Exam Information
Free practice questions with explanations
APMG-International AgilePM-Foundation Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 16
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Agile Project Management - through the lifecycle
A regional logistics company has approved an AgilePM project to replace its legacy warehouse scheduling system. The sponsor wants a decision on whether to proceed within the next two weeks, and the budget for the feasibility stage is limited. The project manager has identified three unknowns: whether the existing data can be migrated, whether the vendor's scheduling engine meets peak-season throughput, and whether drivers will adopt a mobile interface. The team has not yet agreed on the scope of the first timebox. Which action should the project manager take FIRST to support the viability decision?
Correct Answer: DExplanationIn AgilePM the feasibility study is a short, bounded investigation whose purpose is to establish whether the project is viable and worth pursuing, given limited budget and time. Here the sponsor needs a go or no-go within two weeks, so the team must assess the unknowns at a high level before committing to foundations or build. Building a prototype or buying vendor contracts spends money before viability is established, and starting Foundations presumes the decision has already been made.
-
2 Question 2 Single choice The Effective Use of the Products
A product owner for an insurance claims application is preparing the Product Backlog for a team that works in two-week timeboxes. Stakeholders have requested a large number of changes, and the product owner wants each requirement to be captured in a form that can be traced to a deliverable the business has agreed to. The team lead asks whether the backlog should be kept as a single unordered list of ideas to avoid premature commitment. The product owner needs to ensure products are generated, overseen and used effectively throughout the process. Which approach best meets this need?
Correct Answer: DExplanationThe AgilePM approach treats products as managed deliverables, so requirements should be recorded and prioritised with clear ownership and a planned timebox, which keeps the business and team aligned on what will be delivered. A shapeless list of ideas leaves no trace from requirement to product, and a document updated only at project end removes oversight during delivery. Personal developer lists fragment ownership and bypass the product owner's role in controlling what is produced.
-
3 Question 3 Single choice Deliver on time - Combining MoSCoW Prioritization and Timeboxing
A development team is working in a 30-day timebox to deliver a customer self-service portal. The timebox is fixed and cannot be extended because a regulatory reporting date follows immediately. At the start of the timebox, the requirements total roughly 140 percent of the team's expected capacity. Stakeholders insist that the login function, payment processing and the regulatory statement export all be delivered on time, while the product owner would like to include a wish-list of analytics widgets. The project manager needs to plan the timebox so that the fixed date is met. Which approach should the project manager apply?
Correct Answer: BExplanationTimeboxing fixes the time and lets scope flex, so the team delivers the highest-priority Must have requirements within the date and drops or defers lower-priority items. Using MoSCoW to classify the login, payment and export features as Must have, and the analytics widgets as Could have or Won't have, respects the non-negotiable date. Extending the timebox breaks the fixed deadline, overtime and quality reduction are not sanctioned ways of fitting scope, and they do not address the prioritisation problem.
-
4 Question 4 Multiple choice Deliver on time - Combining MoSCoW Prioritization and Timeboxing
A project team has a fixed three-week timebox and a backlog of twelve requirements. The product owner has tagged them as Must have, Should have, Could have and Won't have. During the second week the team realises that two Must have requirements are dependent on an external API that will not be available until week four. Which TWO actions should the project manager take to keep the timebox on track while respecting the MoSCoW priorities? (Choose two.)
Correct Answer: B, DExplanationTimeboxing requires the project manager to protect the date, so if a Must have cannot be completed it must be transparently moved to a later timebox and the product owner informed, which keeps the priority honest. Building against a stub of the API lets the team make real progress without waiting. Re-labelling Must have requirements to make them droppable misrepresents their priority, extending the timebox breaks the fixed date, and Won't have items are already out of scope so removing them does not free any effort.
-
5 Question 5 Single choice People, Teams and Interactions
A product owner, a senior developer and a business analyst on a banking transformation project have been in repeated conflict over acceptance criteria. Status updates in the daily stand-up are short and the three rarely speak to each other outside formal reviews. The project manager notices that decisions are being delayed and the team has started to bypass the product owner. The project manager wants to improve collaboration without changing the team structure. Which action is most consistent with AgilePM principles for fostering effective team interaction?
Correct Answer: DExplanationAgilePM emphasises active collaboration and shared ownership, so a facilitated session in which the roles agree acceptance criteria together, with decision rights made explicit, addresses both the conflict and the delayed decisions. Written memos continue one-way communication that caused the problem, handing decisions to the senior developer removes the product owner's accountability, and separating the roles would reduce the very interaction the team needs.
-
6 Question 6 Single choice People, Teams and Interactions
A newly formed delivery team of seven people, including two contractors who join at different times, is struggling with trust. The contractors feel excluded from planning and the permanent staff complain that the contractors do not commit to shared tasks. The project manager is considering how to build the team's cohesion across the first three timeboxes. Which approach most effectively supports the team's development as a self-organising unit?
Correct Answer: DExplanationTeam cohesion in AgilePM grows when people contribute to planning and jointly agree how they will work, so bringing the contractors into planning and retrospectives from the start builds shared commitment. Isolating contractors deepens the divide, allocating tasks by decree undermines self-organisation, and delaying team development leaves the trust problem to worsen during the critical early timeboxes.
-
7 Question 7 Single choice Requirements and User Stories
A business analyst for a retail bank is preparing user stories for a new customer onboarding journey. The stakeholders have written requirements such as "The system must be secure and fast" and "Customers should be able to open accounts easily." The product owner wants stories that the development team can estimate and test within a single timebox. The business analyst has limited time with the stakeholders before the backlog must be ready. Which approach should the business analyst apply FIRST to convert these statements into usable user stories?
Correct Answer: BExplanationUser stories need to express a specific actor, need and benefit, with acceptance criteria that make them testable and estimable within a timebox. Statements like "secure and fast" are non-functional or vague and must be decomposed into concrete stories and criteria. Copying the wording verbatim keeps the ambiguity, a full specification conflicts with the Agile preference for lightweight, incremental detail, and deferring all detail leaves the backlog unready for the timebox.
-
8 Question 8 Multiple choice Requirements and User Stories
A product owner for a healthcare scheduling system wants a user story for patients to reschedule appointments. The development team has noticed that the current draft lacks clarity and the story cannot be estimated. The team must follow INVEST-style quality and AgilePM practice so that the story can be taken into a timebox. Which TWO elements most directly improve the story's readiness for the timebox? (Choose two.)
Correct Answer: A, EExplanationA ready story names the actor and the value they receive, and includes acceptance criteria that testers can check against observable behaviour, which together make the story estimable and testable. Prescribing database changes pre-empts the team's design decisions, naming a developer undermines self-organisation, and a governance sign-off is a gate that the Agile story does not require before development begins.
-
9 Question 9 Single choice Roles and Responsibilities - the Project Manager's view
An AgilePM project manager has been assigned to a project that is delivering a new payments platform for a telecoms provider. The project board wants a single individual to be accountable for the business benefits, and the team has asked the project manager to decide the priorities for each timebox. The project manager is also asked to handle the risk log and report to the board each fortnight. The project manager is concerned that their role will become a bottleneck. Which allocation of responsibilities is most consistent with the AgilePM roles?
Correct Answer: BExplanationIn AgilePM the Business Visionary is accountable for the business benefits and the Solution Developer team has authority over detailed delivery decisions, while the Project Manager manages project controls, risk and reporting to the board. The project manager is not the owner of benefits or the sole prioritiser, which is why the other allocations would create the very bottleneck the project manager fears. Delegating reporting to developers abandons the project manager's governance responsibility, and the Team Leader role does not own business benefits.
-
10 Question 10 Single choice Roles and Responsibilities - the Project Manager's view
During a mid-project review on a logistics modernisation programme, the project board notices that the Project Manager has been directing daily work of the solution developers in detail, and the developers have stopped raising impediments because they expect the Project Manager to resolve them. The Project Manager is organising everything personally. The board asks the Project Manager to restore the intended working relationship between the project manager and the team. Which change is the BEST response?
Correct Answer: BExplanationAgilePM expects the Project Manager to govern through controls and facilitate, while the solution developers self-organise within the agreed scope, timeboxes and constraints. The current pattern of detailed direction and unresolved impediments shows the team is dependent, so the Project Manager needs to step back and act as facilitator and escalation point. Continued direction entrenches the dependency, delegating board reporting removes the Project Manager's governance role, and appointing a new leader for risk management does not address the working relationship.
-
11 Question 11 Single choice Agile Project Management - through the lifecycle
A public sector agency is running an AgilePM project to deliver an online benefits application service. The project has completed its feasibility assessment and the board has approved the project to continue. The team is now preparing to establish the project's foundations, but the sponsor is concerned that a large amount of design work could be wasted if business objectives change. The project manager needs to set up the project so that governance, principles and the initial plan are in place without over-specifying the solution. Which stage of the AgilePM lifecycle should the project manager now focus on, and what should it deliver?
Correct Answer: AExplanationFoundations is the stage where the governance framework, the business case baseline, the outline plan and the Agile way of working are established, and it deliberately avoids fixing the detailed solution so that change remains possible. Exploration is where the solution is investigated iteratively rather than fully designed upfront, so fixing the design there contradicts the sponsor's concern. Implementation deploys the product and Post-Project evaluates benefits, neither of which is appropriate before foundations are set.
-
12 Question 12 Single choice The Effective Use of the Products
A development team on a customer relationship management upgrade has completed a set of features but the business stakeholders have not reviewed them. The sponsor wants evidence that each product will fulfil its intended purpose before the next timebox begins. The team is considering either writing a detailed test specification that will be signed off in advance, or relying on demonstrations at the timebox review. The project manager must choose a method that keeps the products under control and aligned to business need. Which approach best meets this requirement?
Correct Answer: BExplanationAgilePM uses agreed acceptance criteria and reviews within each timebox so that products are checked against business need as they are produced, keeping them controlled and aligned. Relying only on developer unit tests does not confirm business fit, deferring verification to after closure lets defects accumulate, and a fully signed specification locks in requirements that the Agile approach expects to evolve.
-
13 Question 13 Single choice Deliver on time - Combining MoSCoW Prioritization and Timeboxing
A project has three consecutive timeboxes before a fixed go-live date for a new vehicle booking platform. At the start of the first timebox, the product owner classifies requirements with MoSCoW. In the second timebox, the sponsor asks for an additional Must have feature because of a new regulation. The team's capacity is unchanged and the go-live date cannot move. The project manager needs to preserve the integrity of the timebox while accommodating the new requirement. What is the BEST action?
Correct Answer: DExplanationBecause the go-live date and team capacity are fixed, a new Must have must be accommodated by removing or deferring lower-priority work, which is the trade-off timeboxing requires. Agreeing this with the product owner keeps the priorities honest and transparent. Adding work without reducing scope overloads the team, reclassifying an existing Must have misrepresents priorities, and postponing a regulatory requirement is not acceptable when it is mandatory.
-
14 Question 14 Single choice Requirements and User Stories
A business analyst is working with a travel company's product owner to define requirements for a loyalty points feature. The stakeholders provide a long list of rules, including how points expire, which partners can award points, and how redemption is capped. The product owner intends to use the requirements to plan timeboxes and wants to avoid writing detail prematurely while still ensuring that the most important rules are understood. Which approach is most appropriate?
Correct Answer: BExplanationAgilePM supports progressive elaboration, where broad themes are captured early and detail is added to the highest-priority items shortly before they are built, which keeps effort focused and the backlog current. Documenting every rule upfront wastes effort on items that may change, ignoring the rules leaves the first increment unfounded, and parallel documentation by developers fragments the analysis without a shared view of priority.
-
15 Question 15 Single choice People, Teams and Interactions
An AgilePM project for a pharmaceutical distributor has a team that has been working remotely across three time zones for six months. Recent retrospectives show that the team is meeting its timeboxes, but members report low energy and misunderstandings about who is responsible for integration testing. The project manager wants to strengthen communication and shared understanding without adding bureaucracy or increasing meeting load significantly. Which action is most likely to resolve the problem?
Correct Answer: BExplanationA shared agreement about responsibilities, reviewed in retrospectives, directly addresses the confusion over integration testing and builds shared understanding without heavy process. A longer one-way report or extra meetings add load without resolving role ambiguity, and removing contact entirely would worsen the misunderstandings in a distributed team.
-
16 Question 16 Single choice Agile Project Management - through the lifecycle
An AgilePM project in a manufacturing firm has completed its Foundations and is midway through Exploration, when the business sponsor announces that a key supplier's contract will end in six months and the solution may have to be redesigned around a different supplier's interface. The project manager must decide how to respond within the lifecycle so that viability and benefits remain under control. Which response is most appropriate?
Correct Answer: DExplanationAgilePM expects the business case, risks and viability to be reviewed when the context changes, with the board reconfirming whether the project remains worthwhile and the plan being adjusted accordingly. Restarting from feasibility without consultation ignores governance, ignoring the change leaves the business case invalid, and jumping to Implementation locks in a design that may no longer be viable.
These are 16 of the 150 questions in the full AgilePM-Foundation pack.
Get All 150 QuestionsGet all 150 questions & answers
Full access options for APMG-International AgilePM-Foundation
Self-study
PDF Version
- 150 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 150 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 150 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the AgilePM-Foundation Exam (Agile Project Management Foundation) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.