Exam Information
Free practice questions with explanations
CIPS L5M3 Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 11
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Understand the impact of breach of contract and approaches for managing breach.
A regional logistics provider notified its client in writing, three weeks before the scheduled start of a three-year warehousing contract, that it would not be able to provide the dedicated storage area specified in the contract and would not perform under the agreement as drafted. The client has not yet reached the start date and has no performance failure to point to. The contract contains no express termination-for-convenience right for either party. The client's procurement director wants to act quickly to protect supply continuity and preserve the option of a damages claim. Which is the BEST immediate course of action for the client?
Correct Answer: BExplanationA clear, unequivocal statement that a party will not perform before the performance date is an anticipatory breach (repudiation). The innocent party may accept the repudiation, terminate and claim damages immediately, without waiting for the due date (objectives 2.1.4, 2.1.5). Waiting until the start date (A) forfeits the early option and loses mitigation opportunity. Mediation (C) does not preserve the termination right and delays action when the client wants to protect continuity. Agreeing a variation (D) would waive the damages claim, which the director wants to preserve.
-
2 Question 2 Single choice Understand the impact of breach of contract and approaches for managing breach.
A public body procures a bespoke IT system from a supplier under a fixed-price contract. Acceptance testing fails on one non-critical reporting module that affects around two per cent of functionality. The contract says that a failure which does not prevent the system being used for its primary purpose is a minor breach; a failure preventing that purpose is a material breach; and a failure going to the root of the contract entitles the buyer to treat the contract as ended. The buyer's team wants to reject the whole system and terminate. The supplier has offered a remediation plan within 30 days at no extra cost. Which classification and response are MOST appropriate?
Correct Answer: CExplanationThe failure affects roughly two per cent of functionality and does not prevent the primary purpose being achieved, so it is a minor breach under the contract's own definitions (objective 2.1.1). The appropriate response is to insist on remediation while preserving a damages claim for any loss (2.2, 2.3.4). Classing it as fundamental or material (A, B) misapplies the stated thresholds and risks a wrongful termination. Anticipatory breach (D) does not apply because the supplier has not repudiated, and waiving all claims is unnecessary.
-
3 Question 3 Single choice Understand the legal and process issues relating to the formation of contracts
A buyer sends a purchase order referencing its standard terms. The supplier replies with an acknowledgement stating it accepts the order 'subject to our terms of sale', which include a limitation of liability far lower than the buyer's standard. Goods are delivered and the buyer's goods receipt is recorded. A dispute later arises over which liability cap governs a defective-product claim. Which analysis BEST describes the contractual position?
Correct Answer: CExplanationA purchase order is an offer, and a reply accepting it 'subject to' different terms is a counter-offer rather than an acceptance (objectives 1.1.1, 1.1.2). Where goods are delivered and accepted, the courts may infer acceptance of the counter-offer by conduct, so the supplier's terms are the likely governing terms, creating a battle-of-the-forms risk the buyer should manage. A is wrong because receipt of goods does not automatically impose the buyer's terms. B misreads a qualified reply as unconditional. D is wrong because conduct normally forms a contract.
-
4 Question 4 Single choice Understand the legal and process issues relating to the formation of contracts
A framework agreement contains a clause stating that the main agreement prevails over any schedules in case of conflict. A call-off order issued under the framework includes a schedule with a higher service level and a shorter delivery window than the main agreement. The supplier has agreed to the call-off by signature, and the buyer now wants to enforce the stricter service level. The supplier argues the main agreement governs. The buyer must act within its procurement policy, which requires a documented, compliant change where schedules conflict with the main terms. What should the buyer do FIRST?
Correct Answer: BExplanationThe precedence clause expressly places the main agreement above schedules, so the call-off cannot automatically override it (objective 1.1.4). The first step is to analyse the precedence clause and the call-off wording against the variation mechanism, then formalise any change compliantly (1.1.5). Enforcing the schedule (A) ignores the stated precedence rule. Re-tendering (C) is disproportionate and premature. Invoking dispute resolution and suspending call-offs (D) escalates before the buyer has established its position.
-
5 Question 5 Single choice Understand the legal and process issues relating to the formation of contracts
A construction client agrees a contract with a main contractor that includes a liquidated damages clause for late completion. Two months in, the client instructs significant additional works verbally on site and the contractor proceeds. The contract requires all variations to be instructed in writing by an authorised representative and to state any change to the completion date. No written variation has been issued. The client now wishes to levy liquidated damages for the overrun, arguing the contractor should have claimed an extension. What is the MOST significant risk to the client's position?
Correct Answer: BExplanationThe contract requires written instructions for variations and a stated change to completion date. A verbal instruction that does not comply may not validly vary the contract, so the completion date remains uncertain, and levying liquidated damages on that basis risks challenge (objective 1.1.5, with 3.1.5). A is wrong because prevention-type arguments do not automatically void the clause. C overstates the contractor's position, since the contract governs. D is not automatic: waiver requires clear conduct, and the client's risk lies chiefly in the variation formality.
-
6 Question 6 Single choice Understand the legal and process issues relating to the formation of contracts
A supplier of medical consumables offers a three-year agreement with a clause requiring the buyer to pay on delivery and a second clause allowing the supplier to suspend deliveries if any invoice is more than 15 days overdue. The buyer's finance department has a 60-day payment cycle. The buyer wants to reduce payment-related supply risk without renegotiating prices. Which contractual change is MOST effective?
Correct Answer: AExplanationThe payment term and suspension right create a direct conflict with the buyer's 60-day cycle, making the buyer's own payment process a source of supply interruption risk (objective 1.2.5). Aligning the payment term and removing the suspension right addresses the root cause. B and C are remedies for supplier failure, not the buyer's payment risk. D increases the buyer's exposure by adding a new indemnity liability.
-
7 Question 7 Single choice Understand the legal implications of contractual non-conformance in procurement and supply
A supplier of cleaning services is contracted to provide daily cleaning with a service credit of 2 per cent of the monthly fee for each missed cleaning round. In a month, the supplier misses 10 rounds, but the client's loss from the missed rounds (contamination costs) is estimated at three times the total service credits. The contract states that service credits are the sole and exclusive remedy for missed cleaning rounds. The client wants to recover the full loss. What is the BEST assessment of the client's position?
Correct Answer: BExplanationService credits stated to be the sole and exclusive remedy will generally limit the client's recovery for that type of failure (objective 3.1.1, 3.1.2). The client can only escape the limitation in limited circumstances, such as where the exclusivity clause is argued to be ineffective in a fundamental breach, which is a complex and uncertain route. A ignores the express exclusivity. C wrongly asserts service credits can never be exclusive. D mislabels the remedy, since liquidated damages need a pre-agreed sum and are not claimed for actual loss.
-
8 Question 8 Single choice Understand the legal implications of contractual non-conformance in procurement and supply
A government agency terminated a supplier's contract for persistent non-performance, citing a default clause that allows termination after a written notice of default and a 14-day cure period. The agency issued a termination notice after 10 days, referencing the default but not the cure period. The supplier argues the termination is invalid. The agency now needs to re-procure urgently and wants to recover the cost difference from the original supplier. Which action BEST protects the agency's position?
Correct Answer: BExplanationThe default clause requires a written notice and a 14-day cure period, and the notice issued early and without reference to the cure period is defective (objectives 3.1.3, 3.2.2). Withdrawing it and reissuing a compliant default notice, then terminating only after the cure period expires, restores validity and is the safest course. A relies on a flawed termination. C is unreliable because the supplier is unlikely to consent informally. D ignores the express contractual process, which governs the termination.
-
9 Question 9 Single choice Understand the legal implications of contractual non-conformance in procurement and supply
A buyer is assessing the damages it could claim after a supplier's late delivery of components for a production line. The contract contains a clause requiring the supplier to pay 50,000 per week of delay, described as a pre-estimate of the buyer's loss from production stoppage. The buyer's internal analysis suggests actual weekly losses could be 15,000 to 20,000. The supplier argues the clause is a penalty and should be struck down. Which conclusion is MOST defensible?
Correct Answer: BExplanationThe enforceability of liquidated damages turns on whether the sum was a genuine pre-estimate at formation. A label alone is not decisive, and a sum far beyond the realistic loss is open to challenge as a penalty (objective 3.1.5). A overstates the effect of the gap by assuming any excess is fatal. C ignores the court's ability to look past labels. D is wrong because genuine liquidated damages are enforceable.
-
10 Question 10 Single choice Understand the legal implications of contractual non-conformance in procurement and supply
A supplier of IT managed services has repeatedly breached its service levels. The buyer wants to terminate, but the contract requires a minimum notice period of 90 days and includes a termination-for-convenience fee. The buyer also needs to avoid a claim for wrongful termination and minimise the damages it may face. The service is critical to operations and cannot be interrupted. The procurement manager proposes terminating immediately for repudiatory breach, citing the cumulative service failures. What is the BEST recommendation?
Correct Answer: BExplanationThe buyer should follow the contract's default provisions, serve notices of non-performance, and plan a managed transition so that termination is valid and does not interrupt a critical service (objectives 3.2.1, 3.2.2). Immediate termination (A) risks a wrongful termination claim if the breach is not repudiatory. C pays an unnecessary fee and does not address the breach route. D ignores the buyer's remedies and leaves the failures unaddressed.
-
11 Question 11 Single choice Understand the legal implications of contractual non-conformance in procurement and supply
A supplier of specialist parts failed to deliver under a contract that includes a clause permitting the buyer to recover from the supplier any reasonable costs of cover, which is a more specific remedy than general damages. The buyer sourced replacement parts at a higher price from another supplier and wants to claim the price difference. The supplier argues that the buyer's loss was not caused by the breach, because the buyer chose to buy from a more expensive source. What must the buyer demonstrate to support its claim MOST directly?
Correct Answer: BExplanationRecovery of cover costs depends on showing that the cover was reasonable, made within a reasonable time, and necessitated by the non-delivery (objectives 3.1.4, 3.2.3). Being the cheapest source (A) is not the test. Bad faith (C) is not a requirement for contract damages. A formal termination notice before cover (D) is not generally required for cover-based recovery and is not the core element of the claim.
These are 11 of the 120 questions in the full L5M3 pack.
Get All 120 QuestionsGet all 120 questions & answers
Full access options for CIPS L5M3
Self-study
PDF Version
- 120 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 120 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 120 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the L5M3 Exam (Managing Contractual Risk) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.