1 Question 1 Single choice Construction
A mid-rise hospital wing is being built under a design-bid-build contract. The quality manager is reviewing the structural steel connection details against the specification, which requires a bolted moment connection with pretensioned high-strength bolts and a slip-critical faying surface condition. The steel fabricator's submittal shows a different connection type that is cheaper to fabricate but has not been reviewed by the engineer of record. Work is scheduled to start on the second floor framing in nine days, and the fabricator wants approval to release shop drawings for that floor now. What is the BEST action for the quality manager to take first?
Correct Answer: CExplanationSpecified connection types and faying surface conditions are controlling requirements, and a deviation must go through formal review by the engineer of record before fabrication. Holding the affected shop drawings protects the schedule from rework without conceding the specification. Approving the drawings for the second floor would still let the non-compliant connection proceed into erection. A field change request is issued for changes arising during construction, not for an unreviewed substitution that is still in submittal. Welder certification addresses welding procedure qualification, not whether a bolted connection meets the design basis.
-
2 Question 2 Single choice Design Phase
A client's stated quality objective for a warehouse project is minimal floor movement under forklift traffic to support high-bay racking. During schematic design, the value engineering team proposes thinning the slab from 300 mm to 225 mm and reducing the joint spacing criteria to save cost. The structural engineer has not yet modelled the slab under the racking loads. The project uses a design-build delivery with a fixed price, so the design team is motivated to reduce cost early. Which action BEST ensures the value engineering proposal aligns with the client's quality objective?
Correct Answer: CExplanationValue engineering must be evaluated against the client's quality objectives and the functional requirements they imply, such as floor movement under racking loads. Requiring structural analysis before the change enters the baseline keeps the cost saving from quietly eroding performance. Deferring to construction or relying on post-completion testing shifts risk to a point where correction is costly. Accepting the reduction without analysis ignores the stated objective, which is the very trap value engineering presents.
-
3 Question 3 Multiple choice Operations and Maintenance
A university research building will house temperature-sensitive equipment, and the owner requires that the quality plan support both planned shutdowns for chiller maintenance and unplanned events such as regional flooding. The quality manager is preparing inputs for the facility business continuity plan. Which TWO actions best align the quality plan with operational resilience? (Choose two.)
Correct Answer: A, DExplanationDrills and simulations are the method for testing whether business continuity plans hold, and tracking quality impacts during shutdowns closes the loop on the plan. Recommending risk-based O&M testing to the design team feeds the appropriate inspection strategy into the facility's lifecycle. Limiting inspections to the warranty period leaves later failures undetected. Dismissing a risk because of a map position ignores the stated unplanned-event requirement. Warranty staff alone cannot own shutdown monitoring for the owner's operational quality.
-
4 Question 4 Single choice Planning Phase
A public transit agency is evaluating four project delivery approaches for a rail extension. Match each agency requirement to the delivery method that best fits it.
1. The agency wants a single entity to take design and construction responsibility with a guaranteed maximum price and wants to see the contractor's early input during design.
2. The agency wants separate contracts for design and construction with the lowest price awarded to the lowest responsible bidder.
3. The agency wants the owner's own engineering and procurement team to manage major equipment purchasing while a separate contractor handles construction management for a fee.
Targets: Design-Bid-Build (DBB); Construction Manager at Risk (CMAR); Engineering, Procurement, Construction Management (EPCM); Construction Manager for Fee (CMFF).Correct Answer: DExplanationCMAR provides a guaranteed maximum price and early contractor involvement during design, which matches the first requirement. Design-Bid-Build separates design from construction and awards to the lowest responsible bidder, matching the second. EPCM places the owner's engineering and procurement under a management entity with construction handled separately, matching the third. The other mappings reverse the fee-based and at-risk models or put EPCM on the early-involvement requirement, which it does not fit.
-
5 Question 5 Single choice Procurement
A general contractor is buying precast concrete wall panels from a new trade partner for a parking structure. The trade partner's inspection and test plan lists dimensional checks at delivery and a compressive strength test on one cylinder per batch. The project specification requires dimensional verification on the first production panels at the plant before shipment, plus a concrete mix qualification and dimensional sampling across production. The trade partner has no history with the general contractor, and the first panels are scheduled to ship in three weeks. What is the BEST strategy to confirm the trade partner's plan meets the requirements?
Correct Answer: CExplanationFirst article inspection verifies the first production units against the specification before committing to full production, and factory acceptance testing confirms that the production process meets the specified sampling and verification requirements. Given the trade partner has no track record, these methods provide evidence that a certificate cannot. Plant certification does not show that a specific project's sampling and dimensional requirements are covered. Checking dimensions only at delivery detects problems too late to fix production. Strength cylinders address one property and do not verify dimensions or the specified sampling scheme.
-
6 Question 6 Single choice Project Turnover and Closeout
A hospital expansion has reached substantial completion. The contractor reports that the punch list is closed except for twelve items on a fire-rated door assembly package, and the owner wants occupancy next week. Two inspection records for the fire-rated door assemblies are missing signatures from the third-party inspector, and the as-built digital documentation has not yet been transferred to the owner's facility management platform. The owner's representative asks the quality manager to certify turnover. What should the quality manager do FIRST?
Correct Answer: CExplanationInspection and test records for safety-critical fire-rated assemblies must be compliant before final certification, and nonconforming work on the punch list must be closed. Withholding certification and verifying the records addresses both gaps before the building is occupied. A conditional certificate would transfer fire safety risk to occupants during operation. Relying on verbal confirmation or post-occupancy identification of gaps does not meet documentation requirements.
-
7 Question 7 Single choice Quality Manager Skills
A quality manager on a stormwater tunnel project discovers that a subcontractor's superintendent has been signing daily concrete placement logs for work that was not inspected, to keep the schedule on track. The general contractor's project director has asked the quality manager to keep the matter internal while the foreman is replaced. The quality manager is a member of the ASQ and holds the CCQM credential. Which action BEST demonstrates adherence to the ASQ Code of Ethics?
Correct Answer: CExplanationThe ASQ Code of Ethics requires honesty and integrity, which means falsified inspection records must be made known to the people responsible for the project's integrity, not concealed for schedule reasons. Correcting the records and reporting them promptly to the project director and owner's representative meets that obligation. Keeping the matter internal conflicts with the requirement to disclose. Informing only the owner while excluding the project director is selective disclosure. Delaying to a quarterly review allows continued risk to the structure.
-
8 Question 8 Order list Construction
A concrete subcontractor has submitted a mix design for a bridge deck pour. The quality manager must process the submittal and related field verification in the correct sequence before the pour is released. Drag the steps into the correct order.
Drag the steps into the correct order, or use the arrows.
- Confirm the trial batch results meet the specified strength and durability requirements.
- Release the pour for placement after field verification and the pre-placement inspection are complete.
- Verify the mix design against the project specification and the contractor's quality plan.
- Route the mix design to the engineer for review and obtain written acceptance.
Correct Answer:- Verify the mix design against the project specification and the contractor's quality plan.
- Route the mix design to the engineer for review and obtain written acceptance.
- Confirm the trial batch results meet the specified strength and durability requirements.
- Release the pour for placement after field verification and the pre-placement inspection are complete.
ExplanationThe mix design is first checked against the specification and quality plan, then routed to the engineer for review and written acceptance. Trial batch results are reviewed next, as they support the design's performance claims. Release for placement comes last, after field verification and pre-placement inspection. Sequences that route to the engineer before internal verification, or that release before trial batch confirmation, skip a required gate.
-
9 Question 9 Dropdown Construction
Choose the correct value for each blank.
Choose the correct value for each blank.
A contractor must track a field question from the site superintendent about a conflict between a structural drawing and a mechanical duct penetration. The formal tracking process records the question as a request for information, and when the proposed fix alters the scope or the design intent, it becomes a design change request. The quality manager confirms that the request for information is logged on the day it is raised so that the remains traceable, and that a is issued to the engineer whenever the resolution changes the design basis.
A. response timeline; field change request
B. submittal register; design change request
C. response timeline; design change request
D. submittal register; field change requestCorrect Answer:A contractor must track a field question from the site superintendent about a conflict between a structural drawing and a mechanical duct penetration. The formal tracking process records the question as a request for information, and when the proposed fix alters the scope or the design intent, it becomes a design change request. The quality manager confirms that the request for information is logged on the day it is raised so that the response timeline remains traceable, and that a design change request is issued to the engineer whenever the resolution changes the design basis.
A. response timeline response timeline; design change request field change request
B. response timeline submittal register; design change request design change request
C. response timeline response timeline; design change request design change request
D. response timeline submittal register; design change request field change requestExplanationTraceability of a field question is tracked through the response timeline of the request for information, which records when the question was raised and answered. When the resolution changes the design basis, a design change request goes to the engineer rather than a field change request, since field change requests address field-driven adjustments within the existing design. A submittal register tracks product and shop drawing submittals, not questions, so it does not fit either blank.
-
10 Question 10 Single choice Design Phase
A hotel's owner set a quality objective of low maintenance for exterior cladding over a 25-year service life. The design team coordinates a rain screen system with a high-performance coating on the finish layer. During coordination, the architect proposes a finish that offers the desired appearance but does not perform on the specified substrate in the local coastal exposure. The project requires consistency between the foundation-level structure and the finish-level system, and the lowest-cost option that meets the look also requires a different fastener specification. What is the BEST approach to resolve the coordination of functional and nonfunctional requirements?
Correct Answer: CExplanationFunctional requirements such as durability in coastal exposure and nonfunctional requirements such as appearance must be coordinated across system and component levels, including the substrate and fasteners. Checking compatibility before approving the finish is the coordination step the requirement describes. Waiting for corrosion to appear moves the failure into operation, contrary to the 25-year objective. A manufacturer's warranty does not substitute for verifying the substrate and fastener interface. Removing the rain screen to simplify coordination abandons the functional performance the owner specified.
-
11 Question 11 Multiple choice Procurement
A contractor is subcontracting steel reinforcement fabrication for a water treatment plant. The quality requirements include a qualified bending schedule, traceable mill certificates, and corrosion protection on exposed bars. The contractor has shortlisted a fabricator with strong cost performance but limited history on this type of structure. Which TWO quality actions best integrate subcontractor-specific requirements into the procurement decision? (Choose two.)
Correct Answer: B, EExplanationRequiring hold points in the fabricator's inspection and test plan integrates the specified tolerance and traceability requirements into the subcontractor's own process. Reviewing historical performance and verifying compliance with the reinforcement standard addresses the stated scope, performance history, and standards compliance before award. Lowest price ignores the vendor-specific risk. Excluding delivery inspection leaves traceability unverified. Accepting an unverified corrosion process conflicts with the requirement to confirm protection on exposed bars.
-
12 Question 12 Single choice Operations and Maintenance
A data centre's owner has asked the design team to recommend O&M inspection and testing strategies for the uninterruptible power supply batteries, the standby generator, and the building switchgear. The design team must recommend a strategy that reflects the component health data the owner can realistically collect. The owner has an in-contract maintenance program covering the first two years and a warranty covering the switchgear for five years. Which recommendation BEST supports a sustained quality requirement for operations?
Correct Answer: CExplanationA risk-based strategy that uses measured component health data, such as battery impedance and generator load testing, sustains the quality requirement once the contracts expire. Aligning switchgear inspections with the warranty schedule uses the contractual coverage properly. Fixed replacement ignores measured condition. Stopping inspections at handover leaves the critical systems unmonitored. An unloaded generator test does not verify full load performance, so it cannot support the stated requirement.
-
13 Question 13 Single choice Pre-contract Phase
A developer is evaluating contract forms for a mixed-use project and must match each situation to the contract type that best fits it.
1. The owner wants a private-sector project delivered by a single design-build entity, with the design team and contractor under one contract that is governed by the industry's design-build standard.
2. A municipal authority is financing a water facility with private capital, and the private partner will design, build, finance, and maintain the asset under a long-term concession.
3. An owner wants a standard architect-led contract using the widely used American Institute of Architects form for a traditional design-bid-build project.
Targets: Design-Build Institute of America (DBIA) form; Public-Private Partnership (P3) agreement; American Institute of Architects (AIA) form; International Federation of Consulting Engineers (FIDIC) form.Correct Answer: DExplanationThe DBIA form governs single-entity design-build delivery, matching the first situation. A P3 agreement captures long-term design, build, finance, and maintain concessions with a public authority, matching the second. The AIA form is the standard architect-led contract for design-bid-build, matching the third. The other mappings use forms outside their intended delivery context, such as assigning AIA to design-build or DBIA to a concession.
-
14 Question 14 Single choice Procurement
A contractor plans to procure precast concrete beam elements for a bridge widening. The quality requirement states that each beam must meet camber tolerance and that the trade partner's inspection plan must include a first article inspection before the production run, plus factory acceptance testing of the casting bed alignment. The trade partner's current plan lists final inspection at shipment only. The beam order is needed on site in six weeks, and the trade partner offers to add the required checks at no extra cost if the contractor signs off the plan now. What should the contractor do?
Correct Answer: CExplanationThe requirement specifies first article inspection before the production run and factory acceptance testing of casting bed alignment, so the inspection and test plan must include both before approval. Approving the plan before production means the checks happen when they can still change outcomes. Signing off now and checking after beams arrive pushes verification past the point of cost-effective correction. Relying on temporary bracing to fix camber treats a nonconformance as an erection problem. Inspecting completed deck work misses the checks the requirement specifies.
-
15 Question 15 Single choice Quality Manager Skills
A newly formed commissioning team on a laboratory project is struggling. Members from the mechanical, electrical, and controls subcontractors disagree on who owns the functional test sequence. Meetings are dominated by one member, and two members have stopped attending. The project manager has asked the quality manager to help the team move toward effective performance before the first functional tests in four weeks. Which action BEST uses the stages of team development to move the team forward?
Correct Answer: CExplanationThe team's disagreement over ownership and withdrawal from meetings are typical of the storming stage, so the response is to bring the conflicting interests into the open and agree on shared goals and roles. That builds the norms needed before performing. Imposing an assignment skips the collaboration that sustains performance. Reconstituting the team restarts the process without resolving the cause. Leaving the team to resolve it unaided ignores the four-week deadline and the dominance problem already visible.
These are 15 of the 165 questions in the full CCQM pack.
Get All 165 QuestionsGet all 165 questions & answers
Full access options for ASQ CCQM
Self-study
PDF Version
- 165 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 165 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 165 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the CCQM Exam (Certified Construction Quality Manager) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.