Exam Information
Free practice questions with explanations
APMG-International AgilePM-Practitioner Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 12
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Lifecycle and Products
A public sector organisation is running an AgilePM project to replace a legacy benefits system. The sponsor wants early visibility of the target user experience before committing to build the full solution. The Business Analyst has produced a high-level vision document covering scope, objectives and success measures. The project board is concerned that the vision is too abstract for users to validate the proposed workflow, and the team has a constraint that no more than two weeks can be spent before the first development timebox starts. Which product should the team produce NEXT to best address the board's concern?
Correct Answer: DExplanationThe vision document already captures scope and objectives, so the gap is in validating how users will actually interact with the solution. In AgilePM a prototype is the product built to explore and confirm requirements with users, and it can be produced within the short pre-project window without locking in a full design. A detailed specification conflicts with the agile emphasis on evolving requirements, and a costed plan or risk register does not answer the usability uncertainty the board has raised.
-
2 Question 2 Single choice Lifecycle and Products
A project team using AgilePM is midway through the Exploration phase of a customer portal project. The Business Analyst discovers that a stakeholder has requested a change to the vision statement because a regulator has introduced a new reporting obligation. The sponsor asks whether the vision can be altered without returning to the Feasibility phase. The team wants to keep momentum while ensuring the change is governed correctly. Which action is MOST appropriate?
Correct Answer: AExplanationVision statements are living products that can be revised during the project, but changes should be agreed with the sponsor and recorded so that the whole team works from the same baseline. Returning to Feasibility is unnecessary for a refinement like this and would waste time. Deferring the update until release leaves the team working against an out-of-date vision, and bypassing governance by informing only the stand-up does not give the sponsor the control the project requires.
-
3 Question 3 Single choice People and Roles
An AgilePM project for a logistics company has a Solution Developer team that has been working for three timeboxes. The team lead reports that developers are repeatedly blocked because requirements are being clarified ad hoc by individual developers approaching different business users. The Business Analyst is assigned to the project but spends most of the time writing documents away from the team. The project manager must improve how the team gets requirement clarity without taking over the Business Analyst's role. What should the project manager do FIRST?
Correct Answer: BExplanationIn AgilePM the Business Analyst is responsible for the business view of requirements and works closely with the team, so the project manager should first clarify how that role connects to the team rather than redistribute responsibilities. Agreeing a single point of contact and a responsive question route resolves the blocking without removing the Business Analyst's responsibilities. Routing everything through the project manager or moving the analyst full time changes role boundaries, and a change control board for questions adds bureaucracy that AgilePM discourages.
-
4 Question 4 Multiple choice People and Roles
A project manager on an AgilePM engagement for a hospital scheduling system is planning how to support the agile team. The team has strong technical skills but is new to the DSDM approach, and two members are reluctant to take ownership of decisions. The project manager wants to support the team without undermining their empowerment. Which TWO actions best achieve this? (Choose two.)
Correct Answer: A, EExplanationAgilePM expects the project manager to be a servant-leader who builds team capability while keeping the team empowered, so coaching in the method and facilitating collective decisions fit that role. Removing authority contradicts empowerment, individually assigning every task creates the command-style control agile avoids, and taking over decisions deprives the team of ownership and is not a sustainable way to keep the schedule.
-
5 Question 5 Single choice Planning and Control
A team using AgilePM for a retail analytics project has a fixed delivery date for a Mission-critical release. Stakeholders have listed twelve requirements, and the team must prioritise them. The project board insists that the must-have requirements are delivered in full, and the team has only enough capacity for about 60 percent of the total effort within the timebox. A stakeholder argues that all requirements are equally important. Which MoSCoW approach should the project manager apply?
Correct Answer: DExplanationMoSCoW in AgilePM requires the must-have set to be genuinely essential and achievable within the timebox capacity, because the timebox is fixed and must be met. Labelling everything as Must have defeats prioritisation and will overrun, while dividing effort equally ignores which requirements actually matter. Deferring prioritisation until the end would leave the team unable to plan the timebox at all.
-
6 Question 6 Single choice Planning and Control
An AgilePM project to modernise a government tax filing service has a timebox that must finish on a fixed date because of statutory deadlines. The team estimates a feature set at 80 effort units, but the timebox capacity is 55 units. The project manager is considering several responses. Which response best reflects AgilePM's approach to fixed-time delivery?
Correct Answer: AExplanationAgilePM holds time and resources fixed and flexes scope, so the project manager should prioritise and deliver the must-have features within the timebox while deferring lower-priority work. Extending the timebox breaks the fixed-time principle that the statutory deadline depends on, and asking for overtime is unsustainable. Lowering quality standards is not permitted because the non-negotiable quality criteria must be met.
-
7 Question 7 Single choice Planning and Control
During an AgilePM project for an insurance claims platform, the risk log includes a dependency on a third-party API whose availability is uncertain. The risk owner has rated it as high impact but low probability. The project manager must decide how to manage the risk within a fixed-time, fixed-resource delivery. The team has a budget constraint that rules out buying a redundant commercial API licence. Which action is MOST appropriate?
Correct Answer: AExplanationAgilePM manages risk through identification, assessment, and response planning with named owners, and a fallback or stub can reduce the impact of the dependency without breaking the budget. Ignoring a high-impact risk because of low probability is poor practice, and purchasing a redundant licence is ruled out by the budget constraint. Cancelling the project is an excessive response when the risk can be managed within the timebox.
-
8 Question 8 Single choice Techniques
A team is delivering an AgilePM project for a utilities company that is building a customer billing system. The team has been working in timeboxes of four weeks, but the sponsor is concerned that the iterative cycles are producing rework because requirements are being tested too late. The team lead proposes changing the development approach. Which technique best supports early validation within the existing iterative development principles?
Correct Answer: AExplanationIterative development in AgilePM relies on testing and reviewing products within each iteration so that feedback is obtained early and rework is reduced. Replacing iteration with a single release or a waterfall model removes the feedback loop that the sponsor wants, and lengthening timeboxes delays the discovery of problems rather than solving them.
-
9 Question 9 Single choice Techniques
An AgilePM team delivering an HR onboarding platform for a multinational company has been asked to deliver a release that must go live before a regulatory deadline in six weeks. The team has used timeboxing successfully on earlier releases, but a senior manager asks for an exception so that the timebox length is extended for the final increment to finish a complex integration. The project board is firm that the deadline is fixed. Which response best applies the timeboxing principle?
Correct Answer: DExplanationTimeboxing fixes the duration so that delivery dates remain reliable, and the scope within each timebox is flexed through prioritisation. Extending the timebox or merging timeboxes breaks the fixed-time principle that the regulatory deadline depends on, and removing timeboxes eliminates the discipline the approach relies on.
-
10 Question 10 Single choice Techniques
A product team in an AgilePM project for an energy supplier is building a customer self-service portal. The team wants to apply an agile strategy that supports building the most important capability first while keeping the option to stop when the value is sufficient. The sponsor wants a working release as early as possible for a pilot group of customers. Which strategy best fits this need?
Correct Answer: DExplanationAgilePM favours delivering a minimum usable solution early, built around the highest-priority functionality, and then evolving it through incremental releases informed by feedback. Building everything in parallel to the same depth delays value, while delaying release until all features are complete removes the early pilot the sponsor needs, and starting with low-value features wastes timebox capacity.
-
11 Question 11 Multiple choice Techniques
An AgilePM project for a regional transport authority is using iterative development to deliver a journey planner. The project manager wants to check that the team is applying iterative development principles correctly. Which TWO practices are consistent with those principles? (Choose two.)
Correct Answer: A, CExplanationIterative development in AgilePM depends on using feedback to evolve products and on producing working results in small increments so that the team learns continuously. Completing all analysis upfront, freezing requirements at the outset, and treating early outputs as final all contradict the principle that requirements and designs are refined iteratively.
-
12 Question 12 Single choice Planning and Control
An AgilePM project to build a membership management system for a professional body has been running for six weeks. The team has delivered two timeboxes and the sponsor is asking for an estimate of the total effort to complete the project. The team's velocity has been stable, but the backlog has grown because stakeholders keep adding requests. Which approach to estimation best supports reliable planning in this situation?
Correct Answer: DExplanationIn AgilePM, planning is based on empirical evidence from completed timeboxes, so the project manager uses actual delivery rates and the prioritised backlog to forecast what can be achieved within the fixed time. Multiplying the first estimate ignores the changing backlog, summing individual hour estimates is poor practice at this level, and fixing prices for unstable backlog items conflicts with the iterative approach.
These are 12 of the 184 questions in the full AgilePM-Practitioner pack.
Get All 184 QuestionsGet all 184 questions & answers
Full access options for APMG-International AgilePM-Practitioner
Self-study
PDF Version
- 184 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 184 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 184 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the AgilePM-Practitioner Exam (Agile Project Management (AgilePM) Practitioner) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.