Exam Information
Free practice questions with explanations
Avixa CTS-I Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 11
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Conduct Post Project Activities (e.g., support, warranties, maintenance)
A corporate headquarters installed a 4K video conferencing system in its boardroom eight months ago. The manufacturer's warranty covers parts and labor for 12 months from the date of substantial completion. The integrator's service agreement has just been renewed. During a routine check, the technician finds that a camera has begun intermittently losing its PTZ control, and the facilities manager wants it fixed before the next quarterly board meeting in three weeks. The camera's firmware is two minor releases behind the current version, and the manufacturer's release notes list a known PTZ command-timeout fix in the newer version. The client's IT policy requires that all firmware changes be approved in writing before they are applied to production AV devices. What is the BEST first action?
Correct Answer: DExplanationThe client's IT policy requires written approval before any firmware change reaches production devices, so the technician must not upgrade on their own initiative. Documenting the symptoms and the current firmware version creates the evidence needed for either a firmware remedy or a warranty claim, and gives the client a concrete decision to approve. Replacing the camera first skips the diagnosis that might reveal a simple firmware fix, and the warranty process is not triggered until the fault is confirmed. Upgrading immediately violates the stated approval requirement. Disabling PTZ control degrades the service the client relies on and is not a repair.
-
2 Question 2 Single choice Conduct Site Rough-In/First-Fix (weight: 12%)
A school district is converting a 1970s lecture hall into a hybrid learning room. The existing ceiling is a suspended grid with plenum-rated tiles, and the old analog video cabling runs through an open return-air plenum. The new design calls for HDBaseT transmitters at the lectern and a ceiling-mounted projector fed from a central rack in an adjacent room. The mechanical contractor has asked the AV integrator to remove the old coaxial runs and install new cable pathways before the ceiling is closed. The district requires that all new cable in the return-air plenum be plenum-rated and that no cable be laid on the ceiling grid or pulled through any fire-rated barrier without an approved firestop. Which action should the integrator take during rough-in?
Correct Answer: BExplanationRemoving the abandoned coaxial and running new plenum-rated cable through dedicated J-hooks or conduit meets the requirement that cable be supported independently of the grid and that fire-rated penetrations be sealed. Laying cable on the grid is explicitly prohibited by the district. Leaving legacy coax in place adds fill and creates a fire-load and maintenance problem that the stem's deinstallation requirement is meant to prevent. Riser-rated cable is not a substitute for plenum rating in a return-air space, so it fails the stated plenum requirement.
-
3 Question 3 Single choice Implement Pre-Installation Activities (weight: 17%)
An integrator is preparing to install an AV system in a corporate auditorium with a new 20-metre fibre run between the control room and the stage. During the site survey, the integrator discovers that the planned route passes through a shared telecom riser that the building operator has scheduled for a structural retrofit starting in six weeks. The AV project schedule has a fixed opening date, and the fibre cable has a 10-week lead time. The client has asked for a recommendation that protects the opening date while keeping the design intact. The building operator will not permit AV pathway work in the riser during the retrofit. What is the BEST recommendation to present to the client?
Correct Answer: BExplanationThe building operator has already refused AV pathway work in the riser during the retrofit, so the integrator must find an alternative route that avoids it, and the cable order must wait for that route to be confirmed to protect the 10-week lead time. Proceeding on the planned route ignores the operator's position and the retrofit timing. Switching to copper does not address the physical route conflict and may be unsuitable for the 20-metre distance the design requires. Delaying the opening date is not necessary because a compliant route can be found within the existing schedule constraints.
-
4 Question 4 Single choice Install AV Systems (weight: 39%)
An integrator is assembling a 24U equipment rack for a training room that houses a matrix switcher, a DSP, a control processor, and a 2U power amplifier that draws significant current and exhausts heat from its rear. The rack is in a closet with no active cooling, and the design requires that the amplifier not be heated by the equipment above it. The rack will be cabled from the top down. The client also requires that the rack be serviceable from the front without removing other equipment. Which assembly approach best meets these requirements?
Correct Answer: BExplanationPlacing the high-heat amplifier low in the rack keeps its exhaust from rising through the heavier and more heat-sensitive equipment above it, and a blanking panel above it prevents hot air from being drawn back into the area above. Keeping lighter devices toward the top also reduces load on the rack. Mounting the amplifier at the top exposes the rack's upper devices to rising heat. A solid shelf above a heat source traps heat rather than managing airflow. Putting the DSP directly above the amplifier places a sensitive device in the exhaust path, and rear-mounted rails conflict with the front-access requirement.
-
5 Question 5 Single choice Install AV Systems (weight: 39%)
A company is installing a networked AV system for a boardroom. The control processor and the DSP must be placed on a dedicated AV VLAN, separate from the corporate data network, and the design calls for the DSP to receive a static IP address. The network team has issued the AV VLAN subnet as 10.20.30.0/24, with the default gateway at 10.20.30.1, and has reserved 10.20.30.10 through 10.20.30.49 for the DHCP pool. The DSP's IP address must be assigned outside that range. The control processor must be reachable from the corporate network for remote monitoring through a firewall rule that permits only the control port. Which configuration is correct for the DSP?
Correct Answer: AExplanationThe DSP must use an address outside the DHCP reserved range of 10.20.30.10 to 10.20.30.49, and 10.20.30.50 lies within the same /24 subnet with a correct mask and the gateway that the network team issued. Choosing 10.20.30.25 places the DSP inside the DHCP pool, creating a duplicate-address risk. A gateway of 10.20.31.1 is outside the subnet, so the DSP cannot reach it. A /25 mask changes the subnet boundaries and conflicts with the network team's allocation.
-
6 Question 6 Single choice Install AV Systems (weight: 39%)
During calibration of a conference room's ceiling microphone array, the integrator observes that a single microphone shows a consistently lower signal level than the others, with a different response in the mid-frequency range. The microphones are connected to a DSP through a Dante network, and the array has been wired using the manufacturer's recommended cable and termination. The integrator has confirmed that the cable runs are correct and the connectors are fully seated. The room's ceiling was installed to specification and is within the planned height. The integrator must decide the NEXT step to resolve the discrepancy before final acceptance testing. What should the integrator do next?
Correct Answer: BExplanationWith wiring and connectors verified, the most likely cause of a lower and tonally different level is the microphone's physical placement or orientation relative to its coverage pattern, or an obstruction in front of it. Checking that against the manufacturer's pattern is the logical next diagnostic step. Swapping the microphone without checking geometry risks the same fault and wastes parts. Raising gain on one channel masks the problem and can increase noise. Disabling the microphone leaves a coverage gap the client has paid for.
-
7 Question 7 Multiple choice Install AV Systems (weight: 39%)
A conference room uses a Crestron control processor to manage a projector, a video matrix, and an AV network device through an IP-based control system. The integrator is preparing the control and device settings for handover. The client's network team requires that the control system use only secured protocols and that no default administrative credentials remain on any device. The projector must also be controllable over IP but must not expose its web interface to guest users. Which TWO configuration actions meet these requirements? (Choose two.)
Correct Answer: A, DExplanationReplacing the default credentials on every networked device, with the new values stored in the client's password manager, meets the no-default-credentials requirement. Disabling the projector web server or limiting it to the AV VLAN keeps its interface away from guest users, while enabling its secured control protocol maintains IP control. Retaining default credentials relies on VLAN separation alone and ignores the explicit requirement. Plain HTTP violates the secured-protocol requirement. Placing the projector on the guest VLAN would make it inaccessible to the control processor and breaks the control design.
-
8 Question 8 Single choice Perform AV Systems Closeout (weight: 12%)
An integrator is completing a commercial lecture hall project. During the client's acceptance walkthrough, the client's representative reviews a list of performance criteria in the signed design specification, including a required 95 percent speech intelligibility score measured with a STIPA test at five seats, and the requirement that the lectern wireless microphone operate reliably across the entire seating area. The integrator has completed the pre-acceptance test report, which shows the STIPA scores at the five test seats meet the threshold, but the wireless microphone has not yet been tested beyond the front rows. The client's representative asks the integrator to demonstrate that the system performs to specifications before signing off. What is the BEST next action for the integrator?
Correct Answer: BExplanationThe specification requires reliable wireless microphone operation across the full seating area, and the acceptance demonstration must show compliance with every stated criterion, not only the STIPA result. Testing coverage at the rear and side seats specified in the design and documenting it alongside the STIPA data gives the client the evidence it asked for. Presenting only the STIPA results leaves a stated requirement untested. Signing now shifts the proof burden to the client and risks a failed event. Removing a specified requirement from the punch list without the client's agreement is not an acceptable closeout.
-
9 Question 9 Single choice Perform AV Systems Closeout (weight: 12%)
An integrator has completed a corporate board room installation and is preparing the final documentation package. The client requires that the as-built drawings reflect the installed condition, that the DSP programming file be delivered in its final version, and that any changes made during commissioning be captured. During commissioning, the integrator moved one display 150 mm to the left to clear a structural beam, and changed the DSP's output routing for a ceiling speaker zone after testing revealed a phase problem. The original design drawings and the DSP file on the integrator's laptop both reflect the pre-commissioning design. Which action best ensures the closeout documentation is accurate?
Correct Answer: AExplanationAs-built documentation must reflect the system as installed, so the relocated display and the revised speaker zone routing need to appear on the drawings, and the DSP file delivered must match the running configuration. A change memo or punch-list note does not replace accurate as-built records and programming files. Delivering the original design drawings and the laptop file would leave the client with documentation that does not match the installed system, which can cause problems during future service.
-
10 Question 10 Single choice Practice Ongoing Project Responsibilities (weight: 12%)
A general contractor is building a new campus theatre. The AV integrator is responsible for installing a loudspeaker system above a suspended ceiling, but the mechanical contractor has just issued a revised duct layout that now runs through the planned speaker suspension points. The mechanical contractor has asked the integrator to confirm a new mounting location by the end of the day so the ceiling framing can proceed. The integrator's engineer is off site and cannot review the revised layout until tomorrow. The general contractor's schedule has no float for ceiling framing. The integrator must not commit to a mounting change that affects the acoustic design without engineering approval. What is the BEST action for the integrator to take today?
Correct Answer: AExplanationThe integrator cannot approve a mounting change that affects the acoustic design without engineering review, so the correct move is a written response that holds the position, sets a review time, and gives the mechanical contractor the mounting constraints it needs to plan around. Confirming the new layout without review risks compromising the acoustic performance. Ignoring the request leaves the contractor without information and damages coordination. Relocating the speakers to the stage wall without acoustic checking changes the design unilaterally.
-
11 Question 11 Multiple choice Practice Ongoing Project Responsibilities (weight: 12%)
An integrator is managing daily field reporting on a multi-room AV installation. During a site visit, the integrator's foreman reports that a lift was used near an active electrical panel, a rack was delivered to the wrong floor, and a ceiling speaker bracket was installed in a location that differs from the approved shop drawing. The owner's representative requests a clear record of the issues and the actions taken. Which TWO actions should the integrator include in the daily field report and resulting coordination? (Choose two.)
Correct Answer: B, CExplanationA near-miss involving a lift and an active electrical panel is a safety event that must be logged with full details and reported to the general contractor's safety representative, so the record is complete. A location that differs from the approved shop drawing must go to the engineer for a documented field modification decision before work proceeds in that area. Quietly correcting the bracket or omitting it hides a deviation the owner is entitled to see. Keeping the safety event in a personal log breaks the reporting obligation. The rack delivery issue is worth recording, but it is not a field modification or safety matter, and the stem asks for the two actions that most directly meet the field reporting and modification requirements.
These are 11 of the 511 questions in the full CTS-I pack.
Get All 511 QuestionsGet all 511 questions & answers
Full access options for Avixa CTS-I
Self-study
PDF Version
- 511 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 511 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 511 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CTS-I Exam (Certified Technology Specialist - Installation) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.