current structure places sourcing, contract management and supplier performance in three separate departments, each with its own systems, and there is no shared process owner for the end-to-end sourcing lifecycle. The CPO wants the change to improve value delivery without a large headcount increase, and the board has stated that any new structure must keep regulatory approval steps for high-risk suppliers. Which change is MOST likely to deliver the required improvement?
Correct Answer: AExplanationThe delay stems from fragmented ownership of a single lifecycle, so a single process owner with shared measures addresses the organisational infrastructure and process management problem directly without adding headcount. Removing regulatory approval breaches a stated board constraint. Adding headcount conflicts with the cost requirement and does not fix hand-offs between departments. Replacing systems while leaving reporting lines unchanged leaves the ownership gap in place, so the handoffs that cause the delay remain.
-
7 Question 7 Single choice Understand improvement methodologies that can be used in supply chains
A supplier of injection-moulded parts to an automotive assembler has been asked to adopt just-in-time delivery to reduce the buyer's inventory. The supplier's changeover times are long and its output is variable, and the buyer's line has a minimal buffer. Over the first two months, the supplier has missed call-off windows on 12 percent of deliveries, causing expedited freight costs that exceed the inventory savings. The buyer wants to keep the JIT objective. Which action should the buyer take NEXT?
Correct Answer: DExplanationJIT depends on process stability and short changeovers, and the missed windows trace to the supplier's internal variability, so the sensible next step is joint work on changeover reduction and stability. Holding finished goods at the supplier pushes inventory upstream without solving the variability, and it does not remove the cost the buyer is trying to avoid. Reverting to batch deliveries abandons the objective entirely. Moving the business for proximity addresses transport time, which is not the cause of the missed windows.
-
8 Question 8 Multiple choice Understand measures required to achieve competitive advantage in supply chains
A logistics company is negotiating a three-year contract for warehousing services with a provider that will operate a dedicated site. The buyer wants a gain share arrangement that rewards the provider for handling cost reductions while protecting the buyer from paying for inefficiency. Which TWO features should the buyer include in the pricing design? (Choose two.)
Correct Answer: A, CExplanationGain share depends on a verified baseline, which open book review of the provider's costs establishes, and on a pre-agreed split of savings measured against that baseline, so both parties share risk and reward transparently. A rising fixed fee and a guaranteed margin both decouple payment from performance and remove the incentive the arrangement is meant to create. Cost plus reimbursement pays for inefficiency and works against the buyer's objective.
-
9 Question 9 Single choice Understand the dynamics of supply chains
A pharmaceutical company wants to reduce the risk that a single active ingredient supplier disrupts production. Its current analysis shows the ingredient is sourced from one supplier located in a region subject to frequent port closures, and the supplier holds a regulatory approval that takes around 18 months to replicate. Management has a budget for risk mitigation but cannot afford an immediate change of supplier. Which action BEST balances risk reduction with the regulatory constraint?
Correct Answer: AExplanationContingency inventory covers the port closure exposure immediately, while qualifying a second source in parallel starts the long regulatory timeline early, which respects the 18-month approval constraint. Transferring production within six months ignores the approval lead time. Asking the supplier to relocate at its own cost is unrealistic and would itself trigger regulatory revalidation. Accepting the risk ignores the budget available for mitigation and misreads the constraint, since second sourcing is possible over time rather than prohibited.
-
10 Question 10 Single choice Understand improvement methodologies that can be used in supply chains
A buying organisation has run a six sigma project to reduce invoice discrepancies between purchase orders and goods receipts. The project team has reduced the defect rate from 4 percent to 0.8 percent, but the improvement has not been sustained and the rate has returned to 2.5 percent within four months. The sponsor asks what should be done to make the gains stick. Which action is MOST appropriate?
Correct Answer: AExplanationSustaining an improvement requires embedding statistical process control on the critical drivers, with defined response rules and named owners, so drift is detected early. A further project repeats the same gap if the controls are absent. A one-off bonus does not change the process behaviour that caused the regression. Increasing audit frequency detects defects after they occur but does not hold the improved process in control.
-
11 Question 11 Single choice Understand the dynamics of supply chains
A firm is comparing how two of its divisions interpret the term supply chain management. Division X treats its work as the management of purchase transactions with a list of approved suppliers. Division Y coordinates information, planning and material flows across its direct suppliers and their suppliers, and has built joint planning forums with them. The group CPO wants to set a single definition for performance targets and governance. Which definition should the CPO adopt?
Correct Answer: AExplanationDefining supply chain management as integrated management of flows across the whole network of organisations delivering value to the end customer captures the coordination that Division Y practises and extends beyond transactions. Transactional purchasing describes procurement activity rather than chain management. An internal-only view ignores the external network the firm depends on. Restricting the scope to direct contracts omits the sub-tier dependencies that drive vulnerability and cost.
-
12 Question 12 Multiple choice Understand measures required to achieve competitive advantage in supply chains
A retailer is consolidating its supplier base for a private label range and wants to reduce prices through aggregation of requirements. Its category director is concerned that reducing the supplier count increases the risk of disruption. Which THREE actions together would BEST preserve supply security while capturing aggregation benefits? (Choose three.)
Correct Answer: A, B, EExplanationRetaining a qualified secondary supplier keeps a fallback route, sub-tier disclosure clauses reveal hidden concentration risk, and tiered pricing over aggregated spend converts consolidation into price benefit. Awarding all volume exclusively to one supplier concentrates risk the category director has flagged, and removing performance measures eliminates the means of managing the retained suppliers. Those two options therefore fail the supply security requirement.
-
13 Question 13 Single choice Understand improvement methodologies that can be used in supply chains
A government agency purchases ICT services under a framework agreement. Its quality function has relied on checking each deliverable against the contract at acceptance. Following repeated rework on delivered software releases, the head of procurement proposes a change. The agency works with a small number of suppliers on long term relationships and wants quality built into the supplier's delivery process rather than inspected at the end. Which approach is MOST consistent with this objective?
Correct Answer: AExplanationBuilding quality into the supplier's process is a total quality approach, achieved through shared objectives, joint root cause analysis and supplier-owned controls that rely on the long term relationship. More acceptance testing is quality inspection, which the agency already finds inadequate. Penalties on defects found at acceptance reinforce detection rather than prevention. Rotating suppliers destroys the relationship and the accumulated knowledge that prevention depends on.
-
14 Question 14 Single choice Understand the dynamics of supply chains
A manufacturer is planning to launch a new product line in nine months. Its current sourcing process requires a full tender for each new component, which takes five months, and engineering changes are often delayed by supplier qualification. The manufacturer wants to reduce time to market without compromising the quality of the new components. Which change is MOST likely to deliver the required reduction?
Correct Answer: BExplanationEarly supplier involvement and pre-qualification of component families move the sourcing and qualification work into the design phase, which shortens the critical path to launch while maintaining quality checks. Waiving qualification removes the quality safeguard the scenario says must be preserved. Extending the tender lengthens the timeline the manufacturer is trying to shorten. Delaying launch until the current process completes accepts the timeline problem rather than solving it.
-
15 Question 15 Single choice Understand measures required to achieve competitive advantage in supply chains
An engineering firm is negotiating a new supply agreement for a specialist sub-assembly with a supplier that has strong technical capability but limited pricing transparency. The buyer's cost analysts suspect the supplier's margin is well above market. The buyer wants a price reduction without damaging the collaboration that delivers its design innovations. Which negotiating approach is MOST appropriate?
Correct Answer: AExplanationOpen book analysis gives the buyer evidence of the cost structure, and jointly agreeing a target price linked to shared improvements builds trust while reducing cost, which suits a relationship that delivers innovation. An immediate threatening demand risks the collaboration the scenario says must be protected. Accepting the price forgoes a reduction the buyer has evidence for. Imposing a generic index ignores the supplier's specialist cost base and invites disputes.
-
16 Question 16 Single choice Understand improvement methodologies that can be used in supply chains
A procurement function has collected three years of supplier delivery performance data across 400 suppliers but reports on it only as annual averages, which hide wide variation between categories. The head of supply chain wants KPIs that drive improvement at the level where decisions are taken. Which KPI design is MOST appropriate?
Correct Answer: AExplanationCategory level on-time delivery with control limits lets managers see where variation sits and act on signals rather than averages, which is the purpose of statistical measurement for improvement. A single averaged percentage repeats the masking problem the scenario describes. Spend is a commercial measure and does not indicate performance. Buyer productivity measures the buying team, not the supply performance the head of supply chain wants to improve.
These are 16 of the 88 questions in the full L5M7 pack.
Get All 88 QuestionsGet all 88 questions & answers
Full access options for CIPS L5M7
Self-study
PDF Version
- 88 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 88 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 88 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the L5M7 Exam (Achieving Competitive Advantage Through the Supply Chain) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.