Exam Information
Free practice questions with explanations
API API-SIEE Practice Questions
Answer a question to see the correct answer and the explanation, or click Show answer. Newest questions first.
- Questions
- 12
- Answered
- 0
- Correct
- 0
- Score
- -
-
1 Question 1 Single choice Electrical Induction Motors
A source inspector is witnessing the factory insulation resistance test on a 4000 V, 600 HP totally enclosed fan-cooled induction motor for a hazardous area skid package. The motor has been dried out in the shop oven overnight and the test was started within 20 minutes of removal. The recorded insulation resistance at 1 minute is 35 megohms, and the polarization index calculated from the 10-minute reading is 1.1. The vendor's quality engineer argues the motor passes because the 1-minute value exceeds the minimum of 1 megohm per kV plus 1. The project specification requires a polarization index of at least 2.0 for machines of this rating. What is the BEST inspector action?
Correct Answer: BExplanationPolarization index is the ratio of the 10-minute to the 1-minute insulation resistance, and it indicates moisture and contamination in the winding independently of the absolute minimum value. Because the specification sets a PI of at least 2.0 and the recorded PI is 1.1, the motor fails that criterion even though the 1-minute value is acceptable. The correct response is to document the deviation, have the winding dried and retested, and keep the unit on hold. Accepting on the absolute value ignores the stated PI requirement, and rejecting outright or deferring the fix to the field goes beyond or avoids the source inspection process respectively.
-
2 Question 2 Multiple choice Electrical Inspection Tools and Test Equipment
A source inspector is verifying the test equipment brought to a switchgear factory test. The inspector must confirm that the instruments are suitable and reliable before witnessing insulation resistance and continuity measurements on a 480 V motor control center bus section. Select TWO actions that the inspector should verify before accepting the readings. (Choose two.)
Correct Answer: B, EExplanationReliable results require calibration traceable to a recognized standard and a current due date, which is the verification the inspector must check before accepting readings. The insulation tester's test voltage must match the equipment rating, and a function check against a known reference confirms the instrument is working. A clamp meter measures current through a conductor rather than applying test voltage across insulation, and a multimeter's highest resistance range reduces sensitivity for low-value continuity. Visual inspection of the case does not verify measurement accuracy, so accepting an instrument on that basis is insufficient.
-
3 Question 3 Order list Equipment Risk Assessment
A source inspection team is preparing the inspection plan for a new 13.8 kV indoor metal-clad switchgear lineup with a liquid-immersed step-down transformer supplied under a single purchase order. The vendor has not yet submitted its test procedures, and the schedule for factory acceptance testing is fixed two weeks after the inspection plan is due. Arrange the steps in the correct order the team must perform them.
Drag the steps into the correct order, or use the arrows.
- Develop the inspection and test plan with hold points, witness points and acceptance criteria for each high-risk characteristic
- Obtain vendor agreement to the inspection and test plan and confirm the witness schedule against the factory acceptance test date
- Conduct a risk assessment of each equipment item to rank the characteristics by consequence and likelihood of nonconformance
- Issue the approved plan to the vendor and to the inspection team, and set up the document control for inspection reports
- Review the purchase specification and the referenced codes to identify the critical equipment characteristics and applicable tests
Correct Answer:- Review the purchase specification and the referenced codes to identify the critical equipment characteristics and applicable tests
- Conduct a risk assessment of each equipment item to rank the characteristics by consequence and likelihood of nonconformance
- Develop the inspection and test plan with hold points, witness points and acceptance criteria for each high-risk characteristic
- Obtain vendor agreement to the inspection and test plan and confirm the witness schedule against the factory acceptance test date
- Issue the approved plan to the vendor and to the inspection team, and set up the document control for inspection reports
ExplanationThe source inspection project plan starts from the purchase requirements, since the specification defines what must be verified. Risk ranking must come next so that the depth of inspection can be proportioned to where nonconformance is most likely and most consequential. The inspection and test plan is then built around hold and witness points for those high-risk items, the vendor confirms the plan against the fixed test date, and only after agreement is the plan issued with documentation controls in place. Issuing the plan before vendor agreement or building test points before ranking risk would reverse the logic of the process.
-
4 Question 4 Drag and drop Switchgear (Low & Medium Voltage)
A source inspector is reviewing the design submittal for a 4160 V medium voltage switchgear lineup with draw-out breakers, a main-tie-main arrangement and metering on each incoming section. The inspector must confirm that each design element is verified against the correct requirement during the review. Match each requirement to the switchgear element that satisfies it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
Provide a reduced-level signal of primary voltage to the metering and protection relaysSupply low-voltage control circuits from the medium voltage bus through a fused step-down sourcePrevent both incoming main breakers from being closed at the same time when the tie breaker is closedPrevent a breaker from being racked into the connected position while the breaker is closedMechanical or electrical interlock between main and tie breakersBus compartment barrierCurrent transformer secondary shorting blockRacking interlock on the breaker compartmentVoltage transformers on the busControl power transformerCorrect Answer:- Prevent a breaker from being racked into the connected position while the breaker is closed → Racking interlock on the breaker compartment
- Prevent both incoming main breakers from being closed at the same time when the tie breaker is closed → Mechanical or electrical interlock between main and tie breakers
- Provide a reduced-level signal of primary voltage to the metering and protection relays → Voltage transformers on the bus
- Supply low-voltage control circuits from the medium voltage bus through a fused step-down source → Control power transformer
ExplanationThe racking interlock blocks movement of a closed breaker in and out of the connected position, which is a core switchgear safety feature. The main-tie-main arrangement relies on a main-tie-main interlock so that the two mains and the tie cannot all be closed in a way that paralleled sources would permit. Voltage transformers reduce primary voltage to measurable levels for metering and relaying, while the control power transformer derives the control supply from the bus. The shorting block and bus barrier are real features but do not match any of the four requirements listed.
-
5 Question 5 Dropdown Motor Control Centers (Low to Medium Voltage)
A source inspector is reviewing the main feeder cable entry compartment and ground bus on a 480 V motor control center delivered to a Class I Division 2 classified location. The MCC is fed through a top cable entry from an overhead cable tray, and the inspector must confirm the ground bus is continuous and sized correctly for the main feeder. Complete the inspection statement by selecting the correct value for each blank.
Choose the correct value for each blank.
The ground bus must run the full length of the MCC and be connected to the incoming ground at the of the main feeder compartment. The ground bus conductor cross-section must be selected from the equipment grounding conductor table in for the rating of the main overcurrent device, and each vertical section must be bonded to the ground bus with .Correct Answer:The ground bus must run the full length of the MCC and be connected to the incoming ground at the bottom incoming terminal of the main feeder compartment. The ground bus conductor cross-section must be selected from the equipment grounding conductor table in NFPA 70 Article 250 for the rating of the main overcurrent device, and each vertical section must be bonded to the ground bus with bolted copper connectors.
ExplanationEquipment grounding conductor sizing and bonding requirements for the MCC fall under NFPA 70 Article 250, which covers grounding and bonding of electrical systems and equipment. The ground bus is terminated to the incoming grounding electrode conductor at the bottom incoming terminal of the main feeder compartment, which provides the continuity path for the top-entry feeder arrangement. Vertical sections are bonded to the bus with bolted copper connectors so that the joints remain low-resistance and inspectable. Article 430 applies to motors, Article 501 to Class I locations and Article 725 to remote control circuits, so each of those is the wrong reference for the sizing and bonding question.
-
6 Question 6 Single choice Liquid-Immersed Transformers
A liquid-immersed 2500 kVA transformer is being inspected at the factory before shipment to an outdoor substation in a coastal area. The specification requires a sealed tank with a gas-space pressure and vacuum gauge, a pressure relief device and a conservator-free design. During the inspection, the inspector notes that the vendor has fitted a conservator, the liquid level indicator reads a level that is at the bottom of its range after filling, and the vendor states that the tank is ready for shipment with the gas-space nitrogen blanket already set. What is the inspector's BEST action?
Correct Answer: DExplanationThe specification calls for a conservator-free sealed tank, so a fitted conservator is a design deviation that the inspector must record rather than accept by rationalization. The liquid level at the bottom of its range and the stated nitrogen blanket also require verification against the filling and pressure requirements before release. Deferring the level correction to the field shifts a shop verification to site, which the source inspection is meant to prevent. Removing the pressure relief device would defeat a required safety feature and is not an acceptable way to set the blanket.
-
7 Question 7 Single choice Source Inspection Management Program
A source inspection program supports a multi-package project in which three vendors are building switchgear, motor control centers and skid-mounted equipment for the same offshore platform. Two weeks before the first witnessed factory acceptance test, the vendor for the switchgear reports a delay that will move its test date by ten days, while the motor control center vendor requests that its inspection window be brought forward to match. The project's inspection program requires a single consolidated schedule, and the inspection company has a limited number of inspectors available. What is the BEST first action for the program lead?
Correct Answer: BExplanationThe inspection program requires one consolidated schedule, so the first step is to update it with the revised vendor dates and check the impact on inspector availability and the critical path. Confirming with each vendor and the project team, and then issuing the revised schedule under document control, keeps the program aligned and documented. Moving an inspector between packages before confirming availability risks leaving a witnessed test uncovered. Cancelling a witness requirement would breach the inspection plan, and holding the motor control center without assessing its window does not address the coordination need.
-
8 Question 8 Single choice Switchgear (Low & Medium Voltage)
During a witnessed factory test of a 600 V low voltage switchgear lineup with a 3200 A main breaker and a 1600 A tie breaker, the inspector reviews the electric tie breaker interlock logic. The lineup is specified with a main-main-tie arrangement in which the tie breaker must only close when one main is open, and the transfer scheme must prevent paralleling of the two incoming sources. During the test the vendor demonstrates that closing the tie breaker with both mains closed is blocked, but the inspector finds that closing one main while the tie is closed is also blocked, and that the tie can be closed when one main has been racked out but is still in the cubicle with its primary contacts live. What is the BEST inspector action?
Correct Answer: DExplanationThe specified interlock must block tie closure whenever the mains are not in the correct open-tie-open condition, and the racked-out main case shows the logic is incomplete. A main that is racked out but still has primary contacts live must still be treated as a source for interlock purposes, so the tie must remain blocked. The inspector should document the deviation, require the vendor to correct and re-verify the interlock, and then repeat the test. A warning label does not replace a required interlock, and removing the interlock would eliminate a safety function the specification requires.
-
9 Question 9 Single choice Electrical Skid Mounted Equipment
An electrical skid is being assembled for a Class I Division 1 gas hazardous area on an offshore process unit. The skid houses a pressurized motor starter enclosure that is purged to maintain a positive internal pressure, and the vendor has supplied an inspection report indicating the purge was set at 0.3 inches of water column with a purge time of 4 minutes before power-up. The enclosure has a pressure switch that is fitted but its setpoint has not been verified. The project specification requires the purge to be verified with the pressure switch set to alarm and interlock the enclosure power when pressure is lost, and that the purge be completed before energization. What is the BEST action for the source inspector to take?
Correct Answer: CExplanationA purged enclosure must demonstrate its pressure and purge timing, and the pressure switch must function as a loss-of-pressure alarm and power interlock, so the inspector must witness each of these rather than rely on a vendor report. Confirming that purge completes before energization is part of the specified sequence and needs direct observation. Deferring the setpoint confirmation to after delivery moves a required verification off the shop floor. Re-rating the enclosure to Division 2 changes the design basis and is not a substitute for the stated verification.
-
10 Question 10 Single choice Switchgear (Low & Medium Voltage)
A source inspector is reviewing the current transformer and metering arrangement for a 13.8 kV metal-clad switchgear feeder section. The specification requires the protection and metering circuits to be connected so that CT secondaries are never open-circuited when the primary is energized, and that the ratio and polarity of each CT are verified before the metering is accepted. During the review the inspector notices that the CT secondary terminal block for one feeder has no shorting block, the test switch is wired in series with the CT secondary, and the vendor plans to use the test switch to disconnect the meter during the factory test while the feeder is energized from the test source. What is the BEST inspector action?
Correct Answer: DExplanationAn open-circuit CT secondary under energized primary current produces dangerously high voltage and can damage the transformer, so the design must include a shorting block or equivalent secondary short before energized testing. Withholding the energized metering test until the secondary can be safely shorted and the ratio and polarity are verified meets both stated requirements. Relying on the test switch or on the relay does not guarantee the secondary is shorted when the meter is disconnected. Grounding the secondary at a single terminal does not prevent the open-circuit hazard and is not a substitute for a short.
-
11 Question 11 Drag and drop Source Inspection Performance
A source inspector is preparing the report for a motor control center inspection in which the vendor's installed wiring deviated from the approved drawings in several places, a witnessed functional test was performed out of sequence, and the inspector observed a technician working on energized equipment without a permit. The report must follow report writing and nonconformance practice so that each finding is clearly recorded and actioned. Match each finding to the report treatment that meets it.
Drag each item onto its matching target. On a phone: tap an item, then tap a target.
A technician working on energized equipment without a required energy isolation permitControl wiring routed differently from the approved drawing but still meeting the same functional and separation requirementsA component that fails the specified insulation resistance acceptance value during the witnessed testStop the activity, report it immediately as a safety concern and inform the vendor's safety representativeRecord as a minor observation with no required follow-upRecord as a nonconformance requiring correction and retest before acceptanceRecord as a documented deviation with a request for drawing revisionAccept as a conditional release pending the next inspection visitCorrect Answer:- Control wiring routed differently from the approved drawing but still meeting the same functional and separation requirements → Record as a documented deviation with a request for drawing revision
- A component that fails the specified insulation resistance acceptance value during the witnessed test → Record as a nonconformance requiring correction and retest before acceptance
- A technician working on energized equipment without a required energy isolation permit → Stop the activity, report it immediately as a safety concern and inform the vendor's safety representative
ExplanationA deviation that still meets the functional and separation requirements is recorded as a documented deviation with a drawing revision request, so the as-built record is corrected. A failed insulation resistance value is a nonconformance that must be corrected and retested before acceptance. The energized work without permit is a safety matter that requires an immediate stop and notification, which takes priority over report writing. The minor observation and conditional release targets do not fit the stated findings, since the first deviation changes the record and the second fails a specified value.
-
12 Question 12 Single choice Terms and Definitions
During a source inspection kickoff meeting, the vendor's project manager states that the purchaser's inspector may 'accept' the equipment at the factory, after which the purchaser cannot reject it for shop-verifiable defects found on delivery. The inspection plan defines acceptance in terms of the inspector's release of a witnessed test, while the purchase order defines acceptance as final purchaser approval after receipt. The project quality manager must align the parties before the first inspection. What is the BEST action to resolve the terminology conflict?
Correct Answer: CExplanationThe inspection plan and purchase order must use consistent defined terms, because the difference between shop inspection release and final purchaser acceptance determines who carries the rejection risk after delivery. Confirming the definitions across the plan, the purchase order and the report, and recording them in the project documents, aligns the parties on a single meaning. Adopting the vendor's definition would transfer the purchaser's rights without a contractual basis. Dropping the term or defining it test by test would leave the conflict unresolved in the controlling documents.
These are 12 of the 110 questions in the full API-SIEE pack.
Get All 110 QuestionsGet all 110 questions & answers
Full access options for API API-SIEE
Self-study
PDF Version
- 110 actual exam questions
- Compatible with all devices
- Printable PDF format
- No download limits
- 90 days free updates
- 24/7 customer support
Best value
Bundle Pack
- Discounted PDF + online access
- 110 actual exam questions
- Both PDF and online practice test
- Free 90 days updates
- No download or practice limits
- 24/7 customer support
Exam simulation
Online Practice Test
- 110 actual exam questions
- Actual exam environment
- 90 days free updates
- Browser-based software
- 24/7 customer support
100% Money Back Guarantee
Your success comes first
At DumpsProvider, we give you a 100% money back guarantee on all of our exam dumps. For us, your success is the #1 priority and we are more than confident that our exam material will help you pass the API-SIEE Exam (Source Inspector Electrical Equipment) on your very first attempt.
In a rare case, if you fail your exam, we will refund your amount without asking a single question.