Exam Information
Free practice questions with explanations
APMG-International AgileBA-Foundation Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 14
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Agile Philosophy and Principles
A regional insurer has run a fixed-scope, three-year waterfall programme to replace its claims system. Business sponsors now want to adopt Agile. The programme board insists that every detailed requirement signed off in year one must be delivered unchanged, because the contract penalties depend on it. Delivery teams report that customer needs have shifted twice since sign-off. Which Agile value should the business analyst emphasise first to resolve the conflict between contract scope and changing needs?
Correct Answer: BExplanationThe conflict is between a fixed contractual plan and evolving customer needs, and the Agile principle that addresses how the business should work with the customer during delivery is customer collaboration over contract negotiation. The analyst should move the conversation from locking detailed requirements to ongoing collaboration with the customer, which can then be reflected in the contract through outcomes and change mechanisms. Responding to change is tempting, but it names the symptom rather than the relationship that must be re-established first. Working software and individuals over processes are valid Agile values, but neither targets the contractual tension described in the scenario.
-
2 Question 2 Single choice Agile Analysis and Design
A retail bank is designing a new mobile loan application journey. The UX lead proposes a detailed, fully wired prototype covering all eighty screens before any development starts, arguing that stakeholders must approve everything upfront. The delivery team wants to test the most valuable journey first with real customers, and the regulator requires that any consent screen be validated before go-live in the next release. Which action is the BEST next step for the business analyst?
Correct Answer: CExplanationA minimal, low-fidelity prototype of the most valuable journey supports the Agile aim of validating design with users early and cheaply, and the regulatory constraint means the consent screens must be included in that validation before go-live. Approving the full prototype upfront creates heavy rework risk and locks in assumptions no one has tested. Deferring UX entirely ignores the need to validate the consent flow early. Leaving consent testing until after the first release breaks the requirement that consent be validated before go-live in the next release.
-
3 Question 3 Single choice Agile Requirements Management
A logistics company has a backlog of 120 requirements for a new warehouse scheduling tool. The sponsor wants all items labelled Must, Should, Could or Won't for the first release. The release has a fixed date, and the operations director states that the safety-related rostering rule is non-negotiable. Analysis shows that 30 items are tagged Must, and the team's capacity covers about 18 of them. Which action should the business analyst take FIRST when applying MoSCoW prioritisation?
Correct Answer: BExplanationMoSCoW is a relative prioritisation tool, and a Must is only valid if it is genuinely essential to the release. The director has confirmed the safety rule is non-negotiable, so the analyst should check which Musts truly meet that bar and then test the remaining Must set against capacity, since Musts exceeding capacity signal over-classification. Simply relabelling Musts as Should ignores the stated essentiality test. Moving all 30 Musts out of the release defeats the purpose of the fixed-date release. Estimating all 120 items is useful later but does not come first in MoSCoW classification.
-
4 Question 4 Single choice Agile Roles and Responsibilities
A business analyst in a government agency is embedded in a Scrum team building a citizen benefits portal. The product owner is overloaded with stakeholder requests and frequently delays backlog refinement. The analyst has strong facilitation skills and a good understanding of user needs, but is asked by the scrum master to write all acceptance criteria and act as the sole point of contact for the security team. The product owner remains responsible for the backlog order. Which change would BEST enhance the analyst's role within the team while respecting the existing accountabilities?
Correct Answer: AExplanationWithin the team the analyst adds most value by facilitating refinement and collaborating on acceptance criteria, which spreads understanding of user needs while keeping backlog ordering with the product owner who is accountable for it. Taking over backlog ordering breaks the product owner accountability stated in the scenario. Becoming product owner for a subset of stories fragments ownership of value. A separate specification read after each sprint reintroduces the delayed, document-centric handoff that Agile teams avoid.
-
5 Question 5 Single choice Agile Facilitation and Support
A health-care provider's Agile teams are spread across three sites and two time zones. Stand-ups are held in a shared video channel, but team members often lose track of impediments raised earlier in the week, and the product owner cannot see which blockers remain open. The security policy forbids storing patient data in external collaboration tools, and the budget does not allow new paid software. Which support strategy BEST addresses the visibility problem?
Correct Answer: BExplanationAn impediment board in an approved internal wiki provides a visible, persistent radiator that the whole distributed team and the product owner can see, and it stays within the security policy and the no-new-spend constraint. Public video hosting breaches the rule on patient data and visibility. Weekly emails are not a radiator and are easily lost. Buying a new platform conflicts with the budget and is an expensive migration not needed to solve the visibility problem.
-
6 Question 6 Single choice Agile Facilitation and Support
A financial services firm is running a series of workshops to elicit requirements for a new payments platform. Participants include compliance officers, engineers and customer service staff who frequently interrupt one another. The business analyst is asked to facilitate the next workshop so that all voices are heard and decisions are captured in a way that the team can later retrieve. The firm's data repository policy requires decisions to be stored in the approved team knowledge base. Which approach BEST meets these needs?
Correct Answer: BExplanationA round-robin speaking order with a parking lot manages interruptions and keeps all voices in the room, and recording decisions in the approved knowledge base satisfies the data repository policy and makes them retrievable. Letting a senior officer dominate suppresses the voices the workshop is meant to hear. Notes on a personal laptop breach the repository policy and hinder retrieval. A survey removes the collaborative workshop the scenario requires and the chance to resolve disagreements live.
-
7 Question 7 Multiple choice Agile Requirements Management
A public transport authority is building a user story map for a ticketing app. The team has a fixed budget for the first release and wants to see how the backlog supports the end-to-end journey. Which TWO actions are most appropriate when using user story mapping to plan the release? (Choose two.)
Correct Answer: A, BExplanationIn user story mapping, activities run left to right in the user's journey, with stories below each activity ordered by priority, and a horizontal release line marks the walking skeleton that delivers a coherent end-to-end experience within budget. Alphabetical sorting destroys the journey structure the map exists to show. Keeping infrastructure tasks unlinked hides their dependency on user value. Restricting each activity to one story wrongly constrains the map and removes the detail needed for prioritisation.
-
8 Question 8 Multiple choice Agile Analysis and Design
A pension administrator is reviewing three candidate process models for the redesigned claims process. The regulator requires a traceable audit trail of each decision, and the operations manager wants to reduce handoffs between departments. Which TWO evaluation criteria are most relevant when assessing whether a candidate process model is suitable? (Choose two.)
Correct Answer: B, EExplanationA suitable process model must let the analyst assess handoffs for removal or automation while preserving the audit trail the regulator demands, and must link each activity to a decision point and owner so decisions are traceable. Colour scheme, page length and authorship say nothing about whether the model meets the stated regulatory and operational needs.
-
9 Question 9 Order list Agile Requirements Management
A housing association has received a backlog of forty change requests for its tenant portal after a funding review. The product owner wants a clear, repeatable way to bring these requests into the backlog so that the most valuable work is ready for the next sprint planning event. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Record each request as a candidate backlog item with a short description
- Order the refined backlog items by value and risk with the product owner
- Clarify each request with the requesting stakeholder and capture the underlying need
- Estimate the effort of refined items with the development team
Correct Answer:- Clarify each request with the requesting stakeholder and capture the underlying need
- Estimate the effort of refined items with the development team
- Order the refined backlog items by value and risk with the product owner
- Record each request as a candidate backlog item with a short description
ExplanationRequests must first be recorded as candidate items so they are visible, then clarified to capture the real need before anything is estimated. Estimation only makes sense on refined items, and ordering by value and risk comes last so the product owner decides priority on informed estimates. Ordering before estimating, or estimating before clarifying, would rank items the team does not yet understand.
-
10 Question 10 Order list Agile Facilitation and Support
A telecom company wants to run a backlog refinement session for a new billing feature with its distributed team. The business analyst must prepare and run the session so that the team leaves with stories ready for sprint planning. Arrange the steps in the correct order.
Drag the steps into the correct order, or use the arrows.
- Record the agreed acceptance criteria and open questions in the team backlog tool
- Share the refinement agenda and the candidate stories to the team in advance
- Confirm the top-priority backlog items and the desired outcomes with the product owner
- Walk through each story, capture questions and agree acceptance criteria with the team
Correct Answer:- Confirm the top-priority backlog items and the desired outcomes with the product owner
- Walk through each story, capture questions and agree acceptance criteria with the team
- Share the refinement agenda and the candidate stories to the team in advance
- Record the agreed acceptance criteria and open questions in the team backlog tool
ExplanationThe analyst first aligns with the product owner on priorities and outcomes, then shares the agenda and candidate stories so people can prepare. The session walks the stories and agrees acceptance criteria, and the agreed results are then recorded. Circulating the agenda before confirming priorities would mean preparing around the wrong items, and recording results before the session runs has nothing to record.
-
11 Question 11 Drag and drop Agile Philosophy and Principles
A manufacturing firm is rolling out Agile across several departments and is struggling to explain why certain practices exist. The transformation lead wants each practice matched to the Agile value or principle it primarily supports. Match each practice to its underlying value or principle.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Accepting a revised priority late in the sprintDaily face-to-face conversation between business and developersRetrospectives held at the end of every sprintDelivering a working increment every two weeksRegular reflection on how the team can become more effectiveComprehensive upfront requirements documentation signed before design beginsFixed-scope contract negotiation completed before any deliveryFrequent delivery of working softwareWelcoming changing requirements even late in developmentBusiness people and developers work together dailyCorrect Answer:- Retrospectives held at the end of every sprint → Regular reflection on how the team can become more effective
- Delivering a working increment every two weeks → Frequent delivery of working software
- Daily face-to-face conversation between business and developers → Business people and developers work together daily
- Accepting a revised priority late in the sprint → Welcoming changing requirements even late in development
ExplanationRetrospectives express the principle of reflecting at regular intervals and tuning behaviour, frequent working increments express delivering working software often, daily business-developer contact reflects close collaboration, and accepting late priority changes reflects welcoming change. The two extra targets describe traditional, plan-driven practices that the Agile values deliberately move away from.
-
12 Question 12 Drag and drop Agile Roles and Responsibilities
A pharmacy chain has an Agile programme for its online prescription service. Several roles overlap in people's minds, and the transformation office wants each responsibility assigned to the role accountable for it. Match each responsibility to the role that owns it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Estimating effort and deciding how to build each backlog itemEliciting, analysing and validating requirements and supporting acceptance criteriaDeciding the order in which backlog items are delivered to maximise valueRemoving impediments that block the team and coaching the team on Agile practiceDevelopment teamBusiness analystProduct ownerChief executive officerHead of procurementScrum masterCorrect Answer:- Deciding the order in which backlog items are delivered to maximise value → Product owner
- Removing impediments that block the team and coaching the team on Agile practice → Scrum master
- Eliciting, analysing and validating requirements and supporting acceptance criteria → Business analyst
- Estimating effort and deciding how to build each backlog item → Development team
ExplanationThe product owner is accountable for backlog order and value, the scrum master for removing impediments and coaching, the business analyst for eliciting and validating requirements, and the development team for estimating and building. The chief executive officer and head of procurement do not hold these accountabilities within the team and are distractors from outside the delivery roles.
-
13 Question 13 Dropdown Agile Facilitation and Support
A logistics company runs its Agile teams with a shared team board and needs the stand-up impediment list to be visible to all sites. The business analyst is preparing guidance for the team on how to keep the impediment board current during each stand-up. Complete the guidance by selecting the correct value for each blank.
Choose the correct value for each blank.
At each stand-up, the facilitator reads the items aloud, adds any new impediment to the , and assigns an owner who will resolve it before the .Correct Answer:At each stand-up, the facilitator reads the open impediment items aloud, adds any new impediment to the impediment board, and assigns an owner who will resolve it before the next stand-up.
ExplanationThe facilitator reviews open impediments, adds new ones to the visible impediment board, and assigns owners so blockers are resolved before the next stand-up, which keeps the radiator current. Closed sprints and archived retrospectives are not reviewed daily, a release burndown does not record blockers, and a budget ledger or test log do not capture team impediments.
-
14 Question 14 Dropdown Agile Analysis and Design
A utilities company is creating a conceptual information model for its smart meter data and needs a standard way to show how customers, meters and readings relate. The business analyst is documenting the model conventions for the team. Complete the statement by selecting the correct value for each blank.
Choose the correct value for each blank.
In the information model, each is represented as a box, and the lines between boxes show the between them, with the cardinality marked at each end using a .Correct Answer:In the information model, each entity is represented as a box, and the lines between boxes show the relationships between them, with the cardinality marked at each end using a multiplicity notation.
ExplanationIn an information model such as an entity-relationship diagram, entities are the boxes, relationships are the connecting lines, and multiplicity notation at each end states how many instances participate. Process steps and sequence flows belong to process models, user roles to role maps, and release milestones and acceptance tests lie outside information modelling, so those options are plausible but wrong.
These are 14 of the 50 questions in the full AgileBA-Foundation pack.
Get All 50 QuestionsGet all 50 questions & answers
Full access options for APMG-International AgileBA-Foundation
Self-study
PDF Version
- 50 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 50 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 50 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the AgileBA-Foundation Exam (AgileBA (Agile Business Analysis) Foundation (2015)) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.